Contingencies and Regulatory Matters - Current And Actual Cost Estimate (Details) - Mississippi Power [Member] - Kemper IGCC [Member] - USD ($)
$ in Millions
1 Months Ended 9 Months Ended 12 Months Ended
Mar. 31, 2013
Jan. 31, 2013
Sep. 30, 2015
Dec. 31, 2012
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap $ 2,880 $ 2,880 $ 4,660 $ 2,880
Lignite Mine and Equipment     230  
CO2 Pipeline Facilities     110  
AFUDC     550  
Combined Cycle and Related Assets Placed in Service – Incremental     0  
General Exceptions     80  
Deferred Costs     170  
Total Kemper IGCC, Actual Costs     5,800  
Project Estimate [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap     2,400  
Lignite Mine and Equipment     210  
CO2 Pipeline Facilities     140  
AFUDC     170  
Combined Cycle and Related Assets Placed in Service – Incremental     0  
General Exceptions     50  
Deferred Costs     0  
Total Kemper IGCC, Actual Costs     2,970  
Current Estimate [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap     5,110  
Lignite Mine and Equipment     230  
CO2 Pipeline Facilities     110  
AFUDC     660  
Combined Cycle and Related Assets Placed in Service – Incremental     20  
General Exceptions     100  
Deferred Costs     200  
Total Kemper IGCC, Actual Costs     $ 6,430