XML 53 R10.htm IDEA: XBRL DOCUMENT v3.21.2
Rate Matters
9 Months Ended
Sep. 30, 2021
Rate Matters RATE MATTERS
The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in the 2020 Annual Report, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2020 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2021 and updates the 2020 Annual Report.

Coal-Fired Generation Plants (Applies to AEP, PSO and SWEPCo)

Compliance with extensive environmental regulations requires significant capital investment in environmental monitoring, installation of pollution control equipment, emission fees, disposal costs and permits. Management continuously evaluates cost estimates of complying with these regulations which has resulted in, and in the future may result in, a decision to retire coal-fired generating facilities earlier than their currently estimated useful lives.

Management is seeking or will seek regulatory recovery, as necessary, for any net book value remaining when the plants are retired. To the extent the net book value of these generation assets are not deemed recoverable, it could materially reduce future net income and cash flows and impact financial condition.

Regulated Generating Units that have been Retired

PSO

The Oklaunion Power Station was retired in September 2020 and sold to a nonaffiliated third-party in October 2020. As of September 30, 2021, PSO has a regulatory asset for accelerated depreciation pending approval recorded on its balance sheet of $33 million. PSO has requested recovery of the Oklaunion Power Station as part of its 2021 Oklahoma base rate case. See “2021 Oklahoma Base Rate Case” section below for additional information.

SWEPCo

In April 2016, Welsh Plant, Unit 2 was retired. As part of the 2016 Texas Base Rate Case, SWEPCo received approval from the PUCT to recover the Texas jurisdictional share of Welsh Plant, Unit 2. See “2016 Texas Base Rate Case” section below for additional information. As part of the 2019 Arkansas Base Rate Case, SWEPCo received approval from the APSC to recover the Arkansas jurisdictional share of Welsh Plant, Unit 2. In December 2020, SWEPCo filed a request with the LPSC to recover the Louisiana jurisdictional share of Welsh Plant, Unit 2. See “2020 Louisiana Base Rate Case” section below for additional information. As of September 30, 2021, SWEPCo has a regulatory asset for plant retirement costs pending approval recorded on its balance sheet of $35 million related to the Louisiana jurisdictional share of Welsh Plant, Unit 2.

Regulated Generating Units to be Retired

PSO

In 2014, PSO received final approval from the Federal EPA to close Northeastern Plant, Unit 3, in 2026. The plant was originally scheduled to close in 2040. As a result of the early retirement date, PSO revised the useful life of Northeastern Plant, Unit 3, to the projected retirement date of 2026 and the incremental depreciation is being deferred as a regulatory asset. PSO has requested recovery of Northeastern Plant, Unit 3 as part of its 2021 Oklahoma base rate case. See “2021 Oklahoma Base Rate Case” section below for additional information.
SWEPCo

In January 2020, as part of the 2019 Arkansas Base Rate Case, management announced that the Dolet Hills Power Station was probable of abandonment and was to be retired by December 2026. As a result of the announcement, SWEPCo began recording a regulatory asset for accelerated depreciation. In March 2020, management announced plans to retire the plant in 2021.

In November 2020, management announced plans to retire Pirkey Power Plant in 2023 and that it will cease using coal at the Welsh Plant in 2028. As a result of the announcement, SWEPCo began recording a regulatory asset for accelerated depreciation.

The table below summarizes the net book value including CWIP, before cost of removal and materials and supplies, as of September 30, 2021, of generating facilities planned for early retirement:
PlantNet Book ValueAccelerated Depreciation Regulatory AssetCost of Removal
Regulatory Liability
Projected
Retirement Date
Current Authorized
Recovery Period
Annual
Depreciation (a)
(dollars in millions)
Northeastern Plant, Unit 3$175.1 $123.6 $20.0 (b)2026(c)$14.9 
Dolet Hills Power Station
13.0 126.8 24.4 2021(d)7.8 
Pirkey Power Plant135.4 68.0 39.2 2023(e)13.5 
Welsh Plant, Units 1 and 3493.7 35.6 58.2 (f)2028(g)33.1 
(a)Represents the amount of annual depreciation that has been collected from customers over the prior 12-month period.
(b)Includes Northeastern Plant, Unit 4, which was retired in 2016. Removal of Northeastern Plant, Unit 4, will be performed with Northeastern Plant, Unit 3, after retirement.
(c)Northeastern Plant, Unit 3 is currently being recovered through 2040.
(d)Dolet Hills Power Station is currently being recovered through 2026 in the Louisiana jurisdiction and through 2046 in the Arkansas and Texas jurisdictions.
(e)Pirkey Power Plant is currently being recovered through 2025 in the Louisiana jurisdiction and through 2045 in the Arkansas and Texas jurisdictions.
(f)Includes Welsh Plant, Unit 2, which was retired in 2016. Removal of Welsh Plant, Unit 2, will be performed with Welsh Plant, Units 1 and 3, after retirement.
(g)Unit 1 is being recovered through 2027 in the Louisiana jurisdiction and through 2037 in the Arkansas and Texas jurisdictions. Unit 3 is being recovered through 2032 in the Louisiana jurisdiction and through 2042 in the Arkansas and Texas jurisdictions.

Dolet Hills Power Station and Related Fuel Operations (Applies to AEP and SWEPCo)

DHLC provides 100% of the fuel supply to Dolet Hills Power Station. During the second quarter of 2019, the Dolet Hills Power Station initiated a seasonal operating schedule. In 2020, management of SWEPCo and CLECO determined DHLC would not proceed developing additional Oxbow Lignite Company (Oxbow) mining areas for future lignite extraction and ceased extraction of lignite at the mine in May 2020. Based on these actions, management revised the estimated useful life of DHLC’s and Oxbow’s assets to coincide with the date at which extraction was discontinued in the second quarter of 2020 and the date at which delivery of lignite ceased in October 2021. In addition, management also revised the useful life of the Dolet Hills Power Station to 2021 based on the remaining estimated fuel supply available for continued seasonal operation. In April 2020, SWEPCo and CLECO jointly filed a notification letter to the LPSC providing notice of the cessation of lignite mining.

The Dolet Hills Power Station non-fuel costs are recoverable by SWEPCo through base rates. As of September 30, 2021, SWEPCo’s share of the net investment in the Dolet Hills Power Station is $146 million, including CWIP and materials and supplies, before cost of removal.

