XML 56 R12.htm IDEA: XBRL DOCUMENT v3.7.0.1
Rate Matters
6 Months Ended
Jun. 30, 2017
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
AEP Transmission Co [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
Appalachian Power Co [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
Indiana Michigan Power Co [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
Ohio Power Co [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
Public Service Co Of Oklahoma [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.
Southwestern Electric Power Co [Member]  
Rate Matters
RATE MATTERS

The disclosures in this note apply to all Registrants unless indicated otherwise.

As discussed in AEP’s and AEPTCo’s 2016 Annual Reports, the Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within AEP’s and AEPTCo’s 2016 Annual Reports should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2017 and updates AEP’s and AEPTCo’s 2016 Annual Reports.

Regulatory Assets Pending Final Regulatory Approval
 
 
AEP
 
 
June 30,
 
December 31,
 
 
2017
 
2016
 Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
204.3

 
$
159.9

Storm-Related Costs
 
24.4

 
25.1

Plant Retirement Costs - Materials and Supplies
 
9.1

 
9.1

Ohio Capacity Deferral
 

 
96.7

Other Regulatory Assets Pending Final Regulatory Approval
 
1.1

 
1.3

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
41.2

 
25.9

Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Cook Plant Uprate Project
 
36.3

 
36.3

Environmental Control Projects
 
20.4

 
24.1

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Other Regulatory Assets Pending Final Regulatory Approval
 
21.2

 
21.2

Total Regulatory Assets Pending Final Regulatory Approval (b)
 
$
421.0

 
$
450.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million
(b)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
APCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Materials and Supplies
 
$
9.1

 
$
9.1

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Plant Retirement Costs - Asset Retirement Obligation Costs
 
37.2

 
29.6

Other Regulatory Assets Pending Final Regulatory Approval
 
0.6

 
0.6

Total Regulatory Assets Pending Final Regulatory Approval (a)
 
$
46.9

 
$
39.3



(a)
In 2015, APCo recorded a $91 million reduction to accumulated depreciation related to the remaining net book value of plants retired in 2015, primarily in its Virginia jurisdiction.  These plants were normal retirements at the end of their depreciable lives under the group composite method of depreciation. Recovery of the remaining Virginia net book value for the retired plants will be considered in APCo’s next depreciation study which will be included in APCo’s 2018-2019 Virginia biennial filing in March 2020.
 
 
I&M
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Not Earning a Return
 
 
 
 
Cook Plant Uprate Project
 
$
36.3

 
$
36.3

Cook Plant Turbine
 
14.3

 
12.8

Deferred Cook Plant Life Cycle Management Project Costs - Michigan
 
11.5

 
8.1

Rockport Dry Sorbent Injection System - Indiana
 
8.3

 
6.6

Other Regulatory Assets Pending Final Regulatory Approval
 
1.0

 
0.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
71.4

 
$
64.7


 
 
OPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Capacity Deferral
 
$

 
$
96.7

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Smart Grid Costs
 

 
4.1

Total Regulatory Assets Pending Final Regulatory Approval
 
$

 
$
100.8


 
 
PSO
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant (a)
 
$
128.9

 
$
84.5

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.5

Regulatory Assets Currently Not Earning a Return
 
 

 
 

Storm-Related Costs
 
35.4

 
20.0

Environmental Control Projects
 
20.4

 
13.1

Other Regulatory Assets Pending Final Regulatory Approval
 
0.2

 

Total Regulatory Assets Pending Final Regulatory Approval
 
$
185.4

 
$
118.1



(a)
In March 2017, $41 million was reclassified from accumulated depreciation to regulatory assets related to Northeastern Plant, Unit 3. As of June 30, 2017, the unrecovered plant balance related to Northeastern Plant, Unit 3 was $46 million. 
 
 
SWEPCo
 
 
June 30,
 
December 31,
 
 
2017
 
2016
Noncurrent Regulatory Assets
 
(in millions)
 
 
 
 
 
Regulatory Assets Currently Earning a Return
 
 
 
 
Plant Retirement Costs - Unrecovered Plant
 
$
75.4

 
$
75.4

Other Regulatory Assets Pending Final Regulatory Approval
 
0.5

 
0.8

Regulatory Assets Currently Not Earning a Return
 
 
 
 
Shipe Road Transmission Project - FERC
 
3.3

 
3.1

Asset Retirement Obligation - Arkansas, Louisiana
 
3.3

 
2.7

Rate Case Expense - Texas
 
2.1

 
1.0

Environmental Control Projects
 

 
11.0

Other Regulatory Assets Pending Final Regulatory Approval
 
2.1

 
1.9

Total Regulatory Assets Pending Final Regulatory Approval
 
$
86.7

 
$
95.9



If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

AEP Texas Rate Matters (Applies to AEP)

