CONTINGENCIES, COMMITMENTS, AND GUARANTEES - Commitments (Details) - Georgia Power - USD ($)
$ in Millions
12 Months Ended
Dec. 31, 2023
Dec. 31, 2022
Dec. 31, 2021
MEAG Power      
Loss Contingencies [Line Items]      
Percent ownership 5.00%    
Plant Vogtle Units 1 and 2      
Loss Contingencies [Line Items]      
Capacity payments $ 3 $ 4 $ 6
Recorded Unconditional Purchase Obligation, Fiscal Year Maturity Schedule [Abstract]      
Total 39    
Recorded unconditional purchase obligation, year one 4    
Recorded unconditional purchase obligation, year two 4    
Recorded unconditional purchase obligation, year three 2    
Recorded unconditional purchase obligation, year four 2    
Recorded unconditional purchase obligation, year five 2    
Recorded unconditional purchase obligation, after year five $ 25