XML 53 R28.htm IDEA: XBRL DOCUMENT v3.4.0.3
Commitments and Contingencies (Tables)
3 Months Ended
Mar. 31, 2016
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
At March 31, 2016, estimated capital expenditures for the remainder of 2016 through 2020 for which applicable internal approvals (and also FPSC approvals for FPL, if required) have been received were as follows:
 
Remainder of 2016
 
2017
 
2018
 
2019
 
2020
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
850

 
$
60

 
$
5

 
$
5

 
$

 
$
920

Existing
500

 
955

 
685

 
535

 
550

 
3,225

Transmission and distribution
1,410

 
2,060

 
1,985

 
2,485

 
2,335

 
10,275

Nuclear fuel
105

 
125

 
190

 
170

 
210

 
800

General and other
110

 
265

 
240

 
185

 
185

 
985

Total
$
2,975

 
$
3,465

 
$
3,105

 
$
3,380

 
$
3,280

 
$
16,205

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(d)
$
1,810

 
$
50

 
$
35

 
$
30

 
$
30

 
$
1,955

Solar(e)
735

 
10

 

 

 

 
745

Nuclear, including nuclear fuel
250

 
235

 
265

 
275

 
245

 
1,270

Natural gas pipelines(f)
1,220

 
775

 
465

 
35

 
20

 
2,515

Other
255

 
55

 
75

 
50

 
65

 
500

Total
$
4,270

 
$
1,125

 
$
840

 
$
390

 
$
360

 
$
6,985

Corporate and Other
$
190

 
$
165

 
$
125

 
$
155

 
$
120

 
$
755

————————————
(a)
Includes AFUDC of approximately $51 million, $14 million and $11 million for the remainder of 2016 through 2018, respectively.
(b)
Includes land, generation structures, transmission interconnection and integration and licensing.
(c)
Excludes capital expenditures of approximately $940 million for the natural gas-fired combined-cycle unit in Okeechobee County, Florida for the period from the end of 2016 (when approval by the Florida Power Plant Siting Board (Siting Board), comprised of the Florida governor and cabinet is expected) through 2019. Also excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive and maintain an NRC license for each unit.
(d)
Consists of capital expenditures for new wind projects and related transmission totaling approximately 1,565 MW.
(e)
Includes capital expenditures for new solar projects and related transmission totaling approximately 860 MW.
(f)
Includes capital expenditures for construction of three natural gas pipelines, including equity contributions associated with equity investments in joint ventures for two pipelines and AFUDC associated with the third pipeline. The natural gas pipelines are subject to certain conditions. See Contracts below.

Required capacity and/or minimum payments under contracts
The required capacity and/or minimum payments under the contracts discussed above as of March 31, 2016 were estimated as follows:
 
Remainder of 2016
 
2017
 
2018
 
2019
 
2020
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges(a)
$
135

 
$
170

 
$
155

 
$
135

 
$
110

 
$
690

Minimum charges, at projected prices:(b)
 

 
 

 
 

 
 

 
 

 
 

Natural gas, including transportation and storage(c)
$
795

 
$
930

 
$
870

 
$
860

 
$
910

 
$
12,970

Coal, including transportation
$
70

 
$
45

 
$
5

 
$
5

 
$

 
$

NEER
$
3,515

 
$
750

 
$
610

 
$
130

 
$
75

 
$
320

Corporate and Other(d)(e)
$
80

 
$
5

 
$
5

 
$

 
$
5

 
$

————————————
(a)
Capacity charges under these contracts, substantially all of which are recoverable through the capacity clause, totaled approximately $47 million and $119 million for the three months ended March 31, 2016 and 2015, respectively. Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $16 million and $44 million for the three months ended March 31, 2016 and 2015, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes approximately $200 million, $295 million, $290 million, $360 million and $7,885 million in 2017, 2018, 2019 , 2020 and thereafter, respectively, of firm commitments, subject to certain conditions as noted above, related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.
(d)
Includes an approximately $35 million commitment to invest primarily in clean power and technology businesses through 2021.
(e)
Excludes approximately $865 million in 2016 of joint obligations of NEECH and NEER which are included in the NEER amounts above.