REGULATORY MATTERS - GPC Schedule of Nuclear Construction Cost and Schedule (Details) - USD ($)
$ in Millions
3 Months Ended 12 Months Ended
Dec. 31, 2023
Sep. 30, 2023
Dec. 31, 2022
Dec. 31, 2023
Dec. 31, 2022
Dec. 31, 2021
Commitments [Line Items]            
Total AFUDC and interest capitalized       $ 400 $ 327 $ 282
Georgia Power            
Commitments [Line Items]            
Pre-tax charge to income   $ 160 $ 407 567    
Total AFUDC and interest capitalized       251 $ 213 $ 190
Georgia Power | Plant Vogtle Units 3 and 4            
Commitments [Line Items]            
Base project capital cost forecast $ 10,717     10,717    
Construction contingency estimate 36     36    
Preliminary estimated cost to complete 10,753     10,753    
Net investment (10,564)     (10,564)    
Remaining estimate to complete 189     189    
Estimated cost to complete, costs not shared with other owners 610     610    
Estimated cost to complete, construction monitoring costs approved for recovery 33     33    
Pre-tax charge to income 228          
Total AFUDC and interest capitalized       440    
Total AFUDC and interest capitalized, accrual amount $ 417     $ 417