Leases

 

On May 1, 2019, the Company completed the expansion of new equipment for the Company’s information technology infrastructure, buildout of its corporate headquarters, and expansion of its collocation data center, which it completed using approximately $1,269,000 (the “Lease Amount”) of funds provided by the Bank to finance equipment and services related to the Company’s expansion and relocation pursuant to the Lease Agreement, originally entered into by and between the Company and the Bank on January 9, 2019. Pursuant to the Lease Agreement, as of May 1, 2019, the Bank is now leasing back the property and equipment purchased by the Company. Pursuant to the Lease Agreement, commencing May 1, 2019, the initial term of the lease shall be 48 months, the Lease Amount shall accrue interest at a rate of 5.0% per annum, and the Company shall be required to make monthly rental payments in the amount of approximately $29,097 per month.

 

On June 21, 2018 the Company entered into an office lease at 5252 South Commerce Drive Suite D292, Murray, Utah 84107, providing for the lease of approximately 9,800 square feet for a period of three years, commencing on March 1, 2019. The monthly rent is $10,200.

 

Minimum future payments, including principal and interest, under the non-cancelable capital leases are as follows:

 

Year ending June 30:      
2020   $ 471,564  
2021   $ 471,564  
2022   $ 430,764  
2023   $ 290,970  
2024   $    

 

From time to time the Company may enter into or exit from diminutive operating lease agreements for equipment such as copiers, temporary back up servers, etc. These leases are not of a material amount and thus will not in the aggregate have a material adverse effect on our business, financial condition, results of operation or liquidity.