REGULATORY MATTERS - GPC Nuclear Construction (Details) - Georgia Power
$ in Millions
3 Months Ended 12 Months Ended
Oct. 17, 2023
USD ($)
Oct. 05, 2023
USD ($)
Dec. 31, 2023
USD ($)
Sep. 30, 2023
USD ($)
Dec. 31, 2022
USD ($)
Dec. 31, 2023
USD ($)
Dec. 31, 2012
utility
MW
Public Utilities, General Disclosures [Line Items]              
Number of construction units approved | utility             2
Electric generating capacity (in MWs) | MW             1,100
Pre-tax charge to income       $ 160 $ 407 $ 567  
After tax charge to income       $ 120 $ 304    
Plant Vogtle Units 3 and 4              
Public Utilities, General Disclosures [Line Items]              
Percent ownership     45.70%     45.70%  
Estimated construction financing costs     $ 3,530     $ 3,530  
Construction financing costs incurred to date     3,500     $ 3,500  
Pre-tax charge to income     228        
After tax charge to income     $ 170        
Additional construction capital costs $ 17 $ 308          
Remaining share of construction costs, agreement to pay, percentage   66.00%       100.00%  
Plant Vogtle Units 3 and 4 | Oglethorpe Power Corporation              
Public Utilities, General Disclosures [Line Items]              
Agreement with third party, expected cost   $ 105          
Plant Vogtle Units 3 and 4 | Dalton Utilities              
Public Utilities, General Disclosures [Line Items]              
Agreement with third party, expected cost $ 6            
Plant Watson Unit 4              
Public Utilities, General Disclosures [Line Items]              
Additional base capital costs per month (up to)           $ 25