XML 76 R48.htm IDEA: XBRL DOCUMENT v3.23.3
Regulatory Matters
9 Months Ended
Sep. 30, 2023
Regulated Operations [Abstract]  
Regulatory Matters REGULATORY MATTERS
See Note 2 to the financial statements in Item 8 of the Form 10-K for additional information relating to regulatory matters.
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at September 30, 2023 and December 31, 2022 were as follows:
Regulatory ClauseBalance Sheet Line ItemSeptember 30,
2023
December 31, 2022
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory liabilities, deferred$3 $— 
Other regulatory assets, current 47 
Rate CNP PPAOther regulatory assets, current17 18 
Other regulatory assets, deferred90 102 
Retail Energy Cost Recovery
Other regulatory assets, current
208 102 
Other regulatory assets, deferred80 520 
Georgia Power
Fuel Cost Recovery(*)
Receivables – under recovered fuel clause revenues
$730 $— 
Deferred under recovered fuel clause revenues1,279 2,056 
Mississippi Power
Fuel Cost Recovery
Receivables – customer accounts, net
$25 $
Ad Valorem Tax
Other regulatory assets, current
3 12 
Other regulatory assets, deferred
11 19 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost under recovery$ $108 
Natural gas cost over recovery165 — 
(*)See "Georgia Power – Fuel Cost Recovery" herein for additional information.
Alabama Power
Certificates of Convenience and Necessity
In 2020, the Alabama PSC approved a certificate of convenience and necessity authorizing Alabama Power's construction of Plant Barry Unit 8 and the recovery of estimated in-service costs of $652 million. At September 30, 2023, project expenditures associated with Plant Barry Unit 8 totaled approximately $583 million, of which $578 million and $5 million was included in CWIP and property, plant, and equipment in service, respectively. On November 1, 2023, the unit was placed in service. The ultimate outcome of this matter cannot be determined at this time.
Excess Accumulated Deferred Income Tax Accounting Order
On October 3, 2023, the Alabama PSC issued an order modifying its December 2022 order and authorizing Alabama Power to (i) flow back in 2023 approximately $24 million of certain federal excess accumulated deferred income taxes resulting from the Tax Cuts and Jobs Act of 2017 and (ii) make available any remaining balance of excess accumulated deferred income taxes at the end of 2023 for the benefit of customers in 2024 and/or 2025. The ultimate outcome of this matter cannot be determined at this time.
Rate CNP New Plant
On March 24, 2023, Alabama Power filed Rate CNP New Plant with the Alabama PSC to recover costs associated with the acquisition of the Central Alabama Generating Station. The filing reflected an annual increase in retail revenues of $78 million effective with June 2023 billings. Through May 2023, Alabama Power recovered substantially all costs associated with the Central Alabama Generating Station through Rate RSE, offset by revenues from a power sales agreement. On May 24, 2023, the Central Alabama Generating Station was placed into retail service. See Note 15 to the financial statements under "Alabama Power" in Item 8 of the Form 10-K for additional information.
Renewable Generation Certificate
Through the issuance of a Renewable Generation Certificate (RGC), Alabama Power is authorized by the Alabama PSC to procure renewable capacity and energy and to market the related energy and environmental attributes to customers and other third parties. On April 4, 2023, the Alabama PSC approved two new solar PPAs totaling 160 MWs. Upon approval of these PPAs, Alabama Power had procured solar capacity totaling approximately 490 MWs under the RGC's original 500-MW limit.
On June 14, 2023, the Alabama PSC issued an order approving modifications to Alabama Power's RGC. The modifications authorized Alabama Power to procure an additional 2,400 MWs of renewable capacity and energy by June 14, 2029 and to market the related energy and environmental attributes to customers and other third parties. The modifications also increased the size of allowable renewable projects from 80 MWs to 200 MWs and increased the annual approval limit from 160 MWs to 400 MWs.
Reliability Reserve Accounting Order
On July 11, 2023, the Alabama PSC issued an order authorizing Alabama Power to expand the existing authority of its reliability reserve to include certain production-related expenses that are intended to maintain reliability in between scheduled generating unit maintenance outages.
On August 18, 2023, Alabama Power notified the Alabama PSC of its intent to use a portion of its $166 million reliability reserve balance during 2023. The ultimate outcome of this matter cannot be determined at this time.
Georgia Power
Rate Plans
In accordance with the terms of the 2022 ARP, on October 2, 2023, Georgia Power filed the following tariff adjustments to become effective January 1, 2024 pending approval by the Georgia PSC:
increase traditional base tariffs by approximately $275 million;
decrease the Environmental Compliance Cost Recovery tariff by approximately $99 million;
increase the Demand-Side Management tariffs by approximately $10 million; and
increase the Municipal Franchise Fee tariffs by approximately $5 million.
The ultimate outcome of this matter cannot be determined at this time.
Plant Vogtle Unit 3 and Common Facilities Rate Proceeding
In compliance with a Georgia PSC order approved in November 2021, Georgia Power increased annual retail base rates by $318 million effective August 1, 2023 based on the in-service date of July 31, 2023 for Plant Vogtle Unit 3. See "Plant Vogtle Units 3 and 4 Prudency Proceeding" and "Nuclear Construction" herein for additional information on Plant Vogtle Units 3 and 4.
