Commitments and Contingencies
9 Months Ended
Sep. 30, 2014
Commitments and Contingencies [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments - NEE and its subsidiaries have made commitments in connection with a portion of their projected capital expenditures.  Capital expenditures at FPL include, among other things, the cost for construction or acquisition of additional facilities and equipment to meet customer demand, as well as capital improvements to and maintenance of existing facilities and the procurement of nuclear fuel.  At NEER, capital expenditures include, among other things, the cost, including capitalized interest, for construction and development of wind and solar projects and the procurement of nuclear fuel.  Capital expenditures for Corporate and Other primarily include the cost for construction of a natural gas pipeline system for new natural gas transportation infrastructure in Florida, as well as the cost to meet customer-specific requirements and maintain the fiber-optic network for the fiber-optic telecommunications business (FPL FiberNet) and the cost to maintain existing transmission facilities at NextEra Energy Transmission, LLC (NEET).

At September 30, 2014, estimated capital expenditures for the remainder of 2014 through 2018 were as follows:

 
Remainder of 2014
 
2015
 
2016
 
2017
 
2018
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
180

 
$
300

 
$
80

 
$
5

 
$

 
$
565

Existing
230

 
710

 
590

 
600

 
490

 
2,620

Transmission and distribution
445

 
1,565

 
1,840

 
1,315

 
1,335

 
6,500

Nuclear fuel
35

 
205

 
220

 
125

 
150

 
735

General and other
55

 
215

 
175

 
185

 
160

 
790

Total(d)
$
945

 
$
2,995

 
$
2,905

 
$
2,230

 
$
2,135

 
$
11,210

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(e)
$
375

 
$
1,175

 
$
135

 
$
10

 
$
15

 
$
1,710

Solar(f)
260

 
835

 
495

 

 

 
1,590

Nuclear(g)
105

 
275

 
290

 
245

 
240

 
1,155

Other(h)
185

 
240

 
55

 
50

 
115

 
645

Total
$
925

 
$
2,525

 
$
975

 
$
305

 
$
370

 
$
5,100

Corporate and Other(i)
$
75

 
$
365

 
$
855

 
$
270

 
$
110

 
$
1,675

————————————
(a)
Includes allowance for funds used during construction (AFUDC) of approximately $12 million, $59 million and $17 million for the remainder of 2014 through 2016, respectively.
(b)
Includes land, generating structures, transmission interconnection and integration and licensing.
(c)
Consists of projects that have received FPSC approval.  Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.
(d)
FPL has identified $750 million to $1 billion in potential incremental capital expenditures through 2016 in addition to what is included in the table above.
(e)
Consists of capital expenditures for new wind projects and related transmission totaling approximately 1,740 MW, including approximately 325 MW in Canada, that have received applicable internal approvals.  NEER expects to add new U.S. wind generation of approximately 2,500 MW in 2013 through 2015, including approximately 525 MW added to date, at a total cost of $4.5 billion to $5 billion, and new Canadian wind generation of 640 MW in 2013 through 2016, including 315 MW added to date, at a total cost of $2 billion to $2.5 billion.
(f)
Consists of capital expenditures for new solar projects and related transmission totaling approximately 515 MW that have received applicable internal approvals, including equity contributions associated with a 50% equity investment in a 550 MW solar project.  NEER expects to add new U.S. solar generation of 1,600 MW to 1,800 MW in 2013 through 2016, including approximately 530 MW added to date, at a total cost of $4.5 billion to $5.5 billion.
(g)
Includes nuclear fuel.
(h)
Consists of capital expenditures that have received applicable internal approvals.
(i)
Includes capital expenditures totaling approximately $1.3 billion for the remainder of 2014 through 2018 for construction of a natural gas pipeline system that has received applicable internal approvals, including approximately $825 million of equity contributions associated with a 33% equity investment in the northern portion of the natural gas pipeline system and $520 million for the southern portion, which includes AFUDC of approximately $3 million, $17 million and $10 million for 2015 through 2017, respectively.  Construction of the natural gas pipeline system is subject to certain conditions, including FERC approval.  A FERC decision is expected in 2015.  See Contracts below.