Fuel costs incurred by the Dolet Hills Power Station are recoverable by SWEPCo through active fuel clauses. Under the fuel agreements, SWEPCo’s fuel inventory and unbilled fuel costs from mining related activities were $44 million as of September 30, 2021. Also, as of September 30, 2021, SWEPCo had a net under-recovered fuel balance of $39 million, excluding impacts of the February 2021 severe winter weather event, which includes fuel consumed at the Dolet Hills Power Station. Additional operational, reclamation and other land-related costs incurred by DHLC and Oxbow will be billed to SWEPCo and included in future fuel clauses.
In June 2020, SWEPCo filed a fuel reconciliation with the PUCT for its retail operations in Texas, including Dolet Hills, for the reconciliation period of March 1, 2017 to December 31, 2019. See “2020 Texas Fuel Reconciliation” section below for additional information.

In March 2021, the LPSC issued an order allowing SWEPCo to recover up to $20 million of fuel costs in 2021 and defer approximately $30 million of additional costs with a recovery period to be determined at a later date.

In March 2021, the APSC approved fuel rates that provide recovery of the Arkansas share of the 2021 Dolet Hills Power Station fuel costs over five years through the existing fuel clause.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Pirkey Power Plant and Related Fuel Operations (Applies to AEP and SWEPCo)

In 2020, management announced plans to retire the Pirkey Power Plant in 2023. The Pirkey Power Plant non-fuel costs are recoverable by SWEPCo through base rates and fuel costs are recovered through active fuel clauses. As of September 30, 2021, SWEPCo’s share of the net investment in the Pirkey Power Plant is $203 million, including CWIP, before cost of removal. Sabine is a mining operator providing mining services to the Pirkey Power Plant. Under the provisions of the mining agreement, SWEPCo is required to pay, as part of the cost of lignite delivered, an amount equal to mining costs plus a management fee. SWEPCo expects fuel deliveries, including billings of all fixed and operating costs, from Sabine to cease during the first quarter of 2023. Under the fuel agreements, SWEPCo’s fuel inventory and unbilled fuel costs from mining related activities were $108 million as of September 30, 2021. Also, as of September 30, 2021, SWEPCo had a net under-recovered fuel balance of $39 million, excluding impacts of the February 2021 severe winter weather event, which includes fuel consumed at the Pirkey Power Plant. Additional operational, reclamation and other land-related costs incurred by Sabine will be billed to SWEPCo and included in future fuel clauses. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition..

2020 Texas Fuel Reconciliation (Applies to AEP and SWEPCo)

In June 2020, SWEPCo filed a fuel reconciliation with the PUCT for its retail operations in Texas for the reconciliation period of March 1, 2017 to December 31, 2019. The fuel reconciliation included total fuel costs of $1.7 billion ($616 million of which is related to the Texas jurisdiction). In January 2021, various parties filed testimony recommending fuel cost disallowances totaling $125 million relating to the Texas jurisdiction. Also in January 2021, SWEPCo filed rebuttal testimony disputing the recommended disallowances. In February 2021, SWEPCo and various parties reached a settlement in principle which resulted in a $10 million reduction in recoverable fuel costs for the reconciliation period, which was recognized in SWEPCo’s 2020 financial statements. In June 2021, the settlement was filed and is currently awaiting approval from the PUCT. If additional costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.
Regulatory Assets Pending Final Regulatory Approval (Applies to all Registrants except AEPTCo)
AEP
September 30,December 31,
20212020
 Noncurrent Regulatory Assets(in millions)
  
Regulatory Assets Currently Earning a Return  
Unrecovered Winter Storm Fuel Costs (a)$1,106.3 $— 
Dolet Hills Power Station Accelerated Depreciation126.8 71.2 
Pirkey Power Plant Accelerated Depreciation68.0 12.2 
Kentucky Deferred Purchase Power Expenses45.9 41.3 
Welsh Plant, Units 1 and 3 Accelerated Depreciation35.6 3.6 
Plant Retirement Costs – Unrecovered Plant, Louisiana35.2 35.2 
Oklaunion Power Station Accelerated Depreciation33.0 34.4 
Dolet Hills Power Station Fuel Costs - Louisiana20.3 — 
Other Regulatory Assets Pending Final Regulatory Approval25.5 22.8 
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs325.8 134.2 
Plant Retirement Costs – Asset Retirement Obligation Costs25.9 25.9 
COVID-1914.0 24.9 
Asset Retirement Obligation - Louisiana10.0 9.1 
Other Regulatory Assets Pending Final Regulatory Approval32.6 27.4 
Total Regulatory Assets Pending Final Regulatory Approval$1,904.9 $442.2 

(a)PSO and SWEPCo have active fuel clauses that allow for the recovery of prudently incurred fuel and purchased power expenses. However, the recovery of these costs from customers may be extended over longer than usual time periods to mitigate the impact on customer bills. See “Impacts of Severe Winter Weather” section below for additional information.

AEP Texas
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
Regulatory Assets Currently Earning a Return
Advanced Metering System$16.6 $16.3 
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs22.7 0.8 
Vegetation Management Program5.2 3.8 
Texas Retail Electric Provider Bad Debt Expense4.1 — 
COVID-193.9 10.5 
Other Regulatory Assets Pending Final Regulatory Approval5.3 1.5 
Total Regulatory Assets Pending Final Regulatory Approval$57.8 $32.9 
APCo
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
Regulatory Assets Currently Earning a Return
COVID-19 – Virginia$6.6 $3.7 
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs59.8 3.4 
Plant Retirement Costs – Asset Retirement Obligation Costs25.9 25.9 
COVID-19 – West Virginia0.4 1.5 
Environmental Expense Deferral - Virginia— 9.3 
Other Regulatory Assets Pending Final Regulatory Approval1.2 — 
Total Regulatory Assets Pending Final Regulatory Approval$93.9 $43.8 

 I&M
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
  
Regulatory Assets Currently Earning a Return
Other Regulatory Assets Pending Final Regulatory Approval$— $0.5 
Regulatory Assets Currently Not Earning a Return  
COVID-191.7 3.8 
Other Regulatory Assets Pending Final Regulatory Approval1.7 — 
Total Regulatory Assets Pending Final Regulatory Approval$3.4 $4.3 

 OPCo
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
  
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs$5.5 $4.0 
COVID-191.9 4.4 
Other Regulatory Assets Pending Final Regulatory Approval0.1 — 
Total Regulatory Assets Pending Final Regulatory Approval$7.5 $8.4 

 PSO
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
  
Regulatory Assets Currently Earning a Return  
Unrecovered Winter Storm Fuel Costs (a)$673.2 $— 
Oklaunion Power Station Accelerated Depreciation33.0 34.4 
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs29.3 15.8 
Other Regulatory Assets Pending Final Regulatory Approval0.9 0.3 
Total Regulatory Assets Pending Final Regulatory Approval$736.4 $50.5 

