Commitments and Contingencies (Planned Capital Expenditures) (Details) (USD $)
3 Months Ended
Mar. 31, 2014
MW
FPL [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year $ 2,305,000,000 [1]
2015 2,540,000,000 [1]
2016 2,145,000,000 [1]
2017 1,890,000,000 [1]
2018 1,910,000,000 [1]
Total 10,790,000,000 [1]
Incremental Capital Expenditures Low Range 1,500,000,000
Incremental Capital Expenditures High Range 2,500,000,000
FPL [Member] | New Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 475,000,000 [2],[3],[4]
2015 295,000,000 [2],[3],[4]
2016 70,000,000 [2],[3],[4]
2017 0 [2],[3],[4]
2018 0 [2],[3],[4]
Total 840,000,000 [2],[3],[4]
FPL [Member] | Existing Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 565,000,000 [2]
2015 680,000,000 [2]
2016 610,000,000 [2]
2017 580,000,000 [2]
2018 545,000,000 [2]
Total 2,980,000,000 [2]
FPL [Member] | Transmission And Distribution Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 1,055,000,000
2015 1,200,000,000
2016 1,125,000,000
2017 955,000,000
2018 1,025,000,000
Total 5,360,000,000
FPL [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 80,000,000
2015 210,000,000
2016 220,000,000
2017 190,000,000
2018 180,000,000
Total 880,000,000
FPL [Member] | General And Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 130,000,000
2015 155,000,000
2016 120,000,000
2017 165,000,000
2018 160,000,000
Total 730,000,000
FPL [Member] | Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - remainder of 2014 28,000,000
Allowance for funds used during construction (AFUDC) - 2015 53,000,000
Allowance for funds used during construction (AFUDC) - 2016 17,000,000
NextEra Energy Resources [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 2,595,000,000
2015 1,655,000,000
2016 915,000,000
2017 305,000,000
2018 355,000,000
Total 5,825,000,000
NextEra Energy Resources [Member] | Wind Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 1,505,000,000 [5]
2015 610,000,000 [5]
2016 25,000,000 [5]
2017 10,000,000 [5]
2018 15,000,000 [5]
Total 2,165,000,000 [5]
Planned New Wind Generation To Be Added over 5 Years (in megawatts) 1,815
Planned new wind generation added to date (in megawatts) 325
NextEra Energy Resources [Member] | Wind Expenditures [Member] | CANADA
 
Planned Capital Expenditures [Line Items]  
Planned New Wind Generation To Be Added over 5 Years (in megawatts) 465
NextEra Energy Resources [Member] | Wind Expenditures [Member] | Minimum [Member]
 
Planned Capital Expenditures [Line Items]  
Expected New Wind Projects, Three-Year Period, Capacity 2,000
Expected New Wind Projects, Three-Year Period, Expected Costs 3,500,000,000
NextEra Energy Resources [Member] | Wind Expenditures [Member] | Maximum [Member]
 
Planned Capital Expenditures [Line Items]  
Expected New Wind Projects, Three-Year Period, Capacity 2,500
Expected New Wind Projects, Three-Year Period, Expected Costs 4,500,000,000
NextEra Energy Resources [Member] | Solar Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 480,000,000 [6]
2015 750,000,000 [6]
2016 520,000,000 [6]
2017 0 [6]
2018 0 [6]
Total 1,750,000,000 [6]
Planned new solar generation over 5 year period (in megawatts) 600
Equity Method Investment, Ownership Percentage 50.00%
Planned New Solar Capacity of Equity Method Investment (in megawatts) 550
NextEra Energy Resources [Member] | Solar Expenditures [Member] | Expected to Close Mid 2014 [Member]
 
Planned Capital Expenditures [Line Items]  
Planned new solar generation over 5 year period (in megawatts) 250
Planned New Solar Generation Over Five Year Period, Expected Costs 1,000,000,000
NextEra Energy Resources [Member] | Solar Expenditures [Member] | Requiring Internal Approvals [Member]
 
Planned Capital Expenditures [Line Items]  
Planned new solar generation over 5 year period (in megawatts) 47
Planned New Solar Generation Over Five Year Period, Expected Costs 120,000,000
NextEra Energy Resources [Member] | Nuclear Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 265,000,000 [7]
2015 275,000,000 [7]
2016 295,000,000 [7]
2017 255,000,000 [7]
2018 265,000,000 [7]
Total 1,355,000,000 [7]
NextEra Energy Resources [Member] | Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 345,000,000 [8]
2015 20,000,000 [8]
2016 75,000,000 [8]
2017 40,000,000 [8]
2018 75,000,000 [8]
Total 555,000,000 [8]
Corporate and Other [Member]
 
Planned Capital Expenditures [Line Items]  
Remainder Current Year 190,000,000 [9]
2015 445,000,000 [9]
2016 795,000,000 [9]
2017 225,000,000 [9]
2018 95,000,000 [9]
Total 1,750,000,000 [9]
Corporate and Other [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - remainder of 2014 1,000,000
Allowance for funds used during construction (AFUDC) - 2015 7,000,000
Allowance for funds used during construction (AFUDC) - 2016 20,000,000
Allowance for funds used during construction (AFUDC) - 2017 12,000,000
Potential Capital Expenditures For Natural Gas Pipeline 1,400,000,000
Sabal Trail Transmission, LLC [Member] | Corporate and Other [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Equity method investment in natural gas pipeline, through 2018 885,000,000
Sabal Trail Transmission, LLC [Member] | Corporate and Other [Member]
 
Planned Capital Expenditures [Line Items]  
Equity Method Investment, Ownership Percentage 33.00%
Florida Southeast Connection, LLC [Member] | Corporate and Other [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Planned capital expenditures for natural gas pipeline $ 525,000,000
[1] FPL has identified $1.5 billion to $2.5 billion in potential incremental capital expenditures through 2016 in addition to what is included in the table above.
[2] Includes allowance for funds used during construction (AFUDC) of approximately $28 million, $53 million and $17 million for the remainder of 2014 through 2016, respectively.
[3] Consists of projects that have received FPSC approval. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.
[4] Includes land, generating structures, transmission interconnection and integration and licensing.
[5] Consists of capital expenditures for new wind projects and related transmission totaling approximately 1,815 MW, including approximately 465 MW in Canada, that have received applicable internal approvals. NEER expects to add new U.S. wind generation of 2,000 MW to 2,500 MW in 2013 through 2015, including 325 MW added to date, at a total cost of up to $3.5 billion to $4.5 billion.
[6] Consists of capital expenditures for new solar projects and related transmission totaling approximately 600 MW that have received applicable internal approvals, including equity contributions associated with a 50% equity investment in a 550 MW solar project. Includes approximately $1 billion of total estimated costs associated with the pending acquisition of the development rights for a 250 MW solar project that is expected to close in mid-2014, subject to certain conditions precedent, and construction of the project, which is expected to be completed in 2016. Excludes solar projects requiring internal approvals with generation totaling 47 MW with an estimated cost of approximately $120 million.
[7] Includes nuclear fuel.
[8] Consists of capital expenditures that have received applicable internal approvals.
[9] Includes capital expenditures totaling approximately $1.4 billion for the remainder of 2014 through 2018 for construction of a natural gas pipeline system that has received applicable internal approvals, including approximately $885 million of equity contributions associated with a 33% equity investment in the northern portion of the natural gas pipeline system and $525 million for the southern portion, which includes AFUDC of approximately $1 million, $7 million, $20 million and $12 million for the remainder of 2014 through 2017, respectively. The natural gas pipeline system is subject to certain conditions, including FERC approval. A FERC decision is expected in 2015. See Contracts below.