XML 54 R24.htm IDEA: XBRL DOCUMENT v3.10.0.1
Contingencies and Regulatory Matters (Tables)
9 Months Ended
Sep. 30, 2018
Commitments and Contingencies Disclosure [Abstract]  
Cost Recovery Clauses
The balance of each regulatory clause recovery on the balance sheet follows:
Regulatory Clause
Balance Sheet Line Item
September 30,
2018
December 31,
2017
 
 
(in millions)
Rate CNP Compliance
Deferred under recovered regulatory clause revenues
$

$
17

 
Under recovered regulatory clause revenues
7


Rate CNP PPA
Deferred under recovered regulatory clause revenues
30

12

Retail Energy Cost Recovery
Deferred under recovered regulatory clause revenues
58

25

 
Under recovered regulatory clause revenues
41


Natural Disaster Reserve
Other regulatory liabilities, deferred
24

38

Regulatory clause recovery balances included in the balance sheets are as follows:
Regulatory Clause
Balance Sheet Line Item
September 30,
2018
December 31,
2017
 
 
(in millions)
Fuel Cost Recovery
Under recovered regulatory clause revenues
$

$
22

Fuel Cost Recovery
Other regulatory liabilities, current
23


Purchased Power Capacity Recovery
Other regulatory liabilities, current
4


Purchased Power Capacity Recovery
Under recovered regulatory clause revenues

2

Environmental Cost Recovery(*)
Other regulatory liabilities, current
13


Environmental Cost Recovery(*)
Under recovered regulatory clause revenues

2

Energy Conservation Cost Recovery
Other regulatory liabilities, current
2


(*)
At September 30, 2018 and December 31, 2017, the over and under recovered balances, respectively, included in the balance sheets represents the current portion of the regulatory assets associated with projected environmental expenditures of approximately $8 million and $13 million, respectively, net of the over recovered environmental cost recovery balance of approximately $21 million and $11 million, respectively.
Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4 by the expected in-service dates of November 2021 and November 2022, respectively, is as follows:
 
(in billions)
Base project capital cost forecast(a)(b)
$
8.0

Construction contingency estimate
0.4

Total project capital cost forecast(a)(b)
8.4

Net investment as of September 30, 2018(b)
(4.3
)
Remaining estimate to complete(a)
$
4.1

(a)
Excludes financing costs expected to be capitalized through AFUDC of approximately $350 million.
(b)
Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related Customer Refunds.