Plant Vogtle Units 3 and 4 Prudency Proceeding
On August 30, 2023, as provided for in the December 2017 Georgia PSC approval of the seventeenth VCM report, Georgia Power filed with the Georgia PSC an application to adjust rates to include reasonable and prudent Plant Vogtle Units 3 and 4 costs (Application). The Application provides the necessary support to justify the reasonableness, prudence, and recovery of $8.826 billion in total construction and capital costs, $1.07 billion in associated retail rate base items, and the operating costs related to the full operation and output of Plant Vogtle Units 3 and 4. Through the VCM process, the Georgia PSC has verified and approved all expenditures up to the revised approved construction and capital cost of $7.3 billion and has reviewed, but not verified and approved, all expenditures through December 31, 2022 above that amount.
Also on August 30, 2023, the staff of the Georgia PSC filed a stipulated agreement (Prudency Stipulation) among Georgia Power, the staff of the Georgia PSC, and certain intervenors. The Prudency Stipulation is intended to resolve all issues for determination by the Georgia PSC regarding the reasonableness, prudence, and cost recovery for the remaining costs not already in retail base rates, after considering many of the issues raised by the staff of the Georgia PSC and intervenors in prior VCM proceedings, including the extended construction time, required rework, scheduling of activities, and challenges with testing and productivity. If the Prudency Stipulation is approved, Georgia Power will recover $7.562 billion in total construction and capital costs and associated retail rate base items of $1.02 billion, which includes AFUDC financing costs above $4.418 billion (the Georgia PSC-certified amount) up to $7.562 billion.
The Prudency Stipulation also provides for the recovery of projected operations and maintenance expenses, depreciation expense, nuclear decommissioning accruals, and property taxes, net of projected production tax credits. After considering construction and capital costs already in retail base rates of $2.1 billion and $362 million of associated retail rate base items (approved by the Georgia PSC in November 2021), and upon achieving commercial operation of Unit 4, Georgia Power will include in retail rate base the remaining $5.462 billion of construction and capital costs as well as $656 million of associated retail rate base items.
Under the terms of the Prudency Stipulation, when the rate adjustment occurs, Georgia Power's NCCR tariff will cease to be collected and financing costs will be included in Georgia Power's general revenue requirements. Additionally, if commercial operation for Unit 4 is not achieved by March 31, 2024, Georgia Power's ROE used to determine the NCCR tariff and calculate AFUDC will be reduced to zero, which would result in an estimated negative impact to earnings of approximately $12 million per month until commercial operation for Unit 4 is achieved. The Prudency Stipulation also provides that as of each Unit's respective first refueling outage, if the respective Unit's performance has materially deviated from expected performance, the Georgia PSC may order Georgia Power to credit customers for operations and maintenance expenses or disallow costs associated with the repair or replacement of any system, structure, or component found to have caused the material deviation in performance if proven to be the result of imprudent engineering, construction, procurement, testing, or start-up.
If the Prudency Stipulation is approved by the Georgia PSC, annual retail base revenues will increase approximately $729 million and the average retail base rates will be adjusted by approximately 5% (net of the elimination of the NCCR tariff described above) effective the first day of the month after Unit 4 achieves commercial operation.
Georgia Power expects the Georgia PSC to render a final decision on these matters on December 19, 2023. The ultimate outcome of these matters cannot be determined at this time. See "Plant Vogtle Unit 3 and Common Facilities Rate Proceeding" and "Nuclear Construction" herein for additional information on Plant Vogtle Units 3 and 4.
Fuel Cost Recovery
On May 16, 2023, the Georgia PSC approved a stipulation agreement between Georgia Power and the staff of the Georgia PSC to increase annual fuel billings by 54%, or approximately $1.1 billion, effective June 1, 2023. The increase includes a three-year recovery period for $2.2 billion of Georgia Power's under recovered fuel balance at May 31, 2023. Under the approved stipulation agreement, Georgia Power is allowed to adjust its fuel cost recovery rates under an interim fuel rider prior to the next fuel case, subject to a maximum 40% cumulative change, if its
under or over recovered fuel balance accumulated since May 31, 2023 exceeds $200 million. Georgia Power is scheduled to file its next fuel case no later than February 28, 2026. Changes in fuel rates have no significant effect on Southern Company's or Georgia Power's net income but do impact the related operating cash flows.
Integrated Resource Plans
In August 2022, Restore Chattooga Gorge Coalition (RCG) filed a petition in the Superior Court of Fulton County, Georgia against Georgia Power and the Georgia PSC. The petition challenges Georgia Power's plan to expend $115 million to modernize Plant Tugalo (a hydro facility), as approved in the 2019 IRP, and seeks judicial review of the Georgia PSC's order in the 2022 IRP proceeding with respect to the denial of RCG's challenge to the modernization plan. On October 23, 2023, the court granted Georgia Power's and the Georgia PSC's motions to dismiss the RCG petition. RCG has until November 22, 2023 to file a notice of appeal.
