XML 96 R64.htm IDEA: XBRL DOCUMENT v3.7.0.1
Acquisitions - Schedule of Construction Projects (Details) - SOUTHERN POWER CO - MW
1 Months Ended 3 Months Ended
Jan. 06, 2017
Apr. 30, 2017
Mar. 31, 2017
Jun. 30, 2019
Jun. 30, 2017
Bethel          
Business Acquisition [Line Items]          
Approximate Nameplate Capacity (MW) 276        
Southern Power Percentage Ownership 100.00%        
PPA Contract Period 12 years        
East Pecos          
Business Acquisition [Line Items]          
Approximate Nameplate Capacity (MW)         120
PPA Contract Period     15 years    
Lamesa          
Business Acquisition [Line Items]          
Approximate Nameplate Capacity (MW)         102
PPA Contract Period   15 years      
Scenario, Forecast | Mankato          
Business Acquisition [Line Items]          
Approximate Nameplate Capacity (MW)       345  
PPA Contract Period       20 years