Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - USD ($)
$ in Millions
3 Months Ended 9 Months Ended 12003 Months Ended
Sep. 30, 2023
Sep. 30, 2023
Dec. 31, 2022
Loss Contingencies [Line Items]      
Pre-tax charge to income $ 160   $ 407
Plant Vogtle Units 3 And 4      
Loss Contingencies [Line Items]      
Base project capital cost forecast 10,736 $ 10,736  
Construction contingency estimate 17 17  
Total project capital cost forecast 10,753 10,753  
Net investment as of end of the period (10,495) (10,495)  
Remaining estimate to complete 258 258  
Estimated cost to complete, costs not shared with other owners 610 610  
Estimated cost to complete, construction monitoring costs approved for recovery 33 33  
Pre-tax charge to income     $ 567
Expected capitalized costs   420  
Capitalized interest accrued 385 385  
Plant Vogtle Units 3 And 4 | Twenty Fifth Vogtle Construction Monitoring Report      
Loss Contingencies [Line Items]      
Guarantor obligations $ 1,700 1,700  
Customer refund   $ 188