Commitments and Contingencies (Planned Capital Expenditures) (Details)
$ in Millions
3 Months Ended
Mar. 31, 2023
USD ($)
MW
Planned Capital Expenditures [Line Items]  
Guarantor obligations, current carrying value $ 493
Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 6,465
2024 8,080
2025 8,225
2026 8,875
2027 8,940
Total 40,585
NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 7,725
2024 3,550
2025 1,435
2026 600
2027 505
Total 13,815
New Generation Expenditures [Member] | Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 2,810
2024 2,315
2025 2,820
2026 3,670
2027 3,150
Total 14,765
Allowance for funds used during construction (AFUDC) - remainder of 2023 100
Allowance for funds used during construction (AFUDC) - 2024 105
Allowance for funds used during construction (AFUDC) - 2025 90
Allowance for funds used during construction (AFUDC) - 2026 125
Allowance for funds used during construction (AFUDC) - 2027 115
Existing Generation Expenditures [Member] | Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 1,110
2024 1,175
2025 1,045
2026 1,280
2027 1,465
Total 6,075
Transmission And Distribution Expenditures [Member] | Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 1,945
2024 3,975
2025 3,645
2026 3,340
2027 3,575
Total 16,480
Allowance for funds used during construction (AFUDC) - remainder of 2023 40
Allowance for funds used during construction (AFUDC) - 2024 50
Allowance for funds used during construction (AFUDC) - 2025 55
Allowance for funds used during construction (AFUDC) - 2026 30
Allowance for funds used during construction (AFUDC) - 2027 30
Nuclear Fuel Expenditures [Member] | Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 90
2024 160
2025 200
2026 200
2027 225
Total 875
General And Other Expenditures [Member] | Florida Power & Light Company  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 510
2024 455
2025 515
2026 385
2027 525
Total 2,390
Wind Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 2,750
2024 1,320
2025 625
2026 50
2027 40
Total $ 4,785
Planned new generation over 5 year period (in megawatts) | MW 3,081
Solar Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 $ 3,365
2024 1,320
2025 240
2026 5
2027 5
Total $ 4,935
Planned new generation over 5 year period (in megawatts) | MW 6,890
Other Clean Energy | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 $ 705
2024 300
2025 80
2026 90
2027 15
Total 1,190
Nuclear Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 140
2024 230
2025 220
2026 225
2027 295
Total 1,110
Rate-Regulated Transmission [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 185
2024 105
2025 95
2026 70
2027 20
Total 475
Other Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
Remainder of 2023 580
2024 275
2025 175
2026 160
2027 130
Total $ 1,320