(a)PSO has an active fuel clause that allows for the recovery of prudently incurred fuel and purchased power expenses. However, the recovery of these costs from customers may be extended over longer than usual time periods to mitigate the impact on customer bills. See “Impacts of Severe Winter Weather” section below for additional information.
SWEPCo
September 30,December 31,
20212020
Noncurrent Regulatory Assets(in millions)
  
Regulatory Assets Currently Earning a Return  
Unrecovered Winter Storm Fuel Costs (a)$433.1 $— 
Dolet Hills Power Station Accelerated Depreciation126.8 71.2 
Pirkey Power Plant Accelerated Depreciation68.0 12.2 
Welsh Plant, Units 1 and 3 Accelerated Depreciation35.6 3.6 
Plant Retirement Costs Unrecovered Plant, Louisiana
35.2 35.2 
Dolet Hills Power Station Fuel Costs- Louisiana20.3 — 
Other Regulatory Assets Pending Final Regulatory Approval2.3 2.2 
Regulatory Assets Currently Not Earning a Return  
Storm-Related Costs155.4 99.3 
Asset Retirement Obligation - Louisiana10.0 9.1 
Other Regulatory Assets Pending Final Regulatory Approval19.3 14.5 
Total Regulatory Assets Pending Final Regulatory Approval$906.0 $247.3 

(a)SWEPCo has an active fuel clause that allows for the recovery of prudently incurred fuel and purchased power expenses. However, the recovery of these costs from customers may be extended over longer than usual time periods to mitigate the impact on customer bills. See “Impacts of Severe Winter Weather” section below for additional information.

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

Impacts of Severe Winter Weather

Storm Restoration Costs (Applies to AEP, APCo and SWEPCo)

In February 2021, severe winter weather impacted the service territories of APCo, KPCo and SWEPCo resulting in power outages and extensive damage to transmission and distribution infrastructures. As a result, incremental restoration expenses have been deferred related to the severe winter weather. The storm restoration costs are as follows:

September 30, 2021
CompanyJurisdictionCapitalO&MRegulatory AssetTotal
(in millions)
APCoVirginia$8.1 $2.2 $6.6 $16.9 
APCoWest Virginia23.5 — 47.0 70.5 
SWEPCoLouisiana6.0 — 45.4 51.4 
KPCoKentucky29.0 5.0 42.6 76.6 
Total$66.6 $7.2 $141.6 $215.4 

The amounts in the table above represents costs as of September 30, 2021. In March 2021, the LPSC approved the deferral of incremental other operation and maintenance storm restoration expenses related to the Louisiana jurisdiction for SWEPCo. Similarly, in April 2021, the KPSC approved deferral of KPCo’s incremental other operation and maintenance storm restoration expenses. KPCo intends to seek recovery of these incremental storm restoration costs in their next base rate case while APCo is expected to seek recovery in separate filings. In October 2021, SWEPCo requested recovery of these storm costs, in addition to storm costs from Hurricanes Delta and Laura, in a filing with the LPSC. As part of the filing, SWEPCo requested recovery of the carrying charges on the regulatory asset at a weighted average cost of capital through a rider beginning in January 2022. If any of the
restoration costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

February 2021 Severe Winter Weather Impacts in SPP (Applies to AEP, PSO and SWEPCo)

The February 2021 severe winter weather also had a significant impact in SPP resulting in the declaration of Energy Emergency Alert Levels 2 and 3 for the first time in SPP’s history. The winter storm increased the demand for natural gas and restricted the available natural gas supply resulting in significantly increased market prices for natural gas power plants to meet reliability needs for the SPP electric system. From February 9, 2021, to February 20, 2021, PSO’s and SWEPCo’s natural gas expenses and purchases of electricity still to be recovered from customers are as follows:
PSOSWEPCoTotal
(in millions)
Retail Customers (a)$673.2 $433.1 (b)$1,106.3 
Wholesale Customers— 55.8 55.8 
Total$673.2 $488.9 $1,162.1 

(a)These costs were deferred as regulatory assets as of September 30, 2021.
(b)SWEPCo’s balance consists of $107 million, $151 million and $175 million related to the Arkansas, Louisiana and Texas jurisdictions, respectively.

Retail Customers

PSO and SWEPCo have active fuel clauses that allow for the recovery of prudently incurred fuel and purchased power expenses. Given the significance of these costs, PSO and SWEPCo expect the costs to be subject to prudency reviews. Management believes these costs are probable of future recovery, but expects the recovery period to be extended to mitigate the impact on customer bills.

In March 2021, the APSC issued an order authorizing recovery of the Arkansas jurisdictional share of the retail customer fuel costs over five years, with the appropriate carrying charge to be determined at a later date. Accordingly, in April 2021, SWEPCo began recovery of its Arkansas jurisdictional share of these fuel costs, which are subject to true-up by the APSC. SWEPCo is recovering these fuel costs at an interim carrying charge of 0.8%. Also in April 2021, SWEPCo filed testimony supporting a five-year recovery with a carrying charge of 6.05% which has been supported by APSC staff. Various other parties have recommended recovery periods ranging from 5-20 years with a carrying charge of 1.65%. The APSC ordered more testimony regarding the option of utilizing securitization to recover the fuel costs. SWEPCo is awaiting a decision from the APSC. The prudency of these fuel costs is expected to be addressed in a separate proceeding.

In March 2021, the LPSC approved a special order granting a temporary modification to the FAC that allows SWEPCo to recover the Louisiana jurisdictional share of these retail fuel costs over a longer period than what the FAC traditionally allows. In April 2021, SWEPCo began recovery of its Louisiana jurisdictional share of these fuel costs based on a five year recovery period. SWEPCo is recovering these fuel costs at an interim carrying charge of 3.25%. SWEPCo will work with the LPSC to finalize the actual recovery period and determine the appropriate carrying charge in future proceedings.

In April 2021, the OCC approved a waiver for PSO allowing the deferral of the extraordinary fuel and purchase of electricity costs, including a carrying charge at an interim rate of 0.75%, over a longer time period than what the FAC traditionally allows. Also in April 2021, legislation was enacted in Oklahoma to permit securitization of the extraordinary fuel and purchase of electricity costs impacting the utilities within the state. Under the legislation, the OCC has the authority to determine, after receiving an application from a rate-regulated utility, if the extraordinary fuel and purchase of electricity costs incurred in February 2021 may be mitigated through securitization to reduce the impact on customer bills. PSO has filed an application for a financing order to pursue securitization. The application requests an order on the prudency of the extraordinary fuel and purchase of electricity costs and a
carrying charge of the commission authorized weighted average cost of capital until securitization bonds can be issued. In October 2021, OCC staff and intervenors filed testimony supporting securitization of these costs and a carrying charge until costs are securitized ranging from the interim rate of 0.75% to the actual cost of capital used to finance the costs of 2.32%. In addition, OCC staff supported the prudency of PSO's requested costs while one intervenor recommended disallowances of up to $40 million. A procedural schedule has been set with an ALJ report to be filed in January 2022. An order from the OCC is expected in the first quarter of 2022.

