Wichita Matter

As previously disclosed, the U.S. District Court for the District of Kansas issued a grand jury subpoena in 2011 to Plastic Fabricating Company, Inc. (“PlasticFab”), an indirect wholly owned subsidiary of the Company now known as Kaman Composites - Wichita, Inc., regarding a government investigation of record keeping associated with the manufacture of certain composite parts at PlasticFab's facility located in Wichita, Kansas. On October 21, 2014, the U.S. Attorney's Office for the District of Kansas and PlasticFab entered into a civil settlement agreement, pursuant to which PlasticFab, without admitting any wrongdoing, agreed to pay $0.5 million, all of which was previously accrued. The U.S. Attorney's Office for the District of Kansas has also informed PlasticFab that it is closing its files and will conduct no further investigation relating to this matter.

Other Matters

Revenue Sharing Agreement with the Commonwealth of Australia

Pursuant to the terms of the revenue sharing agreement with the Commonwealth of Australia, the Company was required to share proceeds from the resale of the SH-2G(I) inventory with them. During the third quarter of 2014, the Company settled the revenue sharing agreement with the Commonwealth of Australia and made a final payment of $5.3 million. As a result, no further revenue sharing payments will be due to the Commonwealth of Australia as the Company sells the remainder of the SH-2G(I) inventory. Over the course of the revenue sharing agreement, net of the benefits derived from our hedging arrangements, the Company paid approximately $32.1 million to the Commonwealth of Australia.

Moosup

During the third quarter of 2014, the Company sold its former manufacturing facility in Moosup, Connecticut to TD Development, LLC. In connection with the sale, the Company will contribute $4.0 million in cash to an escrow account over a four-year period to fund environmental remediation work that is expected to be performed on the site. The purchase and sale agreement provides that TD Development is responsible for any costs in excess of the $4.0 million contributed by the Company. The first of these payments, $0.8 million, was made at the closing of the transaction. The Company currently has $3.2 million accrued that represents the remainder due to TD Development.

New Hartford

In connection with the sale of the Company’s Music segment in 2007, the Company assumed responsibility for meeting certain requirements of the Connecticut Transfer Act (the “Transfer Act”) that applied to the transfer of the New Hartford, Connecticut, facility leased by that segment for guitar manufacturing purposes (“Ovation”). Under the Transfer Act, those responsibilities essentially consist of assessing the site's environmental conditions and remediating environmental impairments, if any, caused by Ovation's operations prior to the sale. The site is a multi-tenant industrial park, in which Ovation and other unrelated entities lease space. The environmental assessment process, which began in 2008, has been completed.

The Company's estimate of its portion of the cost to assess the environmental conditions and remediate this site is $2.2 million, unchanged from the previously reported estimate, all of which has been accrued. The total amount paid to date in connection with these environmental remediation activities is $0.5 million. A portion ($0.6 million) of the accrual related to this property is included in other accruals and payables and the balance is included in other long-term liabilities. The remaining balance of the accrual reflects the total anticipated cost of completing these environmental remediation activities. Although it is reasonably possible that additional costs will be paid in connection with the resolution of this matter, the Company is unable to estimate the amount of such additional costs, if any, at this time.

11. COMMITMENTS AND CONTINGENCIES (CONTINUED)

Other Matters - continued

Bloomfield

In connection with the Company’s 2008 purchase of the portion of the Bloomfield campus that a Company subsidiary had leased from the Naval Air Systems Command (NAVAIR), the Company assumed responsibility for environmental remediation at the facility as may be required under the Transfer Act and continues the effort to define the scope of the remediation that will be required by the Connecticut Department of Energy & Environmental Protection. The assumed environmental liability of $10.3 million, all of which has been accrued, was determined by taking the undiscounted estimated remediation liability of $20.8 million and discounting it at a rate of 8%. This remediation process will take many years to complete. The total amount paid to date in connection with these environmental remediation activities is $8.5 million. At September 26, 2014, the Company has $5.8 million accrued for this environmental matter. A portion ($1.6 million) of the accrual related to this property is included in other accruals and payables, and the balance ($4.2 million) is included in other long-term liabilities. Although it is reasonably possible that additional costs will be paid in connection with the resolution of this matter, the Company is unable to estimate the amount of such additional costs, if any, at this time.

United Kingdom

In connection with the purchase of the Company's U.K. composites business operations, the Company accrued £1.6 million for environmental compliance at the acquired facilities. The remaining balance of the accrual at September 26, 2014, was £0.3 million, with £1.1 million having been paid to date in connection with these environmental remediation activities and £0.2 million released to income in 2011. The U.S. dollar equivalent of the remaining environmental compliance liability as of September 26, 2014, is $0.5 million, which is included in other accruals and payables. The Company continues to assess the work that may be required, which may result in a change to this accrual. Although it is reasonably possible that additional costs will be paid in connection with the resolution of this matter, the Company is unable to estimate the amount of such additional costs, if any, at this time.

Other Environmental Matters

The Company has been notified by the Environmental Protection Agency that it is a potentially responsible party ("PRP") at a Superfund Site. At September 26, 2014, the Company had no amount accrued for this matter, as it is unable to estimate the amount of costs, if any, that might be incurred in connection with the remediation of this site. In making this determination, the Company considered all available information related to the site; specifically, the continued identification of PRPs and the inability to determine the proportion of total responsibility attributable to each PRP at this time. As more information is received, the Company will reassess its ability to estimate its portion of the cost for remediation, taking into consideration the financial resources of other PRPs involved in the site, their proportionate share of the total responsibility for waste at the site, the existence of insurance and the financial viability of the insurer.