XML 72 R51.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies (Long-term Purchase Commitment) (Details)
$ in Millions
1 Months Ended 3 Months Ended
Jan. 31, 2018
USD ($)
MW
Mar. 31, 2018
USD ($)
MW
Mar. 31, 2017
USD ($)
Dec. 31, 2017
USD ($)
FPL [Member]        
Required capacity and/or minimum payments [Abstract]        
Capacity payments   $ 5 $ 20  
Energy payments   $ 7 $ 16  
FPL [Member] | Pay-for-Performance Contracts [Member]        
Long-term Purchase Commitment [Line Items]        
Minimum total purchase commitments (in megawatts) | MW   114    
FPL [Member] | Take-or-Pay Contract Range 1 [Member]        
Long-term Purchase Commitment [Line Items]        
Minimum annual purchase commitments (in megawatts) | MW 375      
FPL [Member] | Capacity Charges [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   $ 15    
2019   20    
2020   20    
2021   20    
2022   20    
Thereafter   225    
FPL [Member] | Natural Gas, Including Transportation And Storage, Contract Minimum Payments [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   1,485    
2019   980    
2020   940    
2021   905    
2022   895    
Thereafter   11,240    
FPL [Member] | Coal Contract Minimum Payments [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   30    
2019   5    
2020   0    
2021   0    
2022   0    
Thereafter   0    
FPL [Member] | Sabal Trail and Florida Southeast Connection [Member] | Natural Gas, Including Transportation And Storage, Contract Minimum Payments [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   220    
2019   290    
2020   360    
2021   390    
2022   390    
Thereafter   7,175    
NextEra Energy Resources [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   2,145    
2019   540    
2020   175    
2021   145    
2022   170    
Thereafter   1,330    
NextEra Energy Resources [Member] | Contract Group 1 [Member]        
Long-term Purchase Commitment [Line Items]        
Commitment amount included in capital expenditures   2,900    
NextEra Energy Resources [Member] | Mountain Valley Pipeline [Member]        
Required capacity and/or minimum payments [Abstract]        
2019   65    
2020   65    
2021   65    
2022   65    
Thereafter   $ 1,035    
Equity method investment, ownership percentage   31.00%    
Corporate and Other [Member]        
Required capacity and/or minimum payments [Abstract]        
Remainder of 2018   $ 205    
2019   15    
2020   15    
2021   10    
2022   0    
Thereafter   0    
Commitment to invest   70    
Joint obligations of NEECH and NEER included NEER amounts due in the current year   $ 170    
Jointly Owned Electricity Generation Plant [Member] | FPL [Member]        
Long-term Purchase Commitment [Line Items]        
Public utilities, termination of operations, payment $ 90      
Proportionate ownership percentage 20.00%      
Regulatory asset $ 150      
Plant in service, net book value $ 191      
Regulatory asset amortization period (in years) 15 years      
Regulatory liabilities       $ 62
Jointly Owned Electricity Generation Plant [Member] | JEA [Member]        
Long-term Purchase Commitment [Line Items]        
Proportionate ownership percentage 80.00%      
Jointly Owned Electricity Generation Plant [Member] | Take-or-Pay Purchased Power Contract [Member] | FPL [Member]        
Long-term Purchase Commitment [Line Items]        
Regulatory asset       $ 90
Jointly Owned Electricity Generation Plant [Member] | Environmental Cost Recovery [Member] | FPL [Member]        
Long-term Purchase Commitment [Line Items]        
Regulatory asset amortization period (in years) 10 years