In October 2014, NEE obtained internal approvals to make an equity investment in a joint venture which plans to construct an approximately 300-mile natural gas pipeline to connect the Marcellus and Utica natural gas supply with markets in the Southeast region of the U.S. Based on NEE's expected ownership share, expected equity contributions by NEE are approximately $1.0 billion to $1.4 billion depending on the ultimate size and scope of the natural gas pipeline project. Construction of the natural gas pipeline is subject to certain conditions, including FERC approval.

The above estimates are subject to continuing review and adjustment and actual capital expenditures may vary significantly from these estimates.

Contracts - In addition to the commitments made in connection with the estimated capital expenditures included in the table in Commitments above, FPL has commitments under long-term purchased power and fuel contracts.  As of September 30, 2014, FPL is obligated under take-or-pay purchased power contracts with JEA and with subsidiaries of The Southern Company (Southern subsidiaries) to pay for approximately 1,330 MW annually through 2015 and 375 MW annually thereafter through 2021.  FPL also has various firm pay-for-performance contracts to purchase approximately 705 MW from certain cogenerators and small power producers (qualifying facilities) with expiration dates ranging from 2024 through 2034.  The purchased power contracts provide for capacity and energy payments.  Energy payments are based on the actual power taken under these contracts.  Capacity payments for the pay-for-performance contracts are subject to the qualifying facilities meeting certain contract conditions.  FPL has contracts with expiration dates through 2036 for the purchase and transportation of natural gas and coal, and storage of natural gas.  In addition, FPL has entered into 25-year natural gas transportation agreements with each of Sabal Trail Transmission, LLC (Sabal Trail, an entity in which a NEECH subsidiary has a 33% ownership interest), and Florida Southeast Connection, LLC (Florida Southeast Connection, a wholly-owned NEECH subsidiary), each of which will build, own and operate a pipeline that will be part of a natural gas pipeline system, for a quantity of 400,000 MMBtu/day beginning on May 1, 2017 and increasing to 600,000 MMBtu/day on May 1, 2020.  These agreements contain firm commitments that are contingent upon the occurrence of certain events, including FERC approval and completion of construction of the pipeline system to be built by Sabal Trail and Florida Southeast Connection.  See Commitments above.

As of September 30, 2014, NEER has entered into contracts with expiration dates ranging from November 2014 through 2030 primarily for the purchase of wind turbines, wind towers and solar modules and related construction and development activities, as well as for the supply of uranium, conversion, enrichment and fabrication of nuclear fuel.  Approximately $2.5 billion of commitments under such contracts are included in the estimated capital expenditures table in Commitments above.  In addition, NEER has contracts primarily for the purchase, transportation and storage of natural gas and firm transmission service with expiration dates ranging from December 2014 through 2033.

Included in Corporate and Other in the table below is the remaining commitment by a NEECH subsidiary to invest approximately $890 million in Sabal Trail for the construction of the northern portion of the natural gas pipeline system.  Amounts committed for the remainder of 2014 through 2018 are also included in the estimated capital expenditures table in Commitments above.

The required capacity and/or minimum payments under the contracts discussed above as of September 30, 2014 were estimated as follows:

 
Remainder of 2014
 
2015
 
2016
 
2017
 
2018
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges:(a)
 
 
 
 
 
 
 
 
 
 
 
Qualifying facilities
$
70

 
$
290

 
$
250

 
$
255

 
$
260

 
$
1,965

JEA and Southern subsidiaries
$
55

 
$
195

 
$
70

 
$
50

 
$
10

 
$
5

Minimum charges, at projected prices:(b)
 

 
 

 
 

 
 

 
 

 
 

