Contingencies and Regulatory Matters - Current And Actual Cost Estimate (Details) (Details) - MISSISSIPPI POWER CO - USD ($)
$ in Millions
6 Months Ended 12 Months Ended 38 Months Ended
Nov. 17, 2016
Apr. 08, 2016
Jun. 30, 2017
Dec. 31, 2012
Jun. 30, 2017
Loss Contingencies [Line Items]          
Cost related to grant funding       $ 245  
Maximum cap construction cost       2,880  
Kemper IGCC          
Loss Contingencies [Line Items]          
Estimated cost $ 68   $ 5,680 $ 2,880 $ 2,880
Cost Of Lignite Mine And Equipment     230    
Cost Of CO2 Pipeline Facilities     110    
Cost Of AFUDC     850    
Combined Cycle And Related Assets Placed In Service, Incremental     50    
Plant General Exceptions     80    
Government grants received   $ (137)      
Plant Regulatory Asset     230    
Cost related to grant funding     (140)    
Maximum cap construction cost     7,090    
Deferred costs and other assets     1   1
Project Estimate [Member] | Kemper IGCC          
Loss Contingencies [Line Items]          
Estimated cost     2,400    
Cost Of Lignite Mine And Equipment     210    
Cost Of CO2 Pipeline Facilities     140    
Cost Of AFUDC     170    
Combined Cycle And Related Assets Placed In Service, Incremental     0    
Plant General Exceptions     50    
Plant Regulatory Asset     0    
Cost related to grant funding     0    
Maximum cap construction cost     2,970    
Current Estimate [Member] | Kemper IGCC          
Loss Contingencies [Line Items]          
Estimated cost     5,950    
Cost Of Lignite Mine And Equipment     230    
Cost Of CO2 Pipeline Facilities     110    
Cost Of AFUDC     850    
Combined Cycle And Related Assets Placed In Service, Incremental     50    
Plant General Exceptions     100    
Plant Regulatory Asset     230    
Cost related to grant funding     (140)    
Maximum cap construction cost     7,380    
Deferred costs and other assets     $ 33   $ 33