Regulatory Matters - GPC Nuclear Construction Regulatory Matters (Details) - Plant Vogtle Units 3 And 4 - GEORGIA POWER CO
$ in Millions
6 Months Ended 9 Months Ended 12 Months Ended
Jan. 01, 2023
USD ($)
Jan. 01, 2021
Jan. 01, 2020
Jan. 11, 2018
USD ($)
Jan. 01, 2018
Jan. 01, 2016
Jun. 30, 2023
USD ($)
Jun. 30, 2022
USD ($)
claim
Sep. 30, 2023
USD ($)
Dec. 31, 2024
USD ($)
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Dec. 31, 2009
USD ($)
Jun. 30, 2021
report
Jun. 30, 2018
USD ($)
Dec. 31, 2013
Public Utilities, General Disclosures [Line Items]                                
Estimated in-service capital cost                         $ 4,418      
Financing costs collected, net of tax                 $ 3,000              
Increase (decrease) in tariff $ 36                              
Additional construction capital costs       $ 3,300                        
Payments for contractor settlement agreement       300                        
Amendment to estimated in-service capital cost       $ 5,680                        
Retail rate of return on common equity                               10.95%
Public utilities, approved return on equity percentage   5.30% 8.30%   10.00% 10.00%                    
Public utilities, approved return on equity, monthly percentage increase (decrease)                 (0.10%)              
Return on equity reduction, negative impact on earnings                 $ 12     $ 300        
Increase to base capital cost forecast not seeking recovery                             $ 700  
Twenty Fourth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Cost settlement agreement revised forecast, net of payments                 7,300              
Twenty Fifth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Number of approved construction management reports | report                           25    
Requested capital construction costs                 7,900              
Guarantor obligations                 1,700              
Customer refund                 $ 188              
Twenty Sixth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Requested capital construction costs               $ 1,600                
Number of additional reports reviewed | claim               3                
Twenty Ninth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Cost settlement agreement revised forecast, net of payments             $ 10,600                  
Requested capital construction costs             $ 390                  
Scenario, Forecast                                
Public Utilities, General Disclosures [Line Items]                                
Return on equity reduction, negative impact on earnings                   $ 60 $ 290