AEP Texas Interim Transmission and Distribution Rates

As of June 30, 2017, AEP Texas’ cumulative revenues from interim base rate increases from 2008 through 2017, subject to review, are estimated to be $635 million. A base rate review could produce a refund if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters (Applies to AEP and APCo)

Virginia Legislation Affecting Biennial Reviews

In 2015, amendments to Virginia law governing the regulation of investor-owned electric utilities were enacted. Under the amended Virginia law, APCo’s existing generation and distribution base rates are frozen until after the Virginia SCC rules on APCo’s next biennial review, which APCo will file in March 2020 for the 2018 and 2019 test years. These amendments also preclude the Virginia SCC from performing biennial reviews of APCo’s earnings for the years 2014 through 2017. APCo’s financial statements adequately address the impact of these amendments. The amendments provide that APCo will absorb its Virginia jurisdictional share of incremental generation and distribution costs incurred from 2014 through 2017 that are associated with severe weather events and/or natural disasters and costs associated with potential asset impairments related to new carbon emission guidelines issued by the Federal EPA.

In 2016, the Virginia SCC issued an order that denied the petition of certain APCo industrial customers that requested the issuance of a declaratory order that would find the amendments to Virginia law suspending biennial reviews unconstitutional and, accordingly, direct APCo to make biennial review filings beginning in 2016. In July 2016, the industrial customers filed an appeal of the order with the Supreme Court of Virginia. In April 2017, oral arguments were held before the Supreme Court of Virginia. Management is unable to predict the outcome of these challenges to the Virginia legislation. If the biennial review process is reinstated in advance of March 2020, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

Parent has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next filed base rate proceeding. Through June 30, 2017, AEP’s share of ETT’s cumulative revenues that are subject to review is estimated to be $672 million. A base rate review could produce a refund if ETT incurs a disallowance of the transmission investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters (Applies to AEP and I&M)

2017 Indiana Base Rate Case

In July 2017, I&M filed a request with the IURC for a $263 million annual increase in Indiana rates based upon a proposed 10.6% return on common equity with the annual increase to be implemented after June 2018. Upon implementation, this proposed annual increase would be subject to an offsetting $23 million annual reduction to customer bills through December 2018 for a credit adjustment rider related to the timing of estimated in-service dates of certain capital expenditures.  The proposed annual increase includes $78 million related to increased annual depreciation rates and an $11 million increase related to the amortization of certain Cook Plant and Rockport Plant regulatory assets. The increase in depreciation rates includes a change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant, including the Cook Life Cycle Management Project.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Michigan Base Rate Case

In May 2017, I&M filed a request with the MPSC for a $52 million annual increase in Michigan base rates based upon a proposed 10.6% return on common equity with the increase to be implemented no later than March 2018. The proposed annual increase includes $23 million related to increased annual depreciation rates and a $4 million increase related primarily to the amortization of certain Cook Plant regulatory assets. The increase in depreciation rates is primarily due to the change in the expected retirement date for Rockport Plant, Unit 1 from 2044 to 2028 combined with increased investment at the Cook Plant related to the Life Cycle Management Project. Additionally, the total proposed increase includes incremental costs related to the Cook Plant Life Cycle Management Program and increased vegetation management expenses.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant, Unit 2 Selective Catalytic Reduction (SCR)

In October 2016, I&M filed an application with the IURC for approval of a Certificate of Public Convenience and Necessity (CPCN) to install SCR technology at Rockport Plant, Unit 2 by December 2019. The equipment will allow I&M to reduce emissions of NOx from Rockport Plant, Unit 2 in order for I&M to continue to operate that unit under current environmental requirements. The estimated cost of the SCR project is $274 million, excluding AFUDC, to be shared equally between I&M and AEGCo.  As of June 30, 2017, total costs incurred related to this project, including AFUDC, is approximately $9 million.  The filing included a request for authorization for I&M to defer its Indiana jurisdictional ownership share of costs including investment carrying costs at a weighted average cost of capital (WACC), depreciation over a 10-year period as provided by statute and other related expenses. I&M proposed recovery of these costs using the existing Clean Coal Technology Rider in a future filing subsequent to approval of the SCR project. The AEGCo ownership share of the proposed SCR project will be billable under the Rockport Unit Power Agreement to affiliates, including I&M, with I&M’s share recoverable in its base rates. In February 2017, the Indiana Office of Utility Consumer Counselor (OUCC) and other parties filed testimony with the IURC. The OUCC recommended approval of the CPCN but also stated that any decision regarding recovery of any under-depreciated plant due to retirement should be fully investigated in a base rate case, not in a tracker or other abbreviated proceeding. The other parties recommended either denial of the CPCN or approval of the CPCN with conditions including a cap on the amount of SCR costs allowed to be recovered in the rider and limitations on other costs related to legal issues involving the Rockport lease. A hearing at the IURC was held in March 2017. An order from the IURC is pending. In July 2017, I&M filed a request with the U.S. District Court for the Southern District of Ohio to delay the existing deadline for installation of SCR technology at Rockport Plant, Unit 2.