In August 2021, SWEPCo filed an application with the PUCT to implement a net interim fuel surcharge for the Texas jurisdictional share of these retail fuel costs. The application supported a five-year recovery at a carrying charge of 7.18%. In October 2021, various intervenors filed testimony supporting a five-year recovery with a carrying charge ranging from 0.082% to 1.625%. A hearing with the PUCT is scheduled for November 2021.

Wholesale Customers

During the first quarter of 2021, SWEPCo billed wholesale customers $104 million resulting from the severe winter weather events. SWEPCo worked with wholesale customers to establish payment terms for the outstanding accounts receivable. As of September 30, 2021, $56 million of accounts receivable from wholesale customers are outstanding. Management believes these receivables are probable of future collection.

PSO and SWEPCo Cash Flow Implications

PSO and SWEPCo evaluated financing alternatives to address the timing difference between the payment of the estimated natural gas expenses and purchases of electricity to suppliers and subsequent recovery from customers. In March 2021, PSO drew $100 million on its revolving credit facility and SWEPCo issued $500 million of Senior Unsecured Notes. In March 2021, Parent entered into a $500 million 364-day Term Loan and borrowed the full amount. The proceeds from this loan were used to help fund capital contributions to PSO and SWEPCo totaling $425 million and $100 million, respectively. In April 2021, PSO received an additional capital contribution from Parent of $125 million to further address these costs.

Although the February 2021 severe winter weather did not materially impact AEP’s results of operations for the three and nine months ended September 30, 2021, if either PSO or SWEPCo is unable to recover these fuel and purchased power costs, or obtain authorization of a reasonable carrying charge on these costs, it could reduce future net income and cash flows and impact financial condition.

COVID-19 Pandemic

During 2020, AEP’s electric operating companies informed both retail customers and state regulators that disconnections for non-payment were temporarily suspended. Shortly thereafter, AEP’s state regulators also imposed temporary moratoria on customary disconnection practices. As of September 30, 2021, AEP’s electric operating companies have resumed customary disconnection practices in all regulated jurisdictions with the exception of residential customers in Virginia. AEP continues to work with regulators and stakeholders in Virginia and management currently anticipates resuming customary disconnection practices once available relief funds are received from the state. Continuing adverse economic conditions may result in the inability of customers to pay for electric service, which could affect revenue recognition and the collectability of accounts receivable. If any costs related to COVID-19 are not recoverable, it could reduce future net income and cash flows and impact financial condition.
AEP Texas Rate Matters (Applies to AEP and AEP Texas)

AEP Texas Interim Transmission and Distribution Rates

Through September 30, 2021, AEP Texas’ cumulative revenues from interim base rate increases that are subject to review is approximately $229 million. A base rate review could result in a refund to customers if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition. AEP Texas is required to file for a comprehensive rate review no later than April 5, 2024.

APCo and WPCo Rate Matters (Applies to AEP and APCo)

2017-2019 Virginia Triennial Review

In November 2020, the Virginia SCC issued an order on APCo’s 2017-2019 Triennial Review filing concluding that APCo earned above its authorized ROE but within its ROE band for the 2017-2019 period, resulting in no refund to customers and no change to APCo base rates on a prospective basis. The Virginia SCC approved a prospective 9.2% ROE for APCo's 2020-2022 triennial review period with the continuation of a 140 basis point band (8.5% bottom, 9.2% midpoint, 9.9% top).

In December 2020, an intervenor filed a petition at the Virginia SCC requesting reconsideration of: (a) the failure of the Virginia SCC to apply a threshold earnings test to the approved regulatory asset for APCo’s closed coal-fired generation assets, (b) the Virginia SCC’s use of a 2011 benchmark study to measure the replacement value of capacity for purposes of APCo’s 2017 – 2019 earnings test and (c) the reasonableness and prudency of APCo’s investments in AMI meters.

In December 2020, APCo filed a petition at the Virginia SCC requesting reconsideration of: (a) certain issues related to APCo’s going-forward rates and (b) the Virginia SCC’s decision to deny APCo tariff changes that align rates with underlying costs. For APCo’s going-forward rates, APCo requested that the Virginia SCC clarify its final order and clarify whether APCo’s current rates will allow it to earn a fair return. If the Virginia SCC’s order did conclude on APCo’s ability to earn a fair return through existing base rates, APCo further requested that the Virginia SCC clarify whether it has the authority to also permit an increase in base rates.

In March 2021, an intervenor filed its assignments of error with the Virginia Supreme Court related to the appeal of the November 2020 order in which it stated the Virginia SCC erred: (a) in determining that Virginia law did not apply to its determination to permit amortization for recovery of costs associated with retired coal-fired generation assets, (b) in establishing a new regulatory asset for a cost incurred outside of the triennial review period due to its failure to apply a threshold earnings test before approving deferred cost recovery and (c) in misapplying the requirement that APCo bear the burden of demonstrating that power purchases made by APCo from its affiliate, OVEC, were priced at the lower of OVEC’s cost or the market price for nonaffiliated power.

In March 2021, APCo filed its assignments of error with the Virginia Supreme Court related to its appeal of the November 2020 order in which it stated the Virginia SCC erred: (a) in finding that costs associated with asset impairments related to early retirement determinations made by APCo for certain generation facilities should not be attributed to the test periods under review and deemed fully recovered in the period recorded, (b) in finding that it was permitted to evaluate the reasonableness of APCo’s decision to record, per books for financial reporting purposes, asset impairments related to early retirement determinations for certain generation facilities, (c) as a result of the errors described in (a) and (b), in denying APCo an increase in rates, (d) in failing to review and make any findings regarding whether APCo’s rates would allow it to earn a fair rate of return going forward, (e) in denying APCo an increase in base rates by failing to ensure that APCo has an opportunity to recover its costs and earn a fair rate of return, thereby resulting in a taking of private property for public use without just compensation and (f) in
retroactively adjusting APCo’s depreciation expense for purposes of calculating APCo’s earnings for the 2017-2019 triennial period.