On October 27, 2023, Georgia Power filed an updated IRP (2023 IRP Update) with the Georgia PSC, which sets forth a plan to support the recent increase in the state of Georgia's projected energy needs since the 2022 IRP. In the 2023 IRP Update, Georgia Power requested the following:
Authority to develop, own, and operate up to 1,400 MWs from three simple cycle combustion turbines at Plant Yates.
Approval to pursue potential acquisition of an additional ownership interest in an existing generation asset within the Southern Company system's retail electric service territory.
Certification of an affiliate PPA with Mississippi Power for 750 MWs starting January 2024 through December 2028.
Certification of a non-affiliate PPA for 230 MWs starting the month after conclusion of the 2023 IRP Update proceeding continuing through December 2028.
Authority to develop, own, and operate up to 1,000 MWs of battery energy storage facilities collocated with existing and new Georgia Power-owned solar facilities.
Approval of transmission projects necessary to support the generation resources requested in the 2023 IRP Update.
The schedule for the Georgia PSC to consider the 2023 IRP Update has not been determined. Georgia Power has requested that the Georgia PSC evaluate the 2023 IRP Update by the end of April 2024.
The ultimate outcome of these matters cannot be determined at this time.
Storm Damage Recovery
Georgia Power is recovering $31 million annually under the 2022 ARP for incremental operating and maintenance costs of damage from major storms to its transmission and distribution facilities. During August 2023, Hurricane Idalia caused significant damage to Georgia Power's transmission and distribution facilities. The incremental restoration costs related to this hurricane deferred in the regulatory asset for storm damage totaled approximately $110 million. At September 30, 2023, Georgia Power's regulatory asset balance related to storm damage was $97 million. The rate of storm damage cost recovery is expected to be adjusted in future regulatory proceedings as necessary. As a result of this regulatory treatment, costs related to storms are not expected to have a material impact on Southern Company's or Georgia Power's net income but do impact the related operating cash flows.
Nuclear Construction
In 2009, the Georgia PSC certified construction of Plant Vogtle Units 3 and 4, in which Georgia Power holds a 45.7% ownership interest. In 2012, the NRC issued the related combined construction and operating licenses, which allowed full construction of the two AP1000 nuclear units (with electric generating capacity of approximately 1,100 MWs each) and related facilities to begin. Until March 2017, construction on Plant Vogtle Units 3 and 4 continued under the Vogtle 3 and 4 Agreement, which was a substantially fixed price agreement.
In connection with the EPC Contractor's bankruptcy filing in March 2017, Georgia Power, acting for itself and as agent for the other Vogtle Owners, entered into several transitional arrangements to allow construction to continue. In July 2017, Georgia Power, acting for itself and as agent for the other Vogtle Owners, entered into the Vogtle Services Agreement, whereby Westinghouse provides facility design and engineering services, procurement and technical support, and staff augmentation on a time and materials cost basis. The Vogtle Services Agreement provides that it will continue until the start-up and testing of Plant Vogtle Units 3 and 4 are complete and electricity is generated and sold from both units. The Vogtle Services Agreement is terminable by the Vogtle Owners upon 30 days' written notice.
In October 2017, Georgia Power, acting for itself and as agent for the other Vogtle Owners, executed the Bechtel Agreement, under which Bechtel is reimbursed for actual costs plus a base fee and an at-risk fee, subject to adjustment based on Bechtel's performance against cost and schedule targets. Each Vogtle Owner is severally (not jointly) liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Vogtle Owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Vogtle Owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs, and, at certain stages of the work, the applicable portion of the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including certain Vogtle Owner suspensions of work, certain breaches of the Bechtel Agreement by the Vogtle Owners, Vogtle Owner insolvency, and certain other events.
See Note 8 to the financial statements under "Long-term Debt – DOE Loan Guarantee Borrowings" in Item 8 of the Form 10-K for information on the Amended and Restated Loan Guarantee Agreement, including applicable covenants, events of default, and mandatory prepayment events.
Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through July 2023 and March 2024, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$10,736 
Construction contingency estimate17 
Total project capital cost forecast(a)(b)
10,753 
Net investment at September 30, 2023(b)
(10,495)
Remaining estimate to complete$258 
(a)Includes approximately $610 million of costs that are not shared with the other Vogtle Owners, including $33 million of construction monitoring costs approved for recovery by the Georgia PSC in its nineteenth VCM order, and approximately $567 million of incremental costs under the cost-sharing provisions of the joint ownership agreements described below. Excludes financing costs expected to be capitalized through AFUDC of approximately $420 million, of which $385 million had been accrued through September 30, 2023.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Georgia Power estimates that its financing costs for construction of Plant Vogtle Units 3 and 4 will total approximately $3.5 billion, of which $3.4 billion had been incurred through September 30, 2023.
Georgia Power placed Unit 3 in service on July 31, 2023. See "Plant Vogtle Unit 3 and Common Facilities Rate Proceeding" herein for additional information.
As part of its ongoing processes, Southern Nuclear continues to evaluate cost and schedule forecasts for Unit 4 on a regular basis to incorporate current information available, particularly in the areas of start-up testing and related test results, engineering support, system turnovers, and workforce statistics. Southern Nuclear establishes aggressive target values for monthly testing and system turnover activities, which are reflected in the site work plan for Unit 4.
