XML 63 R36.htm IDEA: XBRL DOCUMENT v3.5.0.2
Contingencies and Regulatory Matters - Current And Actual Cost Estimate (Details) - Mississippi Power [Member] - USD ($)
$ in Millions
9 Months Ended 12 Months Ended
Apr. 08, 2016
Sep. 30, 2016
Dec. 31, 2012
Dec. 03, 2015
Loss Contingencies [Line Items]        
Additional DOE Grants     $ 245  
Kemper IGCC [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap   $ 5,300 2,880  
Lignite Mine and Equipment   230    
CO2 Pipeline Facilities   110    
AFUDC   710    
Combined Cycle and Related Assets Placed in Service – Incremental   30    
General Exceptions   90    
Deferred Costs   200    
Additional DOE Grants   (140)    
Total Kemper IGCC, Actual Costs   $ 6,530    
Purchase of Interest   100.00%   15.00%
Government grants received $ 137      
Project Estimate [Member] | Kemper IGCC [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap   $ 2,400    
Lignite Mine and Equipment   210    
CO2 Pipeline Facilities   140    
AFUDC   170    
Combined Cycle and Related Assets Placed in Service – Incremental   0    
General Exceptions   50    
Deferred Costs   0    
Additional DOE Grants   0    
Total Kemper IGCC, Actual Costs   2,970    
Current Estimate [Member] | Kemper IGCC [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap   5,520    
Lignite Mine and Equipment   230    
CO2 Pipeline Facilities   110    
AFUDC   750    
Combined Cycle and Related Assets Placed in Service – Incremental   40    
General Exceptions   100    
Deferred Costs   210    
Additional DOE Grants   (140)    
Total Kemper IGCC, Actual Costs   $ 6,820    
Maximum [Member] | Kemper IGCC [Member]        
Loss Contingencies [Line Items]        
Plant Subject to Cost Cap     $ 2,880