XML 21 R48.htm IDEA: XBRL DOCUMENT v3.3.0.814
Commitments and Contingencies (Planned Capital Expenditures) (Details)
$ in Millions
9 Months Ended
Sep. 30, 2015
USD ($)
MW
Corporate and Other [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year $ 155
2016 1,215
2017 915
2018 505
2019 160
Total 2,950
FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 1,185
2016 3,845
2017 2,800
2018 2,470
2019 2,455
Total 12,755
NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 1,210
2016 2,655
2017 350
2018 375
2019 365
Total 4,955
New Generation Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 150
2016 865
2017 45
2018 0
2019 0
Total 1,060
Existing Generation Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 375
2016 585
2017 660
2018 535
2019 470
Total 2,625
Transmission And Distribution Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 510
2016 1,960
2017 1,755
2018 1,625
2019 1,680
Total 7,530
Nuclear Fuel Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 20
2016 220
2017 125
2018 150
2019 175
Total 690
General And Other Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 130
2016 215
2017 215
2018 160
2019 130
Total 850
Wind Expenditures [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 235
2016 1,185
2017 65
2018 15
2019 10
Total $ 1,510
Planned new generation over 5 year period (in megawatts) | MW 1,790
Wind Expenditures [Member] | Subsequent Event [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Planned new generation over 5 year period (in megawatts) | MW 125
Solar Expenditures [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year $ 780
2016 1,100
2017 0
2018 0
2019 0
Total $ 1,880
Planned new generation over 5 year period (in megawatts) | MW 1,155
Solar Expenditures [Member] | Subsequent Event [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Planned new generation over 5 year period (in megawatts) | MW 220
Nuclear Expenditures [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year $ 90
2016 300
2017 240
2018 260
2019 310
Total 1,200
Other Expenditures [Member] | NextEra Energy Resources [Member]  
Planned Capital Expenditures [Line Items]  
Remainder Current Year 105
2016 70
2017 45
2018 100
2019 45
Total 365
Generation Expenditures [Member] | FPL [Member]  
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - remainder of 2015 28
Allowance for funds used during construction (AFUDC) - 2016 79
Allowance for funds used during construction (AFUDC) - 2017 $ 13