Since March 2020, the number of active COVID-19 cases at the site has fluctuated consistent with the surrounding area and impacted productivity levels and pace of activity completion, with the site experiencing peaks in the
number of active cases in January 2021, August 2021, and January 2022. Georgia Power estimates the productivity impacts of the COVID-19 pandemic have consumed approximately three to four months of schedule margin previously embedded in the site work plans. As of September 30, 2023, Georgia Power's proportionate share of the estimated incremental cost associated with COVID-19 mitigation actions and impacts on construction productivity is estimated to be approximately $200 million and is included in the total project capital cost forecast.
During the first nine months of 2023, established construction contingency totaling $43 million was assigned to the base capital cost forecast for costs primarily associated with the Unit 3 schedule extension and completion of start-up and pre-operational testing, including continued need of support resources for Unit 3 testing, as well as additional craft and support resources and subcontract work for Unit 4.
Hot functional testing for Unit 4 was completed on May 1, 2023. On July 20, 2023, Southern Nuclear announced that all Unit 4 ITAACs had been submitted to the NRC, and, on July 28, 2023, the NRC published its 103(g) finding that the accepted criteria in the combined license for Unit 4 had been met, which allowed nuclear fuel to be loaded and start-up testing to begin. Fuel load for Unit 4 was completed on August 19, 2023. On October 6, 2023, Georgia Power announced that during the start-up and pre-operational testing for Plant Vogtle Unit 4, Southern Nuclear identified a motor fault in one of four reactor coolant pumps (RCPs) and has started the process to replace this RCP with an on-site spare RCP from inventory. Considering this remediation and the remaining pre-operational testing, Unit 4 is projected to be placed in service during the first quarter 2024.
With Unit 3's four RCPs operating as designed, Southern Nuclear believes that the motor fault on this single Unit 4 RCP is an isolated event. However, any findings related to the root cause of the motor fault on the single Unit 4 RCP could require engineering changes or remediation related to the other seven Unit 3 and Unit 4 RCPs. The projected schedule for Unit 4 significantly depends on the pace and success of replacing the RCP, which involves removing and re-installing commodities around the RCP. As Unit 4 completes the RCP replacement, including any associated repairs to other RCPs, and transitions further into testing, ongoing and potential future challenges include the management of contractors and vendors, subcontractor performance, the availability of materials and parts, and/or related cost escalation; the pace of remaining work package closures; the availability of craft, supervisory, and technical support resources; and the timeframe and duration of final component and pre-operational testing. New challenges also may continue to arise as Unit 4 moves further into testing and start-up, which may result in required engineering changes or remediation related to plant systems, structures, or components (some of which are based on new technology that only within the last few years began initial operation in the global nuclear industry at this scale). These challenges may result in further schedule delays and/or cost increases.
There have been technical and procedural challenges to the construction and licensing of Plant Vogtle Units 3 and 4 at the federal and state level and additional challenges may arise. Processes are in place that are designed to ensure compliance with the requirements specified in the Westinghouse Design Control Document and the combined construction and operating licenses, including inspections by Southern Nuclear and the NRC that occur throughout construction. With the receipt of the NRC's 103(g) findings for Units 3 and 4 in August 2022 and July 2023, respectively, the site is subject to the NRC's operating reactor oversight process and must meet applicable technical and operational requirements contained in its operating license. Various design and other licensing-based compliance matters may result in additional license amendment requests or require other resolution. If any license amendment requests or other licensing-based compliance issues are not resolved in a timely manner, there may be delays in the Unit 4 project schedule that could result in increased costs.
The ultimate outcome of these matters cannot be determined at this time. However, any extension of the in-service date beyond March 2024 for Unit 4, including the joint owner cost sharing impacts described below, is estimated to result in additional base capital costs for Georgia Power of up to $25 million per month, as well as the related AFUDC and any additional related construction, support resources, or testing costs. Pursuant to Georgia Power's Application and the Prudency Stipulation (as discussed under "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein), any further changes to the capital cost forecast are not expected to be recoverable through regulated rates and will be required to be charged to income. Such charges could be material.
Joint Owner Contracts
In November 2017, the Vogtle Owners entered into an amendment to their joint ownership agreements for Plant Vogtle Units 3 and 4 to provide for, among other conditions, additional Vogtle Owner approval requirements. Effective in August 2018, the Vogtle Owners further amended the joint ownership agreements to clarify and provide procedures for certain provisions of the joint ownership agreements related to adverse events that require the vote of the holders of at least 90% of the ownership interests in Plant Vogtle Units 3 and 4 to continue construction (as amended, and together with the November 2017 amendment, the Vogtle Joint Ownership Agreements). The Vogtle Joint Ownership Agreements also confirm that the Vogtle Owners' sole recourse against Georgia Power or Southern Nuclear for any action or inaction in connection with their performance as agent for the Vogtle Owners is limited to removal of Georgia Power and/or Southern Nuclear as agent, except in cases of willful misconduct.