Natural gas, including transportation and storage(c)
$
415

 
$
1,250

 
$
755

 
$
745

 
$
825

 
$
14,520

Coal
$
20

 
$
70

 
$
40

 
$
35

 
$

 
$

NEER
$
485

 
$
1,335

 
$
655

 
$
135

 
$
130

 
$
480

Corporate and Other(d)(e)
$
70

 
$
250

 
$
505

 
$
50

 
$
25

 
$
70

————————————
(a)
Capacity charges under these contracts, substantially all of which are recoverable through the capacity cost recovery clause, totaled approximately $123 million and $121 million for the three months ended September 30, 2014 and 2013, respectively, and approximately $369 million and $365 million for the nine months ended September 30, 2014 and 2013, respectively.  Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $110 million and $93 million for the three months ended September 30, 2014 and 2013, respectively, and approximately $242 million and $202 million for the nine months ended September 30, 2014 and 2013, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes approximately $200 million, $295 million and $8,535 million in 2017, 2018 and thereafter, respectively, of firm commitments, subject to certain conditions as noted above, related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.
(d)
Includes an approximately $45 million commitment to invest in clean power and technology businesses through 2021.
(e)
Excludes approximately $325 million in 2015 of joint obligations of NEECH and NEER which are included in the NEER amounts above.

Insurance - Liability for accidents at nuclear power plants is governed by the Price-Anderson Act, which limits the liability of nuclear reactor owners to the amount of insurance available from both private sources and an industry retrospective payment plan.  In accordance with this Act, NEE maintains $375 million of private liability insurance per site, which is the maximum obtainable, and participates in a secondary financial protection system, which provides up to $13.2 billion of liability insurance coverage per incident at any nuclear reactor in the United States.  Under the secondary financial protection system, NEE is subject to retrospective assessments of up to $1.0 billion ($509 million for FPL), plus any applicable taxes, per incident at any nuclear reactor in the United States, payable at a rate not to exceed $152 million ($76 million for FPL) per incident per year.  NEE and FPL are contractually entitled to recover a proportionate share of such assessments from the owners of minority interests in Seabrook, Duane Arnold Energy Center (Duane Arnold) and St. Lucie Unit No. 2, which approximates $15 million, $38 million and $19 million, plus any applicable taxes, per incident, respectively.

NEE participates in a nuclear insurance mutual company that provides $2.75 billion of limited insurance coverage per occurrence per site for property damage, decontamination and premature decommissioning risks at its nuclear plants and a sublimit of $1.5 billion for non-nuclear perils.  The proceeds from such insurance, however, must first be used for reactor stabilization and site decontamination before they can be used for plant repair.  NEE also participates in an insurance program that provides limited coverage for replacement power costs if a nuclear plant is out of service for an extended period of time because of an accident.  In the event of an accident at one of NEE's or another participating insured's nuclear plants, NEE could be assessed up to $176 million ($106 million for FPL), plus any applicable taxes, in retrospective premiums in a policy year.  NEE and FPL are contractually entitled to recover a proportionate share of such assessments from the owners of minority interests in Seabrook, Duane Arnold and St. Lucie Unit No. 2, which approximates $2 million, $5 million and $4 million, plus any applicable taxes, respectively.

Due to the high cost and limited coverage available from third-party insurers, NEE does not have property insurance coverage for a substantial portion of its transmission and distribution property and has no property insurance coverage for FPL FiberNet's fiber-optic cable.  Should FPL's future storm restoration costs exceed the reserve amount established through the issuance of storm-recovery bonds by a VIE in 2007, FPL may recover storm restoration costs, subject to prudence review by the FPSC, either through surcharges approved by the FPSC or through securitization provisions pursuant to Florida law.