KPCo Rate Matters (Applies to AEP)

2017 Kentucky Base Rate Case

In June 2017, KPCo filed a request with the KPSC for a $66 million annual increase in Kentucky base rates based upon a proposed 10.31% return on common equity with the increase to be implemented no later than January 2018. The proposed increase includes: (a) lost load since KPCo last changed base rates in July 2015, (b) incremental costs related to OATT charges from PJM not currently recovered from retail ratepayers, (c) increased depreciation expense including updated Big Sandy, Unit 1 depreciation rates using a proposed retirement date of 2031, (d) recovery of other Big Sandy, Unit 1 generation costs currently recovered through a retail rider and (e) incremental purchased power costs. Additionally, KPCo requested a $4 million annual increase in environmental surcharge revenues.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

Ohio Electric Security Plan Filings

June 2015 - May 2018 ESP Including PPA Application and Proposed ESP Extension through 2024

In 2013, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments and the continuation and modification of certain existing riders, including the Distribution Investment Rider (DIR), effective June 2015 through May 2018. The proposal also involved a PPA rider that would include OPCo’s OVEC contractual entitlement (OVEC PPA) and would allow retail customers to receive a rate stabilizing charge or credit by hedging market-based prices with a cost-based PPA.

In 2015, the PUCO issued orders that approved OPCo’s ESP application, subject to certain modifications, with a return on common equity of 10.2% on capital costs for certain riders. The orders included: (a) approval of the DIR, with modified rate caps established by the PUCO, (b) authorization to establish a zero rate rider for OPCo’s proposed OVEC PPA and (c) the option for OPCo to reapply in a future proceeding with a more detailed PPA proposal. Also in 2015, OPCo subsequently filed an amended OVEC PPA application that, among other things, addressed certain PPA requirements set forth in a 2015 PUCO order. In 2016, the PUCO issued an additional order on rehearing that approved the DIR caps with additional amendments.

In 2016, the PUCO issued orders that approved a contested stipulation agreement related to the PPA rider application. Additionally, as part of these orders, the PUCO approved (a) recovery of OVEC-related net margin incurred beginning June 2016, (b) potential additional contingent customer credits of up to $15 million to be included in the PPA rider over the final four years of the PPA rider and (c) the limitation that OPCo will not flow through any capacity performance penalties or bonuses through the PPA rider. Additionally, subject to cost recovery and PUCO approval, OPCo agreed to develop and implement, by 2021, a solar energy project(s) of at least 400 MWs and a wind energy project(s) of at least 500 MWs, with 100% of all output to be received by OPCo. AEP affiliates could own up to 50% of these solar and wind projects. In December 2016, in accordance with the stipulation agreement, OPCo filed a carbon reduction plan that focused on fuel diversification and carbon emission reductions. In April 2017, the PUCO rejected all pending rehearing requests and the orders are all now final. In June 2017, intervenors filed appeals to the Supreme Court of Ohio stating that the PUCO’s approval of the OVEC PPA was unlawful and does not provide customers with rate stability.

In November 2016, OPCo refiled its amended ESP extension application and supporting testimony, consistent with the terms of the modified and approved stipulation agreement and based upon a 2016 PUCO order. The amended filing proposed to extend the ESP through May 2024 and included (a) an extension of the OVEC PPA rider, (b) a proposed 10.41% return on common equity on capital costs for certain riders, (c) the continuation of riders previously approved in the June 2015 - May 2018 ESP, (d) proposed increases in rate caps related to OPCo’s DIR and (e) the addition of various new riders, including a Distribution Technology Rider and a Renewable Resource Rider. A hearing at the PUCO is scheduled for August 2017.