In March 2021, the Virginia SCC issued an order confirming certain of its decisions from the November 2020 order and rejecting the various requests for reconsideration from APCo and an intervenor. In confirming its decision to reject an intervenor’s recommendation that APCo’s AMI costs incurred during the triennial period be disallowed, the Virginia SCC clarified that APCo established the need to replace its existing AMR meters, and that based on the uncertainty surrounding the continued manufacturing and support of AMR technology, APCo reasonably chose to replace them with AMI meters. In March 2021, APCo filed a notice of appeal of the reconsideration order with the Virginia Supreme Court. In September 2021, APCo submitted its brief before the Virginia Supreme Court. The brief was in alignment with the assignments of error filed by APCo in March 2021. In October 2021, the Virginia SCC and certain intervenors filed briefs with the Virginia Supreme Court disagreeing with APCo’s assignments of error in its appeal of the Triennial Review decision. Additionally, the Virginia SCC and APCo filed briefs disagreeing with an intervenor’ s assignments of error in a separate appeal of the same decision.

APCo ultimately seeks an increase in base rates through its appeal to the Virginia Supreme Court. Among other issues, this appeal includes APCo’s request for proper treatment of the closed coal-fired plant assets in APCo’s 2017-2019 triennial period, reducing APCo’s earnings below the bottom of its authorized ROE band. If APCo’s appeals regarding treatment of the closed coal plants are granted by the Virginia Supreme Court, it could initially reduce future net income and impact financial condition. The initial negative impact for the write-off of closed coal-fired plant asset balances would potentially be partially offset by an increase in base rates for earning below APCo’s 2017-2019 authorized ROE band.

CCR/ELG Compliance Plan Filings

In December 2020, APCo submitted filings with the Virginia SCC and WVPSC requesting approvals necessary to implement CCR/ELG compliance plans at the Amos and Mountaineer Plants. Intervenors in Virginia and West Virginia recommended that only the CCR-related investments be constructed at Amos and Mountaineer and, as a consequence, that APCo close these generating facilities at the end of 2028.

In August 2021, the Virginia SCC issued an order approving APCo’s request to construct CCR-related investments at the Amos and Mountaineer Plants and approved recovery of CCR-related other operation and maintenance expenses and investments through an active rider. The order denied APCo’s request to construct the ELG investments and denied recovery of previously incurred ELG costs. APCo may refile for approval of the ELG investments and previously incurred ELG costs at a later date.

Also in August 2021, the WVPSC approved the request to construct CCR/ELG investments at the Amos and Mountaineer Plants and approved recovery of the West Virginia jurisdictional share of these costs through an active rider. In September 2021, APCo submitted a filing with the WVPSC to reopen the CCR/ELG case that was approved by the WVPSC in August 2021. Due to the initial rejection by the Virginia SCC of the Virginia jurisdictional share of the ELG investments, APCo requested the WVPSC consider approving the construction and recovery of all ELG costs at the plants. In October 2021, the WVPSC affirmed its August 2021 order approving the construction of CCR/ELG investments and directed APCo to proceed with CCR/ELG compliance plans that would allow the plants to continue operating beyond 2028. The WVPSC’s order further states that APCo will not share capacity and energy from the plants with customers from Virginia if those customers are not paying for ELG compliance costs, or for any new capital investment or continuing operations costs incurred, to allow the plants to operate beyond 2028 or prevent downgrades prior to 2028. The WVPSC also ordered that APCo will be given the opportunity to recover, from West Virginia customers, the new capital and operating costs arising solely from the WVPSC's directive to operate the plants beyond 2028 if the WVPSC finds that the costs are reasonably and prudently incurred. In October 2021, an intervenor filed a petition for reconsideration at the WVPSC requesting clarification on certain aspects of the order, primarily the jurisdictional allocation of future operating expenses and plant costs.
APCo expects total Amos and Mountaineer Plant ELG investment, including AFUDC, to be approximately $177 million. As of September 30, 2021, APCo’s Virginia jurisdictional share of the net book value, before cost of removal including CWIP and inventory, of the Amos and Mountaineer Plants was approximately $1.5 billion and APCo’s Virginia jurisdictional share of its ELG investment balance in CWIP for these plants was $19 million.

If any of the ELG costs are not approved for recovery and/or the retirement dates of the Amos and Mountaineer plants are accelerated to 2028 without commensurate cost recovery, it would reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

AEP has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next base rate proceeding. Through September 30, 2021, AEP’s share of ETT’s cumulative revenues that are subject to review is approximately $1.3 billion. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. ETT is required to file for a comprehensive rate review no later than February 1, 2023, during which the $1.3 billion of cumulative revenues above will be subject to review.

I&M Rate Matters (Applies to AEP and I&M)

Indiana Earnings Test Filings

I&M is required by Indiana law to submit an earnings test evaluation for the most recent one-year and five-year periods as part of I&M’s semi-annual Indiana FAC filings. These earnings test evaluations require I&M to include a credit in the FAC factor computation for periods in which I&M earned above its authorized return for both the one-year and five-year periods. The credit is determined as 50% of the lower of the one-year or five-year earnings above the authorized level. In July 2021, I&M submitted its FAC filing and earnings test evaluation for the period ended May 2021, which calculated a credit due to customers of $9 million. In September 2021, the IURC approved the FAC filing and earnings test evaluation, with the credit to customers starting in October 2021 through the FAC.

2021 Indiana Base Rate Case

In July 2021, I&M filed a request with the IURC for a $104 million annual increase in Indiana base rates based upon a proposed 10% ROE. I&M proposed a phased-in annual increase in rates of $73 million effective in May 2022 with the remaining $31 million annual increase in rates to be effective January 2023. The proposed annual increase includes $7 million related to an annual increase in depreciation expense, driven by increased depreciation rates and proposed investments. The request also includes a new AMI rider for proposed meter projects.

In October 2021, intervenors submitted testimony recommending an annual decrease in Indiana base rates ranging from $13 million to $68 million based upon a ROE ranging from 9.1% to 9.3%. Among other issues, intervening parties recommended that the IURC reject the following: (a) I&M’s proposed re-allocation of capacity costs related to the 2020 loss of a significant FERC wholesale contract, (b) continued recovery of a return on remaining Rockport Unit 2 leasehold improvements once the related lease ends in December 2022, (c) inclusion of net operating loss in rate base, (d) the proposed new AMI rider and (e) inclusion of prepaid pension and OPEB assets in rate base. I&M rebuttal testimony is due in November 2021. If any costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.
KPCo Rate Matters (Applies to AEP)

CCR/ELG Compliance Plan Filings

KPCo and WPCo each own a 50% interest in the Mitchell Plant. In December 2020 and February 2021, WPCo and KPCo filed requests with the WVPSC and KPSC, respectively, to obtain the regulatory approvals necessary to implement CCR and ELG compliance plans and seek recovery of the estimated $132 million investment for the Mitchell Plant that would allow the plant to continue operating beyond 2028. Within those requests, WPCo and KPCo also filed a $25 million alternative to implement only the CCR-related investments with the WVPSC and KPSC, respectively, which would allow the Mitchell Plant to continue operating only through 2028.