Amendments to the Vogtle Joint Ownership Agreements
In connection with a September 2018 vote by the Vogtle Owners to continue construction, Georgia Power entered into (i) a binding term sheet (Vogtle Owner Term Sheet) with the other Vogtle Owners and MEAG Power's wholly-owned subsidiaries MEAG Power SPVJ, LLC (MEAG SPVJ), MEAG Power SPVM, LLC (MEAG SPVM), and MEAG Power SPVP, LLC (MEAG SPVP) to take certain actions which partially mitigate potential financial exposure for the other Vogtle Owners, including additional amendments to the Vogtle Joint Ownership Agreements and the purchase of PTCs from the other Vogtle Owners at pre-established prices, and (ii) a term sheet (MEAG Term Sheet) with MEAG Power and MEAG SPVJ to provide up to $300 million of funding with respect to MEAG SPVJ's ownership interest in Plant Vogtle Units 3 and 4 under certain circumstances. In January 2019, Georgia Power, MEAG Power, and MEAG SPVJ entered into an agreement to implement the provisions of the MEAG Term Sheet. In February 2019, Georgia Power, the other Vogtle Owners, and MEAG Power's wholly-owned subsidiaries MEAG SPVJ, MEAG SPVM, and MEAG SPVP entered into certain amendments to the Vogtle Joint Ownership Agreements to implement the provisions of the Vogtle Owner Term Sheet (Global Amendments).
Pursuant to the Global Amendments: (i) each Vogtle Owner paid its proportionate share of qualifying construction costs for Plant Vogtle Units 3 and 4 based on its ownership percentage up to the estimated cost at completion (EAC) for Plant Vogtle Units 3 and 4, of which Georgia Power's share is $8.4 billion (VCM 19 Forecast Amount), plus $800 million; (ii) Georgia Power was responsible for 55.7% of actual qualifying construction costs between $800 million and $1.6 billion over the VCM 19 Forecast Amount (resulting in $80 million of potential additional costs to Georgia Power), with the remaining Vogtle Owners responsible for 44.3% of such costs pro rata in accordance with their respective ownership interests; and (iii) Georgia Power was responsible for 65.7% of qualifying construction costs between $1.6 billion and $2.1 billion over the VCM 19 Forecast Amount (resulting in a further $100 million of potential additional costs to Georgia Power), with the remaining Vogtle Owners responsible for 34.3% of such costs pro rata in accordance with their respective ownership interests. The Global Amendments provide that if the EAC was revised and exceeded the VCM 19 Forecast Amount by more than $2.1 billion, each of the other Vogtle Owners had a one-time option at the time the project budget cost forecast was so revised to tender a portion of its ownership interest to Georgia Power in exchange for Georgia Power's agreement to pay 100% of such Vogtle Owner's remaining share of total construction costs in excess of the VCM 19 Forecast Amount plus $2.1 billion.
In addition, pursuant to the Global Amendments, the holders of at least 90% of the ownership interests in Plant Vogtle Units 3 and 4 must vote to continue construction if certain adverse events (Project Adverse Events) occur, including, among other events: (i) the bankruptcy of Toshiba; (ii) the termination or rejection in bankruptcy of certain agreements, including the Vogtle Services Agreement, the Bechtel Agreement, or the agency agreement with Southern Nuclear; (iii) Georgia Power's public announcement of its intention not to submit for rate recovery any portion of its investment in Plant Vogtle Units 3 and 4 or the Georgia PSC determines that any of Georgia Power's costs relating to the construction of Plant Vogtle Units 3 and 4 will not be recovered in retail rates, excluding any additional amounts paid by Georgia Power on behalf of the other Vogtle Owners pursuant to the Global Amendments described above and the first 6% of costs during any six-month VCM reporting period that are disallowed by the Georgia PSC for recovery, or for which Georgia Power elects not to seek cost recovery, through retail rates; and (iv) an incremental extension of one year or more from the seventeenth VCM report estimated in-
service dates of November 2021 and November 2022 for Units 3 and 4, respectively. The schedule extension announced in February 2022 triggered the requirement for a vote to continue construction and all the Vogtle Owners voted to continue construction. The filing of the Application with the Georgia PSC, which included Georgia Power's public announcement of its intention not to submit for rate recovery an amount that is greater than the first 6% of costs during any six-month VCM reporting period, triggered the requirement for a vote to continue construction and all the Vogtle Owners voted to continue construction. See "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein for additional information on Georgia Power's prudency application filing.
Georgia Power and the other Vogtle Owners did not agree on either the starting dollar amount for the determination of cost increases subject to the cost-sharing and tender provisions of the Global Amendments or the extent to which COVID-19-related costs impact those provisions. The other Vogtle Owners notified Georgia Power that they believed the project capital cost forecast approved by the Vogtle Owners in February 2022 triggered the tender provisions. In June 2022 and July 2022, OPC and Dalton, respectively, notified Georgia Power of their purported exercises of their tender options. Georgia Power did not accept these purported tender exercises.