If OPCo is ultimately not permitted to fully collect all components of its ESP rates, it could reduce future net income and cash flows and impact financial condition.

2016 SEET Filing

Ohio law provides for the return of significantly excessive earnings to ratepayers upon PUCO review. Significantly excessive earnings are measured by whether the earned return on common equity of the electric utility is significantly in excess of the return on common equity that was earned during the same period by publicly traded companies, including utilities, that face comparable business and financial risk.

In December 2016, OPCo recorded a 2016 SEET provision of $58 million based upon projected earnings data for companies in the comparable utilities risk group. In determining OPCo’s return on equity in relation to the comparable utilities risk group, management excluded the following items resolved in OPCo’s Global Settlement: (a) gain on the deferral of RSR costs, (b) refunds to customers related to the SEET remands and (c) refunds to customers related to fuel adjustment clause proceedings. In May 2017, OPCo submitted its 2016 SEET filing with the PUCO in which management indicated that OPCo did not have significantly excessive earnings in 2016 based upon actual earnings data for the comparable utilities risk group. Although management believes that OPCo’s 2016 earnings were not excessive, management did not adjust OPCo’s 2016 SEET provision due to risks that the PUCO could rule against OPCo’s SEET treatment of the Global Settlement issues described above or adopt a different 2016 SEET threshold. If the PUCO orders a refund of 2016 OPCo earnings, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2017 Oklahoma Base Rate Case

In June 2017, PSO filed an application for a base rate review with the OCC that requested a net increase in annual revenues of $156 million based upon a proposed 10% return on common equity. The proposed base rate increase includes (a) environmental compliance investments, including recovery of previously deferred environmental compliance related costs currently recorded as regulatory assets, (b) Advanced Metering Infrastructure deployment cost, (c) additional capital investments and customer costs to serve PSO’s customers, and (d) an annual $42 million depreciation rate increase due primarily to shorter service lives and lower net salvage estimates. As part of this filing, PSO also requested recovery through 2040 of the net book value of Northeastern Plant, Unit 4 that was retired in 2016. As of June 30, 2017, the net book value of Northeastern Plant, Unit 4 was $83 million, before cost of removal, including materials and supplies inventory and CWIP. 

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs. Additionally, the PUCT deferred consideration of the requested increase in depreciation expense related to the change in the 2016 retirement date of the Welsh Plant, Unit 2.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, in the fourth quarter of 2013, SWEPCo reversed $114 million of previously recorded regulatory disallowances. The resulting annual base rate increase was approximately $52 million. In 2014, intervenors filed appeals of that order with the Texas District Court and SWEPCo intervened in those appeals. In June 2017, the Texas District Court upheld the PUCT’s 2014 order. In July 2017, an intervenor filed a notice of appeal with the Texas District Court.

If certain parts of the PUCT order are overturned and if SWEPCo cannot ultimately recover its Texas jurisdictional share of the Turk Plant investment, including AFUDC, it could reduce future net income and cash flows and impact financial condition.

2016 Texas Base Rate Case

In December 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% return on common equity. The annual increase includes approximately (a) $34 million related to additional environmental controls, including those installed at the Welsh Plant, to comply with Federal EPA mandates, (b) $25 million for additional generation, transmission and distribution investments and increased operating costs, (c) $8 million related to transmission cost recovery within SWEPCo’s regional transmission organization and (d) $2 million in additional vegetation management. As part of this filing, SWEPCo requested recovery of the Texas jurisdictional share (approximately 33%) of the net book value of Welsh Plant, Unit 2 through 2042, the remaining life of Welsh Plant, Unit 3.
In April and May 2017, various intervenors and the PUCT staff filed testimony that included annual net revenue increase recommendations ranging from $36 million to $47 million. The recommended return on common equity ranged from 9.2% to 9.35%. In addition, no parties recommended approval of SWEPCo’s proposed transmission cost recovery and certain parties recommended investment disallowances that could result in write-offs of up to approximately $89 million, including approximately $40 million related to environmental investments and $25 million related to Welsh Plant, Unit 2. A hearing at the PUCT was held in June 2017.

If any of these costs are not recoverable, including environmental investments and retirement-related costs for Welsh Plant, Unit 2, it could reduce future net income and cash flows and impact financial condition.

Louisiana Turk Plant Prudence Review

Beginning January 2013, SWEPCo’s formula rates, including the Louisiana jurisdictional share (approximately 29%) of the Turk Plant, have been collected subject to refund pending the outcome of a prudence review of the Turk Plant investment, which was placed into service in December 2012.