In July 2021, the KPSC issued an order approving the CCR only alternative and rejecting the full CCR and ELG compliance plan. In August 2021, the WVPSC approved the full CCR and ELG compliance plan for the WPCo share of the Mitchell Plant. In September 2021, WPCo submitted a filing with the WVPSC to reopen the CCR/ELG case that was approved by the WVPSC in August 2021. Due to the rejection by the KPSC of the KPCo share of the ELG investments, WPCo requested the WVPSC consider approving the construction and recovery of all ELG costs at the plant. In October 2021, the WVPSC affirmed its August 2021 order approving the construction of CCR/ELG investments and directed WPCo to proceed with CCR/ELG compliance plans that would allow the plant to continue operating beyond 2028. The WVPSC’s order further states WPCo will not share capacity and energy from the plant with KPCo customers if those customers are not paying for ELG compliance costs, or for any new capital investment or continuing operations costs incurred, to allow the plant to operate beyond 2028 or prevent downgrades prior to 2028. The WVPSC also ordered that WPCo will be given the opportunity to recover, from its customers, the new capital and operating costs arising solely from the WVPSC's directive to operate the plant beyond 2028 if the WVPSC finds that the costs are reasonably and prudently incurred. In October 2021, an intervenor filed a petition for reconsideration at the WVPSC requesting clarification on certain aspects of the order, primarily the jurisdictional allocation of future operating expenses and plant costs.

As of September 30, 2021, KPCo’s share of the Mitchell Plant’s ELG investment balance in CWIP was $2 million. As of September 30, 2021, the net book value of KPCo’s share of the Mitchell Plant, before cost of removal including CWIP and inventory, was $587 million.

If any of the ELG costs are not approved for recovery and/or the retirement date of the Mitchell Plant is accelerated to 2028 without commensurate cost recovery, it would reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

2020 Ohio Base Rate Case

In June 2020, OPCo filed a request with the PUCO for a $42 million annual increase in base rates based upon a proposed 10.15% ROE net of existing riders.

In November 2020, the PUCO staff filed testimony supporting an annual revenue decrease ranging from $102 million to $123 million based upon a ROE of 8.76% to 9.78%. The difference between OPCo’s request and the staff testimony are primarily due to reductions in: (a) demand-side management programs of $40 million, (b) ROE ranging from $9 million to $30 million, (c) employee-related expenses of $23 million, (d) rate base of $19 million, (e) property taxes of $17 million, (f) other various expenses of $15 million, (g) depreciation expense of $11 million and (h) vegetation management programs of $10 million which is subject to over/under-recovery through a rider. The staff’s proposed disallowance of plant in service could also result in a write-off of up to $27 million. In addition, the staff recommended that capitalized incentives be excluded from base rates prospectively and also recommended annual revenue caps for the DIR of $57 million in 2021, $78 million in 2022, $96 million in 2023 and $46 million for the first five months of 2024. In December 2020, OPCo and intervenors filed objections.
In March 2021, OPCo, the PUCO staff and various intervenors filed a joint stipulation and settlement agreement with the PUCO. The agreement includes a $68 million annual decrease in base rates based on an ROE of 9.7%. The difference between OPCo’s requested annual base rate increase and the agreed upon decrease is primarily due to a reduction in the requested ROE, the removal of proposed future energy efficiency costs and a decrease in vegetation management expenses moved to recovery in riders. Additionally, the agreement includes: (a) an increased fixed monthly residential customer charge, (b) the discontinuation of rate decoupling and (c) the continuation of the DIR with annual revenue caps of $57 million in 2021, $91 million in 2022, $116 million in 2023 and $51 million for the first five months of 2024. Annual revenue caps for the DIR can be increased if OPCo achieves certain reliability standards. If the joint stipulation and settlement agreement is approved by the PUCO, new base rates will go into effect 14 days after such approval. A hearing took place with the PUCO in May 2021 and initial briefs were filed in June 2021 followed by reply briefs in July 2021. An order from the PUCO is expected in the fourth quarter of 2021. If the joint stipulation and settlement agreement is denied by the PUCO, it could reduce future net income and cash flows and impact financial condition.

2019 Ohio DIR Audit

OPCo conducts business under an ESP as approved by the PUCO which subjects the DIR to annual audits. In August 2020, a third-party consulting company filed an audit report with the PUCO indicating that OPCo exceeded its 2019 authorized revenue limit by $17 million. In September 2021, the third-party consulting company adjusted its findings in the previous audit, indicating that OPCo exceeded its 2019 authorized revenue limit by $3 million. Management disagrees with the audit results and believes that OPCo was below its authorized revenue limit in 2019. If the results of the audit are upheld by the PUCO and any refunds to customers or revenue reductions are ordered, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2021 Oklahoma Base Rate Case

In April 2021, PSO filed a request with the OCC for a $172 million net annual increase in Oklahoma base rates based upon a 10% ROE. The proposed net annual increase includes: (a) a $57 million annual depreciation expense increase, of which $45 million is related to the accelerated depreciation recovery of the Oklaunion Power Station and Northeastern Plant, Unit 3 through 2026 and (b) $31 million related to increased SPP expenses. PSO also requested the continuation of its SPP Transmission Tariff that tracks transmission costs as well as continuation and expansion of its Distribution and Safety Reliability Rider to recover projects in its proposed grid transformation and revitalization plan, which includes $100 million annual capital spend over a 5 year period. In August 2021, PSO updated its request for a net annual revenue increase to appropriately reflect certain cost reductions and annualized rider revenues transitioning into base rates. PSO’s updated request filed with the OCC is for a $128 million net annual increase in Oklahoma base rates based upon a 10% ROE.