In June 2022, OPC and MEAG Power each filed a separate lawsuit against Georgia Power in the Superior Court of Fulton County, Georgia seeking a declaratory judgment that the starting dollar amount is $17.1 billion and that the cost-sharing and tender provisions had been triggered. The lawsuits also assert other claims, including breach of contract allegations, and seek, among other remedies, damages and injunctive relief requiring Georgia Power to track and allocate construction costs consistent with MEAG Power's and OPC's interpretations of the Global Amendments. In July 2022, Georgia Power filed its answers in the lawsuits filed by MEAG Power and OPC and included counterclaims seeking a declaratory judgment that the starting dollar amount is $18.38 billion and that costs related to force majeure events are excluded prior to calculating the cost-sharing and tender provisions and when calculating Georgia Power's related financial obligations. In September 2022, Dalton filed complaints in each of these lawsuits.
Also in September 2022, Georgia Power and MEAG Power reached an agreement to resolve their dispute regarding the proper interpretation of the cost-sharing and tender provisions of the Global Amendments. Under the terms of the agreement, among other items, (i) MEAG Power will not exercise its tender option and will retain its full ownership interest in Plant Vogtle Units 3 and 4; (ii) Georgia Power will reimburse a portion of MEAG Power's costs of construction for Plant Vogtle Units 3 and 4 as such costs are incurred and with no further adjustment for force majeure costs, which payments will total approximately $92 million based on the current project capital cost forecast; and (iii) Georgia Power will reimburse 20% of MEAG Power's costs of construction with respect to any amounts over the current project capital cost forecast, with no further adjustment for force majeure costs. In addition, MEAG Power agreed to vote to continue construction upon occurrence of a Project Adverse Event unless the commercial operation date of either of Plant Vogtle Unit 3 or Unit 4 is not projected to occur by December 31, 2025. In October 2022, MEAG Power and Georgia Power filed a notice of settlement and voluntary dismissal of their pending litigation, including Georgia Power's counterclaim, and Dalton dismissed its related complaint.
On October 5, 2023 and October 17, 2023, Georgia Power reached agreements with OPC and Dalton, respectively, to resolve its respective dispute with each of OPC and Dalton regarding the proper interpretation of the cost-sharing and tender provisions of the joint ownership agreements relating to the Global Amendments. Under the terms of the agreements with OPC and Dalton, among other items, (i) each of OPC and Dalton retracted its exercise of the tender option and will retain its full ownership interest in Plant Vogtle Units 3 and 4, (ii) Georgia Power made payments immediately after execution of the agreements of $308 million and $17 million to OPC and Dalton, respectively, representing payment for a portion of each of OPC's and Dalton's costs of construction for Plant Vogtle Units 3 and 4 previously incurred, (iii) Georgia Power will pay a portion of each of OPC's and Dalton's further costs of construction for Plant Vogtle Units 3 and 4 as such costs are incurred and with no further adjustment for force majeure costs, which payments will be in an aggregate amount of approximately $105 million and $6 million for OPC and Dalton, respectively, based on the current project capital cost forecast, and (iv) Georgia Power will pay 66% of each of OPC's and Dalton's costs of construction with respect to any amounts above the current project capital cost forecast, with no further adjustment for force majeure costs. On October 23, 2023, OPC, Dalton, and
Georgia Power filed a stipulation of dismissal with prejudice of their litigation described above, including Georgia Power's counterclaims.
Georgia Power recorded pre-tax charges to income through the fourth quarter 2022 of $407 million ($304 million after tax) associated with the cost-sharing provisions of the Global Amendments, including the settlement with MEAG Power. Based on the current project capital cost forecast and the settlements with OPC and Dalton described above, Georgia Power recorded a pre-tax charge to income of approximately $160 million ($120 million after tax) in the third quarter 2023. These charges are included in the total project capital cost forecast and will not be recovered from retail customers.
The ultimate outcome of these matters cannot be determined at this time.
Regulatory Matters
In 2009, the Georgia PSC voted to certify construction of Plant Vogtle Units 3 and 4 with a certified capital cost of $4.418 billion. In addition, in 2009 the Georgia PSC approved inclusion of the Plant Vogtle Units 3 and 4 related CWIP accounts in rate base, and the State of Georgia enacted the Georgia Nuclear Energy Financing Act, which allows Georgia Power to recover financing costs for Plant Vogtle Units 3 and 4. Financing costs are recovered on all applicable certified costs through annual adjustments to the NCCR tariff up to the certified capital cost of $4.418 billion. At September 30, 2023, Georgia Power had recovered approximately $3.0 billion of financing costs. Financing costs related to capital costs above $4.418 billion are being recognized through AFUDC and are expected to be recovered through retail rates over the life of Plant Vogtle Units 3 and 4; however, Georgia Power is not recording AFUDC related to any capital costs in excess of the total deemed reasonable by the Georgia PSC (currently $7.3 billion) and not requested for rate recovery. In December 2022, the Georgia PSC approved Georgia Power's filing to increase the NCCR tariff by $36 million annually, effective January 1, 2023. On November 1, 2023, Georgia Power filed a request to continue the current NCCR tariff for 2024, pending Georgia PSC approval. See "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein for additional information on the NCCR tariff following commercial operation of Unit 4.
Georgia Power is required to file semi-annual VCM reports with the Georgia PSC by February 28 and August 31 of each year. In 2013, in connection with the eighth VCM report, the Georgia PSC approved a stipulation between Georgia Power and the staff of the Georgia PSC to waive the requirement to amend the Plant Vogtle Units 3 and 4 certificate in accordance with the 2009 certification order until the completion of Plant Vogtle Unit 3, or earlier if deemed appropriate by the Georgia PSC and Georgia Power.
