Contingencies and Regulatory Matters - Textual - SO Nuclear Construction (Details)
3 Months Ended 9 Months Ended 12 Months Ended 48 Months Ended 90 Months Ended
Jan. 01, 2021
Jan. 01, 2020
Feb. 28, 2018
USD ($)
Jan. 30, 2018
USD ($)
Jan. 11, 2018
USD ($)
Dec. 08, 2017
payment
Jun. 09, 2017
USD ($)
Dec. 31, 2016
USD ($)
Dec. 20, 2016
USD ($)
Jan. 01, 2016
Feb. 20, 2014
USD ($)
Sep. 30, 2018
USD ($)
installment
Sep. 30, 2017
USD ($)
Dec. 31, 2019
USD ($)
Dec. 31, 2018
USD ($)
Dec. 31, 2017
USD ($)
Dec. 31, 2016
USD ($)
Dec. 31, 2009
USD ($)
utility
MW
Dec. 31, 2022
USD ($)
Dec. 31, 2020
USD ($)
Jun. 30, 2016
USD ($)
Sep. 28, 2017
USD ($)
Mar. 31, 2016
USD ($)
Dec. 31, 2013
Jan. 01, 2013
Loss Contingencies [Line Items]                                                  
Construction work in progress               $ 8,977,000,000               $ 6,904,000,000 $ 8,977,000,000                
Line of credit facility, maximum borrowing capacity                               8,145,000,000                  
GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Number of construction units approved | utility                                   2              
Electric generating capacity in mega watts under construction agreement | MW                                   1,100              
Construction work in progress               4,939,000,000               4,613,000,000 4,939,000,000                
Line of credit facility, maximum borrowing capacity                               1,750,000,000                  
Maximum guarantee                               $ 43,000,000                  
Retail rate of return on common equity                                                 10.95%
Return on equity, potential decrease each month percentage                               10.00%                  
Eligible project costs to be reimbursed                     $ 3,460,000,000                            
GEORGIA POWER CO | Plant Vogtle Units 3 And 4                                                  
Loss Contingencies [Line Items]                                                  
Line of credit facility, maximum borrowing capacity                                             $ 920,000,000    
Plant Vogtle Units 3 And 4                                                  
Loss Contingencies [Line Items]                                                  
Maximum guarantee             $ 3,680,000,000.00                                    
Plant Vogtle Units 3 And 4 | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Percent ownership                               45.70%                  
Cost settlement agreement revised forecast                               $ 8,800,000,000                  
Project capital cost forecast                               7,300,000,000                  
Construction work in progress                               3,300,000,000                  
Construction financing costs               1,600,000,000                                  
Maximum guarantee             $ 1,700,000,000.0                                    
Number of payments made | payment           3                                      
Ownership interest percentage required for voting for continuing construction                         90.00%                        
Increase (decrease) in construction budget                         $ 1,000,000,000                        
Public utilities extension project schedule term                         1 year                        
Percentage of approval required to change primary construction contractor                         90.00%                        
Percentage of approval required for material amendments                         67.00%                        
Estimated in-service capital cost                                   $ 4,418,000,000              
Additional construction capital costs                 $ 3,300,000,000                       $ 4,400,000,000        
Construction In progress, before payments                               4,800,000,000                  
Retail rate of return on common equity                                               10.95%  
Public utilities, approved return on equity                   10.00%                              
Return on equity reduction, negative impact on earnings                               25,000,000 20,000,000                
Production tax credit amount per unit net present value                               500,000,000                  
Scenario, Forecast | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Customer refund                             $ 44,000,000                    
Scenario, Forecast | Plant Vogtle Units 3 And 4 | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Construction financing costs                           $ 3,100,000,000                      
Customer refunds, number of installments | installment                       3                          
Customer refunds, amount per customer                       $ 25                          
Additional construction capital costs     $ 450,000,000                                            
Amendment to estimated in-service capital cost                                       $ 5,680,000,000          
Public utilities, approved return on equity 5.30% 8.30%                                              
Return on equity reduction, negative impact on earnings                             $ 120,000,000       $ 585,000,000            
FFB Loan | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Line of credit facility, maximum borrowing capacity               $ 2,600,000,000               $ 2,600,000,000 $ 2,600,000,000                
Loan Guarantee Agreement | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Credit facility conditional borrowing commitment                                           $ 1,670,000,000      
Subsequent Event | Plant Vogtle Units 3 And 4 | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Increase (decrease) in tariff       $ 50,000,000                                          
Customer refund       $ 188,000,000                                          
Additional construction capital costs         $ 542,000,000                                        
Vogtle Owners [Member] | Plant Vogtle Units 3 And 4 | GEORGIA POWER CO                                                  
Loss Contingencies [Line Items]                                                  
Period of notice required in the event letters of credit are not renewed             30 days