XML 53 R26.htm IDEA: XBRL DOCUMENT v3.21.2
Regulatory Matters (Tables)
6 Months Ended
Jun. 30, 2021
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at June 30, 2021 and December 31, 2020 were as follows:
Regulatory ClauseBalance Sheet Line ItemJune 30,
2021
December 31, 2020
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory liabilities, current$1 $28 
Rate CNP PPAOther regulatory assets, deferred64 58 
Retail Energy Cost RecoveryOther regulatory liabilities, current 18 
Other regulatory assets, deferred54 — 
Natural Disaster ReserveOther regulatory liabilities, deferred36 77 
Georgia Power
Fuel Cost Recovery
Over recovered fuel clause revenues
$ $113 
Other deferred charges and assets21 — 
Mississippi Power
Fuel Cost Recovery
Over recovered regulatory clause liabilities
$9 $24 
Ad Valorem Tax
Other regulatory assets, current
12 11 
Other regulatory assets, deferred
45 41 
Property Damage Reserve
Other regulatory liabilities, deferred
 
Other regulatory assets, deferred
5 — 
Southern Company Gas
Natural Gas Cost Recovery(*)
Other regulatory liabilities
$5 $88 
Natural gas cost under recovery485 — 
Other regulatory assets, deferred119 — 
(*)The significant change during the six months ended June 30, 2021 was primarily driven by an increase in the cost of gas purchased in February 2021 resulting from Winter Storm Uri.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through June 2022 and March 2023, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$9,096 
Construction contingency estimate119 
Total project capital cost forecast(a)(b)
9,215 
Net investment at June 30, 2021(b)
(7,856)
Remaining estimate to complete$1,359 
(a)    Includes approximately $570 million of costs that are not shared with the other Vogtle Owners. Excludes financing costs expected to be capitalized through AFUDC of approximately $290 million, of which $143 million had been accrued through June 30, 2021.
(b)    Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs during the first six months of 2021 were as follows:
UtilityProgramSix Months Ended June 30, 2021
(in millions)
Nicor GasInvesting in Illinois$179 
Virginia Natural GasSteps to Advance Virginia's Energy22 
Total$201