Jointly Owned Electric Utility Plant [Line Items]  
Electric Plant $ 2,663
Accumulated Provision for Depreciation 886
Construction Work in Progress 42
IPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Electric Plant 1,024
Accumulated Provision for Depreciation 445
Construction Work in Progress 27
WPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Electric Plant 1,639
Accumulated Provision for Depreciation 441
Construction Work in Progress $ 15
Ottumwa Unit 1 [Member] | IPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 48.00%
Electric Plant $ 612
Accumulated Provision for Depreciation 241
Construction Work in Progress $ 17
George Neal Unit 4 [Member] | IPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 25.70%
Electric Plant $ 193
Accumulated Provision for Depreciation 103
Construction Work in Progress $ 4
George Neal Unit 3 [Member] | IPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 28.00%
Electric Plant $ 176
Accumulated Provision for Depreciation 80
Construction Work in Progress $ 6
Louisa Unit 1 [Member] | IPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 4.00%
Electric Plant $ 43
Accumulated Provision for Depreciation 21
Construction Work in Progress $ 0
Columbia Units 1-2 [Member] | WPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 53.50%
Electric Plant $ 805
Accumulated Provision for Depreciation 338
Construction Work in Progress $ 13
West Riverside [Member] | WPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 91.00%
Electric Plant $ 716
Accumulated Provision for Depreciation 53
Construction Work in Progress $ 2
Forward Wind Energy Center [Member] | WPL [Member]  
Jointly Owned Electric Utility Plant [Line Items]  
Ownership Interest % 42.60%
Electric Plant $ 118
Accumulated Provision for Depreciation 50
Construction Work in Progress $ 0