In the event of a loss, the amount of insurance available might not be adequate to cover property damage and other expenses incurred.  Uninsured losses and other expenses, to the extent not recovered from customers in the case of FPL or Lone Star Transmission, LLC (Lone Star), would be borne by NEE and/or FPL and/or their affiliates, as the case may be, and could have a material adverse effect on NEE's and FPL's financial condition, results of operations and liquidity.

Spain Solar Projects - In March 2013 and May 2013, events of default occurred under the project-level financing agreements for the Spain solar projects (project-level financing) as a result of changes of law that occurred in December 2012 and February 2013.  These changes of law negatively affected the projected economics of the projects and caused the project-level financing to be unsupportable by expected future project cash flows.  Under the project-level financing, events of default (including those discussed below) provide for, among other things, a right by the lenders (which they have not exercised) to accelerate the payment of the project-level debt.  Accordingly, in 2013, the project-level debt and the associated derivative liabilities related to interest rate swaps were classified as current maturities of long-term debt and current derivative liabilities, respectively, on NEE's condensed consolidated balance sheets, and totaled $689 million and $128 million, respectively, as of September 30, 2014.  In July 2013, the Spanish government published a new law that created a new economic framework for the Spanish renewable energy sector.  Additional regulatory pronouncements from the Spanish government needed to complete and implement the framework were finalized in June 2014.  Based on NEE's assessment, the regulatory pronouncements do not indicate a further impairment of the Spain solar projects. However, the Spanish government's interpretation of the new remuneration scheme resulted in a reduction to 2013 revenues of approximately $19 million which was reflected in operating revenues for the three and nine months ended September 30, 2014 in NEE's condensed consolidated statements of income. During the third quarter of 2014, events of default occurred under the project-level financing agreements related to certain debt service coverage ratio covenants not being met. The project-level subsidiaries have requested the lenders to waive the events of default related to the debt service coverage ratio.

As part of a settlement agreement reached on December 20, 2013 between NEECH, NextEra Energy España, S.L. (NEE España), which is the NEER subsidiary in Spain that is the direct shareholder of the project-level subsidiaries, the project-level subsidiaries and the lenders, the future recourse of the lenders under the project-level financing is effectively limited to the letters of credit described below and to the assets of the project-level subsidiaries. Under the settlement agreement, the lenders, among other things, irrevocably waived events of default related to changes of law that existed at the time of the settlement as described above, and NEECH affiliates provided for the project-level subsidiaries to post approximately €37 million (approximately $47 million as of September 30, 2014) in letters of credit to fund operating and debt service reserves under the project-level financing.  NEE España, the project-level subsidiaries and the lenders will continue to seek to restructure the project-level financing; however, there can be no assurance that the project-level financing will be successfully restructured or that additional events of default under the project-level financing will not occur.

Legal Proceedings - In November 1999, the Attorney General of the United States, on behalf of the U.S. Environmental Protection Agency (EPA), brought an action in the U.S. District Court for the Northern District of Georgia against Georgia Power Company and other subsidiaries of The Southern Company for certain alleged violations of the Prevention of Significant Deterioration (PSD) provisions and the New Source Performance Standards (NSPS) of the Clean Air Act.  In May 2001, the EPA amended its complaint to allege, among other things, that Georgia Power Company constructed and is continuing to operate Scherer Unit No. 4, in which FPL owns an interest of approximately 76%, without obtaining a PSD permit, without complying with NSPS requirements, and without applying best available control technology for nitrogen oxides, sulfur dioxides and particulate matter as required by the Clean Air Act.  It also alleges that unspecified major modifications have been made at Scherer Unit No. 4 that require its compliance with the aforementioned Clean Air Act provisions.  The EPA seeks injunctive relief requiring the installation of best available control technology and civil penalties.  Under the EPA's civil penalty rules, the EPA could assess up to $25,000 per day for each violation from an unspecified date after June 1, 1975 through January 30, 1997, up to $27,500 per day for each violation from January 31, 1997 through March 15, 2004, up to $32,500 per day for each violation from March 16, 2004 through January 12, 2009 and up to $37,500 per day for each violation thereafter.  Georgia Power Company has answered the amended complaint, asserting that it has complied with all requirements of the Clean Air Act, denying the plaintiff's allegations of liability, denying that the plaintiff is entitled to any of the relief that it seeks and raising various other defenses.  In June 2001, a federal district court stayed discovery and administratively closed the case and the EPA has not yet moved to reopen the case.  In April 2007, the U.S. Supreme Court in a separate unrelated case rejected an argument that a "major modification" occurs at a plant only when there is a resulting increase in the hourly rate of air emissions.  Georgia Power Company has made a similar argument in defense of its case, but has other factual and legal defenses that are unaffected by the U.S. Supreme Court's decision.

