Regulatory Matters - GPC Nuclear Construction (Details) - GEORGIA POWER CO
$ in Millions
9 Months Ended 12 Months Ended
Sep. 30, 2023
USD ($)
Dec. 31, 2012
utility
MW
Oct. 06, 2023
pump
Sep. 20, 2023
USD ($)
Aug. 31, 2018
Plant Vogtle Units 3 And 4          
Loss Contingencies [Line Items]          
Proportionate ownership share 45.70%        
Number of construction units approved | utility   2      
Electric generating capacity in mega watts under consortium agreement | MW   1,100      
Estimated cost to complete, construction contingency estimate, financing costs $ 3,500        
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date 3,400        
Construction contingency estimate       $ 43  
Monthly AFUDC $ 25        
Percentage of ownership interest required for voting for continuing construction         90.00%
Plant Vogtle Units 3 And 4 | Vogtle Owners          
Loss Contingencies [Line Items]          
Period of notice required in the event letters of credit are not renewed 30 days        
Plant Vogtle Unit 4 | Subsequent Event          
Loss Contingencies [Line Items]          
Number of RPCs | pump     1    
Minimum | Plant Vogtle Units 3 And 4 | COVID-19          
Loss Contingencies [Line Items]          
Loss contingency, estimate of possible loss, loss of productivity, term 3 months        
Maximum | Plant Vogtle Units 3 And 4 | Subsequent Event          
Loss Contingencies [Line Items]          
Number of RPCs | pump     7    
Maximum | Plant Vogtle Units 3 And 4 | COVID-19          
Loss Contingencies [Line Items]          
Loss contingency, estimate of possible loss, loss of productivity, term 4 months        
Estimate of possible loss $ 200        
Maximum | Plant Vogtle Unit 4 | Subsequent Event          
Loss Contingencies [Line Items]          
Number of RPCs | pump     4