Contingencies
CONTINGENCIES
 
IDACORP and Idaho Power have in the past and expect in the future to become involved in various claims, controversies, disputes, and other contingent matters, including the items described in this Note 9. Some of these claims, controversies, disputes, and other contingent matters involve litigation and regulatory or other contested proceedings. The ultimate resolution and outcome of litigation and regulatory proceedings is inherently difficult to determine, particularly where (a) the remedies or penalties sought are indeterminate, (b) the proceedings are in the early stages or the substantive issues have not been well developed, or (c) the matters involve complex or novel legal theories or a large number of parties. In accordance with applicable accounting guidance, IDACORP and Idaho Power, as applicable, establish an accrual for legal proceedings when those matters proceed to a stage where they present loss contingencies that are both probable and reasonably estimable. In such cases, there may be a possible exposure to loss in excess of any amounts accrued. IDACORP and Idaho Power monitor those matters for developments that could affect the likelihood of a loss and the accrued amount, if any, and adjust the amount as appropriate. If the loss contingency at issue is not both probable and reasonably estimable, IDACORP and Idaho Power do not establish an accrual and the matter will continue to be monitored for any developments that would make the loss contingency both probable and reasonably estimable. As of the date of this report, IDACORP's and Idaho Power's accruals for loss contingencies are not material to their financial statements as a whole; however, future accruals could be material in a given period. IDACORP's and Idaho Power's determination is based on currently available information, and estimates presented in financial statements and other financial disclosures involve significant judgment and may be subject to significant uncertainty. For matters that affect Idaho Power’s operations, Idaho Power intends to seek, to the extent permissible and appropriate, recovery through the ratemaking process of costs incurred.

Western Energy Proceedings
 
High prices for electricity, energy shortages, and blackouts in California and in the western wholesale markets during 2000 and 2001 caused numerous purchasers of electricity in those markets to initiate proceedings to consider requiring refunds and other forms of disgorgement from energy sellers. Some of these proceedings remain pending before the FERC or are on appeal to the United States Court of Appeals for the Ninth Circuit, and thus there remains some uncertainty about the ultimate outcome of the proceedings. Idaho Power and IESCo (as successor to IDACORP Energy L.P.) believe that the current state of the FERC's orders, if maintained, and the settlement releases they have obtained, will restrict potential claims that might result from the pending proceedings. As a result, IDACORP and Idaho Power predict that these matters will not have a material adverse effect on their respective results of operations or financial condition. However, if unanticipated orders are issued by the FERC or by the Ninth Circuit Court of Appeals or other courts, exposure to indirect claims in the proceedings could exist. These indirect claims would consist of so-called "ripple claims," which involve potential claims for refunds in the Pacific Northwest markets from an upstream seller of power based on a finding that its downstream buyer was liable for refunds as a seller of power during the relevant period. Given the speculative nature of ripple claims and in light of Idaho Power's and IESCo's participation in the market as both buyers and sellers of energy, Idaho Power and IESCo are unable to estimate the possible loss or range of loss that could result from the proceedings and have no amount accrued relating to the proceedings. To the extent the availability of any ripple claims materializes, Idaho Power and IESCo will continue to vigorously defend their positions in the proceedings.

Hoku Corporation Bankruptcy Claims

On June 26, 2015, the trustee in the Hoku Corporation chapter 7 bankruptcy case (In Re: Hoku Corporation, United States Bankruptcy Court, District of Idaho, Case No. 13-40838 JDP) filed a complaint against Idaho Power, alleging that specified payments made by Hoku Corporation to Idaho Power in the six years prior to Hoku Corporation's bankruptcy filing in July 2013 should be recoverable by the trustee as constructive fraudulent transfers. Hoku Corporation was the parent entity of Hoku Materials, Inc., with which Idaho Power had an electric service agreement approved by the IPUC in March 2009. Under the electric service agreement, Idaho Power agreed to provide electric service to a polysilicon production facility under construction by Hoku Materials in the state of Idaho. Idaho Power also had agreements with Hoku Materials pertaining to the design and construction of apparatus for the provision of electric service to the polysilicon plant. The trustee's complaint against Idaho Power includes alternative causes of action for constructive fraudulent transfer under the federal bankruptcy code, Idaho law, and federal law, with requests for recovery from Idaho Power in amounts up to approximately $36 million. The complaint alleges that the payments made by Hoku Corporation to Idaho Power are subject to recovery by the trustee on the basis that Hoku Corporation was insolvent at the time of the payments and did not have any legal or equitable title in the polysilicon plant or liability for Hoku Materials' debts, and thus did not receive reasonably equivalent value for the payments it made for or on behalf of Hoku Materials.

As of the date of this report, the proceedings are in preliminary stages and it is not possible to determine Idaho Power's potential liability, if any, or to reasonably estimate a possible loss or range of possible loss, if any, within the trustee's alternative prayers for relief. Idaho Power intends to vigorously defend against the claims.

Other Proceedings

IDACORP and Idaho Power are parties to legal claims and legal and regulatory actions and proceedings in the ordinary course of business that are in addition to those discussed above and, as noted above, record an accrual for associated loss contingencies when they are probable and reasonably estimable. As of the date of this report the companies believe that resolution of those matters will not have a material adverse effect on their respective consolidated financial statements. Idaho Power is also actively monitoring various pending environmental regulations that may have a significant impact on its future operations. Given uncertainties regarding the outcome, timing, and compliance plans for these environmental matters, Idaho Power is unable to estimate the financial impact of these regulations. However, Idaho Power does believe that future capital investment for infrastructure and modifications to its electric generating facilities could be significant to comply with these regulations.