Also, in August 2021, OCC staff and various intervenors filed testimony supporting net annual revenue changes ranging from a $44 million net decrease to a $74 million net increase based upon a ROE of 9.0% to 9.4%. The difference between PSO’s request and OCC staff and intervenor testimony is primarily due to: (a) disallowance of recovery of Oklaunion Power Station or allowing recovery with a debt-only return over Oklaunion Power Station's original useful life of 2046, (b) rejection of PSO’s request to accelerate the recovery of Northeastern Plant, Unit 3 from its original retirement date of 2040 to its projected retirement date of 2026, (c) disallowance of $41 million in SPP transmission expense and denial of prospective tracking of most SPP transmission costs through the SPP transmission tariff, (d) opposition to PSO’s recommendation to include its deferred tax asset associated with net operating loss on a stand-alone tax basis in rate base, (e) a lower recommended ROE and (f) recommendations to discontinue the Distribution and Safety Reliability Rider.
In September 2021, PSO, OCC staff and certain intervenors filed a contested joint stipulation and settlement agreement with the OCC that included a net annual revenue increase of $51 million based upon a 9.4% ROE. The agreement also included: (a) recovery of, with a debt return on, the Oklaunion Power Station regulatory asset through 2046 and continued recovery of Northeastern Plant, Unit 3 through 2040, (b) updated depreciation rates for plant in service, not including coal production plant, (c) approval to defer a weighted average cost of capital carrying charge on PSO’s deferred tax asset associated with net operating loss on a stand-alone tax basis beginning in November 2021 and, contingent upon receipt of a supportive private letter ruling from the IRS, approval to collect the deferral through a rider over a 20-month period, (d) modification of the SPP transmission tariff to reduce the scope of tracked transmission expense and (e) modification of the Distribution Reliability and Safety Rider to limit recovery to previously approved projects not in service as of June 2021. In October 2021, a hearing on the merits of the contested joint stipulation and settlement agreement was held at the OCC. PSO will implement interim rates subject to refund starting with the November 2021 billing cycle. An order is expected in December 2021. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, SWEPCo reversed $114 million of a previously recorded regulatory disallowance in 2013. In 2017, the Texas District Court upheld the PUCT’s 2014 order and intervenors filed appeals with the Texas Third Court of Appeals.

In July 2018, the Texas Third Court of Appeals reversed the PUCT’s judgment affirming the prudence of the Turk Plant and remanded the issue back to the PUCT. In January 2019, SWEPCo and the PUCT filed petitions for review with the Texas Supreme Court. In March 2021, the Texas Supreme Court issued an opinion reversing the July 2018 judgment of the Texas Third Court of Appeals and agreeing with the PUCT’s judgment affirming the prudence of the Turk Plant. In addition, the Texas Supreme Court remanded the AFUDC dispute back to the Texas Third Court of Appeals. No parties filed a motion for rehearing with the Texas Supreme Court. In August 2021, the Texas Third Court of Appeals reversed the Texas District Court judgement affirming the PUCT’s order on AFUDC, concluding that the language of the PUCT’s original 2008 order intended to include AFUDC in the Texas jurisdictional capital cost cap, and remanded the case to the PUCT for future proceedings. SWEPCo disagrees with the Court of Appeals decision and expects to submit a Petition for Review with the Texas Supreme Court in November 2021.

If SWEPCo is ultimately unable to recover capitalized Turk Plant costs including AFUDC in excess of the Texas jurisdictional capital cost cap it would result in a pretax net disallowance ranging from $80 million to $100 million. In addition, if AFUDC is ultimately determined to be included in the Texas jurisdictional capital cost cap, SWEPCo estimates it may be required to make customer refunds ranging from $0 to $160 million related to revenues collected from February 2013 through September 2021 and such determination may reduce SWEPCo’s future revenues by approximately $15 million on an annual basis.
2016 Texas Base Rate Case

In 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% ROE. In January 2018, the PUCT issued a final order approving a net increase in Texas annual revenues of $50 million based upon a ROE of 9.6%, effective May 2017. The final order also included: (a) approval to recover the Texas jurisdictional share of environmental investments placed in-service, as of June 30, 2016, at various plants, including Welsh Plant, Units 1 and 3, (b) approval of recovery of, but no return on, the Texas jurisdictional share of the net book value of Welsh Plant, Unit 2, (c) approval of $2 million in additional vegetation management expenses and (d) the rejection of SWEPCo’s proposed transmission cost recovery mechanism.

As a result of the final order in 2017, SWEPCo: (a) recorded an impairment charge of $19 million, which included $7 million associated with the lack of return on Welsh Plant, Unit 2 and $12 million related to other disallowed plant investments, (b) recognized $32 million of additional revenues, for the period of May 2017 through December 2017, that was surcharged to customers in 2018 and (c) recognized an additional $7 million of expenses consisting primarily of depreciation expense and vegetation management expense, offset by the deferral of rate case expense. SWEPCo implemented new rates in February 2018 billings. The $32 million of additional 2017 revenues was collected during 2018. In March 2018, the PUCT clarified and corrected portions of the final order, without changing the overall decision or amounts of the rate change. The order has been appealed by various intervenors. The appeal will move forward following the conclusion of the 2012 Texas Base Rate Case. If certain parts of the PUCT order are overturned, it could reduce future net income and cash flows and impact financial condition.

Hurricane Laura

In August 2020, Hurricane Laura hit the coasts of Louisiana and Texas, causing power outages to more than 130,000 customers across SWEPCo’s service territories. Prior to Hurricane Laura, SWEPCo did not have a catastrophe reserve or automatic deferral authority within any of its jurisdictions. In October 2020, the LPSC issued an order allowing Louisiana utilities, including SWEPCo, to establish a regulatory asset to track and defer expenses associated with Hurricane Laura. In October 2020, as part of the 2020 Texas Base Rate Case, SWEPCo requested deferral authority of incremental other operation and maintenance expenses. As of September 30, 2021, management estimates that SWEPCo has incurred incremental other operation and maintenance expenses of $92 million ($89 million of which has been deferred as a regulatory asset related to the Louisiana jurisdiction) and incremental capital expenditures of $18 million, all of which is related to the Louisiana jurisdiction. In October 2021, SWEPCo requested recovery of these storm costs, in addition to Hurricane Delta and February 2021 winter storm costs, in a filing with the LPSC. See “Storm Restoration Costs” above for more information. If any costs related to Hurricane Laura are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Hurricane Delta

In October 2020, Hurricane Delta hit the coast of Louisiana, causing power outages to more than 23,000 customers in SWEPCo’s Louisiana jurisdiction. In November 2020, the LPSC issued an order allowing Louisiana utilities, including SWEPCo, to establish a regulatory asset to track and defer expenses associated with Hurricane Delta. As of September 30, 2021, management estimates that SWEPCo has incurred incremental other operation and maintenance expenses of $18 million, which has been deferred as a regulatory asset. Also, management estimates that SWEPCo has incurred incremental capital expenditures of $2 million. In October 2021, SWEPCo requested recovery of these storm costs, in addition to Hurricane Laura and February 2021 winter storm costs, in a filing with the LPSC. See “Storm Restoration Costs” above for more information. If any costs related to Hurricane Delta are not recoverable, it could reduce future net income and cash flows and impact financial condition.
2020 Texas Base Rate Case