In 1995 and 1996, NEE, through an indirect subsidiary, purchased from Adelphia Communications Corporation (Adelphia) 1,091,524 shares of Adelphia common stock and 20,000 shares of Adelphia preferred stock (convertible into 2,358,490 shares of Adelphia common stock) for an aggregate price of approximately $35,900,000.  On January 29, 1999, Adelphia repurchased all of these shares for $149,213,130 in cash.  In June 2004, Adelphia, Adelphia Cablevision, L.L.C. and the Official Committee of Unsecured Creditors of Adelphia filed a complaint against NEE and its indirect subsidiary in the U.S. Bankruptcy Court, Southern District of New York.  The complaint alleges that the repurchase of these shares by Adelphia was a fraudulent transfer, in that at the time of the transaction Adelphia (i) was insolvent or was rendered insolvent, (ii) did not receive reasonably equivalent value in exchange for the cash it paid, and (iii) was engaged or about to engage in a business or transaction for which any property remaining with Adelphia had unreasonably small capital.  The complaint seeks the recovery for the benefit of Adelphia's bankruptcy estate of the cash paid for the repurchased shares, plus interest from January 29, 1999.  NEE filed an answer to the complaint.  NEE believes that the complaint is without merit because, among other reasons, Adelphia will be unable to demonstrate that (i) Adelphia's repurchase of shares from NEE, which repurchase was at the market value for those shares, was not for reasonably equivalent value, (ii) Adelphia was insolvent at the time of the stock repurchase, or (iii) the stock repurchase left Adelphia with unreasonably small capital.  The trial was completed in May 2012 and closing arguments were heard in July 2012.  On May 6, 2014, the U.S. Bankruptcy Court, Southern District of New York, issued its decision after trial, finding, among other things, that Adelphia was not insolvent, or rendered insolvent, at the time of the stock repurchase.  The bankruptcy court further ruled that Adelphia was not left with inadequate capital or equitably insolvent at the time of the stock repurchase.  The decision after trial represents proposed findings of fact and conclusions of law which are subject to de novo review by the U.S. District Court for the Southern District of New York.  Adelphia filed its objections to the decision on June 10, 2014 and NEE filed its response to those objections on July 15, 2014.  The issuance of a final order by the district court is pending.

NEE and FPL are vigorously defending, and believe that they or their affiliates have meritorious defenses to, the lawsuits described above.  In addition to the legal proceedings discussed above, NEE and its subsidiaries, including FPL, are involved in other legal and regulatory proceedings, actions and claims in the ordinary course of their businesses.  Generating plants in which subsidiaries of NEE, including FPL, have an ownership interest are also involved in legal and regulatory proceedings, actions and claims, the liabilities from which, if any, would be shared by such subsidiary.  In the event that NEE and FPL, or their affiliates, do not prevail in the lawsuits described above or these other legal and regulatory proceedings, actions and claims, there may be a material adverse effect on their financial statements.  While management is unable to predict with certainty the outcome of the lawsuits described above or these other legal and regulatory proceedings, actions and claims, based on current knowledge it is not expected that their ultimate resolution, individually or collectively, will have a material adverse effect on the financial statements of NEE or FPL.