Regulatory Matters (Regulatory Matters Narrative - Duke Energy Florida) (Details) - Duke Energy Florida
3 Months Ended 12 Months Ended
Oct. 17, 2022
USD ($)
Oct. 04, 2022
USD ($)
Jun. 15, 2022
USD ($)
May 04, 2021
USD ($)
Jul. 01, 2020
USD ($)
plant
MW
Mar. 31, 2023
USD ($)
Dec. 31, 2034
USD ($)
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Sep. 28, 2022
outage
Sep. 27, 2022
USD ($)
Apr. 11, 2022
USD ($)
Solar Project                        
Public Utilities, General Disclosures [Line Items]                        
Estimated cost of facilities         $ 1,000,000,000              
FPSC                        
Public Utilities, General Disclosures [Line Items]                        
Number of solar plants | plant         10              
Generation capacity (MW) | MW         750              
FPSC | Hurricane Ian                        
Public Utilities, General Disclosures [Line Items]                        
Number of outages | outage                   1,100,000    
Deferred storm coats           $ 357,000,000            
Storm reserves                 $ 132,000,000   $ 107,000,000  
Interim recovery payments           442,000,000            
2021 Settlement | FPSC                        
Public Utilities, General Disclosures [Line Items]                        
Approved rate increase (decrease), amount           67,000,000            
Public utilities, approved equity capital structure, percentage (as a percent)       53.00%                
Public utilities, approved debt capital structure, percentage       47.00%                
Public utilities, basis points, increase, percentage       0.25%                
Contract with customer, asset, after allowance for credit loss, noncurrent     $ 154,000,000 $ 173,000,000   $ 54,000,000            
Proceeds from legal settlements     $ 180,000,000                  
Requested rate increase (decrease), amount $ (56,000,000)                      
Future investment in infrastructure       $ 1,000,000,000                
2021 Settlement | FPSC | US Treasury Securities                        
Public Utilities, General Disclosures [Line Items]                        
Public utilities, basis points, increase, percentage       0.50%                
2021 Settlement | FPSC | Minimum                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity percentage (as a percent)       8.85%                
2021 Settlement | FPSC | Minimum | US Treasury Securities                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity percentage (as a percent)       9.85%                
2021 Settlement | FPSC | Maximum                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity percentage (as a percent)       10.85%                
2021 Settlement | FPSC | Maximum | US Treasury Securities                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity percentage (as a percent)       10.10%                
2021 Settlement | FPSC | Weighted Average                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity percentage (as a percent)       9.85%                
2021 Settlement | FPSC | Forecast                        
Public Utilities, General Disclosures [Line Items]                        
Approved rate increase (decrease), amount             $ 79,000,000 $ 49,000,000        
Contract with customer, asset, after allowance for credit loss, noncurrent               $ 119,000,000        
Storm Protection Plan | FPSC                        
Public Utilities, General Disclosures [Line Items]                        
Investment in transmission and distribution                       $ 7,000,000,000
Cost reduction to transmission loop   $ 80,000,000                    
Cost reduction period (in years)   10 years