In 2016, the Georgia PSC voted to approve a settlement agreement (Vogtle Cost Settlement Agreement) resolving certain prudency matters in connection with the fifteenth VCM report. In December 2017, the Georgia PSC voted to approve (and issued its related order on January 11, 2018) Georgia Power's seventeenth VCM report and modified the Vogtle Cost Settlement Agreement. The Vogtle Cost Settlement Agreement, as modified by the January 11, 2018 order, resolved the following regulatory matters related to Plant Vogtle Units 3 and 4: (i) none of the $3.3 billion of costs incurred through December 31, 2015 and reflected in the fourteenth VCM report should be disallowed from rate base on the basis of imprudence; (ii) the Contractor Settlement Agreement was reasonable and prudent and none of the $0.3 billion paid pursuant to the Contractor Settlement Agreement should be disallowed from rate base on the basis of imprudence; (iii) (a) capital costs incurred up to $5.68 billion would be presumed to be reasonable and prudent with the burden of proof on any party challenging such costs, (b) Georgia Power would have the burden to show that any capital costs above $5.68 billion were prudent, and (c) a revised capital cost forecast of $7.3 billion (after reflecting the impact of payments received under the Guarantee Settlement Agreement and related customer refunds) was found reasonable; (iv) construction of Plant Vogtle Units 3 and 4 should be completed, with Southern Nuclear serving as project manager and Bechtel as primary contractor; (v) approved and deemed reasonable Georgia Power's revised schedule placing Plant Vogtle Units 3 and 4 in service in November 2021 and November 2022, respectively; (vi) confirmed that the revised cost forecast does not represent a cost cap and that a prudence proceeding on cost recovery will occur following Unit 4 fuel load, consistent with applicable Georgia law; (vii) reduced the ROE used to calculate the NCCR tariff (a) from 10.95% (the ROE rate setting point authorized by the Georgia PSC at that time) to 10.00% effective January 1, 2016, (b) from 10.00% to 8.30%,
effective January 1, 2020, and (c) from 8.30% to 5.30%, effective January 1, 2021 (provided that the ROE in no case will be less than Georgia Power's average cost of long-term debt); (viii) reduced the ROE used for AFUDC equity for Plant Vogtle Units 3 and 4 from 10.00% to Georgia Power's average cost of long-term debt, effective January 1, 2018; and (ix) agreed that effective the first month after Unit 3 reaches commercial operation, retail base rates would be adjusted to include the costs related to Unit 3 and common facilities deemed prudent in the Vogtle Cost Settlement Agreement. On July 31, 2023, Georgia Power notified the Georgia PSC that Unit 3 had reached commercial operation, and, effective August 1, 2023, Georgia Power adjusted retail base rates for Unit 3 and the common facilities shared between Units 3 and 4 (see "Plant Vogtle Unit 3 and Common Facilities Rate Proceeding" herein for additional information). On August 19, 2023, fuel load for Unit 4 was completed, and, on August 30, 2023, Georgia Power filed an application to adjust rates to include reasonable and prudent Plant Vogtle Units 3 and 4 costs (see "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein for additional information).
The January 11, 2018 order also stated that if Plant Vogtle Units 3 and 4 are not commercially operational by June 1, 2021 and June 1, 2022, respectively, the ROE used to calculate the NCCR tariff will be further reduced by 10 basis points each month (but not lower than Georgia Power's average cost of long-term debt) until the respective Unit is commercially operational. The ROE reductions negatively impacted earnings by approximately $300 million in 2022 and are estimated to have negative earnings impacts of approximately $290 million in 2023 and $60 million in 2024. In its January 11, 2018 order, the Georgia PSC also stated if other conditions change and assumptions upon which Georgia Power's seventeenth VCM report are based do not materialize, the Georgia PSC reserved the right to reconsider the decision to continue construction. See "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein for additional information on impacts to the NCCR tariff if commercial operation for Unit 4 is not achieved by March 31, 2024.
In the August 2021 order approving the twenty-fourth VCM report, the Georgia PSC approved a stipulation addressing the following matters: (i) beginning with its twenty-fifth VCM report, Georgia Power will continue to report to the Georgia PSC all costs incurred during the period for review and will request for approval costs up to the $7.3 billion determined to be reasonable in the Georgia PSC's seventeenth VCM order and (ii) Georgia Power will not seek rate recovery of the $0.7 billion increase to the base capital cost forecast included in the nineteenth VCM report and charged to income by Georgia Power in the second quarter 2018. In addition, the August 2021 stipulation confirmed that Georgia Power may request verification and approval of costs above $7.3 billion for inclusion in rate base at a later time, but no earlier than the prudence review contemplated by the seventeenth VCM order described previously. See "Plant Vogtle Units 3 and 4 Prudency Proceeding" herein for additional information on Georgia Power's request for verification and approval of costs above $7.3 billion for inclusion in rate base.
