Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - USD ($)
$ in Millions
3 Months Ended
Mar. 31, 2023
Dec. 31, 2022
Loss Contingencies [Line Items]    
Pre-tax charge to income   $ 407
Plant Vogtle Units 3 And 4    
Loss Contingencies [Line Items]    
Base project capital cost forecast $ 10,553  
Construction contingency estimate 40  
Total project capital cost forecast 10,593  
Net investment as of end of the period (9,747)  
Remaining estimate to complete 846  
Estimated cost to complete, costs not shared with other owners 610  
Estimated cost to complete, construction monitoring costs approved for recovery 33  
Expected capitalized costs 418  
Capitalized interest accrued 334  
Plant Vogtle Units 3 And 4 | Twenty Fifth Vogtle Construction Monitoring Report    
Loss Contingencies [Line Items]    
Guarantor obligations 1,700  
Customer refund $ 188