In October 2020, SWEPCo filed a request with the PUCT for a $105 million annual increase in Texas base rates based upon a proposed 10.35% ROE. The request would move transmission and distribution interim revenues recovered through riders into base rates. Eliminating these riders would result in a net annual requested base rate increase of $90 million primarily due to increased investments. The proposed net annual increase: (a) includes $5 million related to vegetation management to maintain and improve the reliability of SWEPCo’s Texas jurisdictional distribution system, (b) requests a $10 million annual depreciation increase and (c) seeks $2 million annually to establish a storm catastrophe reserve. In addition, SWEPCo requested recovery of the Texas jurisdictional share of the Dolet Hills Power Station of $45 million which is expected to be retired by the end of 2021. SWEPCo subsequently filed a request with the PUCT lowering the requested annual increase in Texas base rates to $100 million which would result in an $85 million net annual base rate increase after moving the proposed riders to rate base.

In August 2021, an ALJ issued a Proposal for Decision (PFD) which would provide SWEPCo with an annual revenue increase of $41 million based upon a 9.45% ROE. The PFD also includes: (a) rates implemented retroactively back to March 18, 2021, (b) $5 million of the proposed increase related to vegetation management, (c) a denial of the requested $2 million annually to establish a storm catastrophe reserve and (d) the creation of a rider that would recover the Dolet Hills Power Station as if it were in rate base until its retirement at the end of 2021 and starting in 2022 the remaining net book value would be recovered as a regulatory asset through 2046. An order from the PUCT is expected in the fourth quarter of 2021. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2020 Louisiana Base Rate Case

In December 2020, SWEPCo filed a request with the LPSC for a $134 million annual increase in Louisiana base rates based upon a proposed 10.35% ROE. In March 2021, SWEPCo filed a revised request with the LPSC to remove hurricane storm costs from the base rate case filing and seek recovery of those costs in a separate filing. SWEPCo’s revised filing requested an annual increase in Louisiana base rates of $114 million. The request would extend the formula rate plan for five years and includes modifications to the formula rate plan to allow for forward-looking transmission costs, reflects the impact of net operating losses associated with the acceleration of certain tax benefits and incorporates future federal corporate income tax changes. The proposed net annual increase requests a $32 million annual depreciation increase to recover Louisiana’s share of the Dolet Hills Power Station, Pirkey Power Plant and Welsh Plant, all of which are expected to be retired early. In April 2021, the LPSC approved SWEPCo’s request to remove the hurricane storm costs from the base rate case filing. In October 2021, SWEPCo requested recovery of the $152 million of storm costs associated with Hurricanes Delta, Laura and the February 2021 winter storm in a filing with the LPSC. See “Storm Restoration Costs” above for more information.

In July 2021, the LPSC staff filed testimony supporting a $6 million annual increase in base rates based upon an ROE of 9.1% while other intervenors recommended an ROE ranging from 9.35% to 9.8%. The primary differences between SWEPCo’s requested annual increase in base rates and the LPSC staff’s recommendation include: (a) a reduction in depreciation expense, (b) recovery of Dolet Hills Power Station and Pirkey Power Plant in a separate rider mechanism, (c) the rejection of SWEPCo’s proposed adjustment to include a stand-alone net operating loss carryforward deferred tax asset in rate base and (d) a reduction in the proposed ROE.

In September 2021, SWEPCo filed rebuttal testimony supporting a revised requested annual increase in base rates of $95 million. The primary differences in the rebuttal testimony from the previous revised request of $114 million are modifications to the proposed recovery of the Dolet Hills Power Station and revisions to various proposed amortizations. LPSC staff and intervenor responses to SWEPCo’s rebuttal testimony were filed in October 2021.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.
2021 Arkansas Base Rate Case

In July 2021, SWEPCo filed a request with the APSC for an $85 million annual increase in Arkansas base rates based upon a proposed 10.35% ROE. The proposed annual increase includes: (a) a $41 million revenue requirement for the North Central Wind Facilities, (b) a $14 million annual depreciation increase primarily due to recovery of the Dolet Hills Power Station through 2026 and Pirkey Plant and Welsh Plant, Units 1 and 3 through 2037 and (c) a $6 million increase due to SPP costs. SWEPCo requests that rates are effective beginning in June 2022. Staff and intervenor testimony is expected in December 2021.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

FERC SPP Transmission Formula Rate Challenge (Applies to AEP, AEPTCo, PSO and SWEPCo)

In May 2021, certain joint customers submitted a formal challenge at the FERC related to the 2020 Annual Update of the 2019 SPP Transmission Formula Rates of the AEP transmission owning subsidiaries within SPP. Management has reviewed the formal challenge and responses were filed with the FERC at the end of July 2021. If the FERC orders revenue refunds or reductions, it could reduce future net income and cash flows and impact financial condition.

Independence Energy Connection Project (Applies to AEP)

In 2016, PJM approved the Independence Energy Connection Project (IEC) and included it in its Regional Transmission Expansion Plan to alleviate congestion. Transource Energy owns the IEC, which is located in Maryland and Pennsylvania. In June 2020, the Maryland Public Service Commission approved a Certificate of Public Convenience and Necessity to construct the portion of the IEC in Maryland. In May 2021, the Pennsylvania Public Utility Commission (PA PUC) denied the IEC certificate for siting and construction of the portion in Pennsylvania. Transource Energy has appealed the PA PUC ruling in Pennsylvania state court and challenged the ruling before the United States District Court for the Middle District of Pennsylvania. The case before the state court is pending and the case before the United States District Court for the Middle District of Pennsylvania is on hold, pending the outcome of the case in the Pennsylvania state court.

In September 2021, PJM notified Transource Energy that the IEC was suspended to allow for the regulatory and related appeals process to proceed in an orderly manner without breaching milestone dates in the project agreement. PJM stated that the IEC has not been cancelled and remains necessary to alleviate congestion. PJM will reevaluate the need for the IEC at the end of 2021 during its annual reevaluation process. As of September 30, 2021, AEP’s share of IEC capital expenditures was approximately $79 million. The FERC has previously granted abandonment benefits for this project, allowing the full recovery of prudently incurred costs if the project is cancelled for reasons outside the control of Transource Energy. If any of the IEC costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.