The Georgia PSC approved 25 VCM reports covering periods through June 30, 2021. These reports reflect total construction capital costs incurred of $7.9 billion (net of $1.7 billion of payments received under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds), of which the Georgia PSC has verified and approved $7.3 billion as described above. The Georgia PSC also has reviewed three additional VCM reports, which reflected $1.6 billion of additional construction capital costs incurred through December 31, 2022. Georgia Power filed its twenty-ninth VCM report with the Georgia PSC on August 30, 2023, which reflects the revised capital cost forecast as of June 30, 2023 of $10.6 billion and $390 million of construction capital costs incurred from January 1, 2023 through June 30, 2023.
The ultimate outcome of these matters cannot be determined at this time.
Mississippi Power
Performance Evaluation Plan
On June 13, 2023, the Mississippi PSC approved Mississippi Power's annual retail PEP filing for 2023 indicating no change in retail rates.
Ad Valorem Tax Adjustment
On May 2, 2023, the Mississippi PSC approved Mississippi Power's annual ad valorem tax adjustment filing for 2023, resulting in a $7 million annual decrease in revenues effective with the first billing cycle of June 2023.
Mississippi Power's operating revenues are adjusted for differences in actual recoverable ad valorem taxes and amounts billed in accordance with the currently approved cost recovery rate. Accordingly, changes in the billing factor should have no significant effect on Mississippi Power's revenues or net income but will affect operating cash flows.
Environmental Compliance Overview Plan
On April 4, 2023, the Mississippi PSC approved Mississippi Power's annual ECO Plan filing for 2023, resulting in a $3 million annual increase in revenues effective with the first billing cycle of May 2023.
System Restoration Rider
On April 4, 2023, the Mississippi PSC approved Mississippi Power's annual SRR filing, which indicated no change in retail rates. Mississippi Power's minimum annual SRR accrual was increased from $8 million to $12 million.
Municipal and Rural Associations Tariff
On October 27, 2023, the FERC approved a settlement agreement filed by Mississippi Power and Cooperative Energy on July 31, 2023 related to Mississippi Power's July 2022 request for a $23 million increase in annual wholesale base revenues under the MRA tariff. The settlement agreement provides for a $16 million increase in annual wholesale base revenues, effective September 14, 2022, and a refund to customers of approximately $6 million primarily related to the difference between the approved rates and interim rates.
Integrated Resource Plans
In October 2023, Mississippi Power signed an affiliate PPA with Georgia Power for 750 MWs of capacity and energy starting January 2024 through December 2028. In order to fulfill this agreement and serve the interests of customers, Mississippi Power will need to delay the anticipated retirement of certain electric generating units, as identified in its 2021 IRP. Mississippi Power is expected to file its next IRP in April 2024 in accordance with the rules and orders of the Mississippi PSC.
Southern Company Gas
Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs and capital projects during the first nine months of 2023 were as follows:
UtilityProgram
Nine Months
Ended
September 30, 2023
(in millions)
Nicor GasInvesting in Illinois$320 
Virginia Natural GasSAVE56 
Atlanta Gas LightSystem Reinforcement Rider84 
Chattanooga GasPipeline Replacement Program
Total$467 
Nicor Gas
On June 15, 2023, the Illinois Commission concluded its review of the Qualifying Infrastructure Plant (QIP) capital investments by Nicor Gas for calendar year 2019 under the QIP Rider, also referred to as Investing in Illinois, program. The Illinois Commission disallowed $32 million of the $415 million of capital investments commissioned in 2019, together with the related return on investment. Nicor Gas recorded a pre-tax charge to income in the second quarter 2023 of $38 million ($28 million after tax) associated with the disallowance of capital investments. The disallowance is reflected on the statement of income as an $8 million reduction to revenues and a $30 million increase in operating expenses. On August 3, 2023, the Illinois Commission denied a rehearing request filed by Nicor Gas. On August 24, 2023, Nicor Gas filed a notice of appeal with the Illinois Appellate Court. Nicor Gas defends these investments in infrastructure as prudently incurred. The Illinois Commission has not yet conducted its review for calendar years 2020 through 2022 or the nine months ended September 30, 2023. Any further disallowance by the Illinois Commission could be material. The ultimate outcome of these matters cannot be determined at this time.
Rate Proceedings
Atlanta Gas Light
On July 14, 2023, Atlanta Gas Light filed its annual GRAM update with the Georgia PSC. The filing requests an annual base rate increase of $53 million based on the projected 12-month period beginning January 1, 2024. Resolution of the GRAM filing is expected by December 31, 2023, with new rates effective January 1, 2024. The ultimate outcome of this matter cannot be determined at this time.
Virginia Natural Gas
On August 28, 2023, the Virginia Commission approved a stipulation agreement related to Virginia Natural Gas' August 2022 general base rate case filing. The approved agreement provides for a $48 million increase in annual base rate revenues, including the recovery of investments under the SAVE program, an ROE of 9.70%, and an equity ratio of 49.06%. Interim rates became effective January 1, 2023, subject to refund, based on Virginia Natural Gas' original requested increase of approximately $69 million. Refunds to customers related to the difference between the approved rates effective September 1, 2023 and the interim rates will be completed later in the fourth quarter 2023.