A hearing at the LPSC related to the Turk Plant prudence review is scheduled for November 2017. If the LPSC orders refunds based upon the pending prudence review of the Turk Plant investment, it could reduce future net income and cash flows and impact financial condition.

2015 Louisiana Formula Rate Filing

In April 2015, SWEPCo filed its formula rate plan for test year 2014 with the LPSC.  The filing included a $14 million annual increase, which was effective August 2015.  This increase is subject to LPSC staff review and is subject to refund.  If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2017 Louisiana Formula Rate Filing

In April 2017, the LPSC approved an uncontested stipulation agreement that SWEPCo filed for its formula rate plan for test year 2015.  The filing included a net annual increase not to exceed $31 million , which was effective May 2017 and includes Louisiana’s jurisdictional share of Welsh and Flint Creek environmental controls which were placed in service in 2016. These environmental costs are subject to prudence review. The $31 million net annual increase is subject to LPSC staff review and is subject to refund. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

Welsh Plant - Environmental Impact

Management currently estimates that the investment necessary to meet proposed environmental regulations through 2025 for Welsh Plant, Units 1 and 3 could total approximately $850 million, excluding AFUDC. As of June 30, 2017, SWEPCo had incurred costs of $398 million, including AFUDC, related to these projects.  Management continues to evaluate the impact of environmental rules and related project cost estimates. As of June 30, 2017, the total net book value of Welsh Plant, Units 1 and 3 was $628 million, before cost of removal, including materials and supplies inventory and CWIP. 

In 2016, as approved by the APSC, SWEPCo began recovering $79 million related to the Arkansas jurisdictional share of these environmental costs, subject to prudence review in the next Arkansas filed base rate proceeding. In December 2016, the LPSC approved deferral of certain expenses related to the Louisiana jurisdictional share of environmental controls installed at Welsh Plant. In April 2017, the LPSC approved SWEPCo’s recovery of these deferred costs effective May 2017. The approved Louisiana jurisdictional share of Welsh Plant deferrals were $11 million, excluding $6 million of unrecognized equity, subject to review by the LPSC, and include a WACC return on environmental investments and the related depreciation expense and taxes. Effective May 2017, SWEPCo began recovering $131 million in investments related to Louisiana’s jurisdictional share of environmental costs.   SWEPCo has sought recovery of its project costs from retail customers at the PUCT and is recovering these costs from wholesale customers through their FERC-approved agreements. See “2016 Texas Base Rate Case” and “2017 Louisiana Formula Rate Filing” disclosures above.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In June 2016, PJM transmission owners, including the eastern AEP affiliates, and various state commissions filed a settlement agreement with the FERC to resolve outstanding issues related to cost responsibility for charges to transmission customers for certain transmission facilities that operate at or above 500 kV. In July 2016, certain parties filed comments at the FERC contesting the settlement agreement. Upon final FERC approval, PJM would implement a transmission enhancement charge adjustment through the PJM OATT, billable through 2025. Management expects that any refunds received would generally be returned to retail customers through existing state rider mechanisms.

FERC Transmission Complaint - AEP’s PJM Participants (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In October 2016, several parties filed a joint complaint with the FERC that states the base return on common equity used by eastern AEP affiliates in calculating formula transmission rates under the PJM OATT is excessive and should be reduced from 10.99% to 8.32%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.

Modifications to AEP’s PJM Transmission Rates (Applies to AEP, AEPTCo, APCo, I&M and OPCo)

In November 2016, certain AEP affiliates filed an application with the FERC to modify the PJM OATT formula transmission rate calculation, including an adjustment to recover a tax-related regulatory asset and a shift from historical to estimated expenses. In March 2017, the FERC accepted the proposed modifications effective January 1, 2017, subject to refund, and set this matter for hearing and settlement procedures. Effective January 1, 2017, the modified PJM OATT formula rates were implemented, subject to refund, based on projected 2017 calendar year financial activity and projected plant balances. If the FERC determines that any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

FERC Transmission Complaint - AEP’s SPP Participants (Applies to AEP, AEPTCo, PSO and SWEPCo)

In June 2017, several parties filed a joint complaint with the FERC that states the base return on common equity used by western AEP affiliates in calculating formula transmission rates under the SPP OATT is excessive and should be reduced from 10.7% to 8.36%, effective upon the date of the complaint. Management believes its financial statements adequately address the impact of the complaint. If the FERC orders revenue reductions as a result of the complaint, including refunds from the date of the complaint filing, it could reduce future net income and cash flows and impact financial condition.