Commitments and Contingencies (Planned Capital Expenditures) (Details) (USD $)
9 Months Ended 1 Months Ended
Sep. 30, 2013
FPL [Member]
Sep. 30, 2013
FPL [Member]
New Generation Expenditures [Member]
Sep. 30, 2013
FPL [Member]
Existing Generation Expenditures [Member]
Sep. 30, 2013
FPL [Member]
Transmission And Distribution Expenditures [Member]
Sep. 30, 2013
FPL [Member]
Nuclear Fuel Expenditures [Member]
Sep. 30, 2013
FPL [Member]
General And Other Expenditures [Member]
Sep. 30, 2013
FPL [Member]
Generation Expenditures [Member]
Sep. 30, 2013
NextEra Energy Resources [Member]
Sep. 30, 2013
NextEra Energy Resources [Member]
Nuclear Fuel Expenditures [Member]
Sep. 30, 2013
NextEra Energy Resources [Member]
Wind Expenditures [Member]
MW
Sep. 30, 2013
NextEra Energy Resources [Member]
Solar Expenditures [Member]
MW
Sep. 30, 2013
NextEra Energy Resources [Member]
Other Expenditures [Member]
Sep. 30, 2013
Corporate and Other [Member]
Oct. 31, 2013
Subsequent Event [Member]
NextEra Energy Resources [Member]
Wind Expenditures [Member]
MW
Planned Capital Expenditures [Line Items]                            
Remainder of 2013 $ 850,000,000 [1] $ 195,000,000 [2],[3],[4] $ 245,000,000 [2] $ 235,000,000 $ 115,000,000 $ 60,000,000   $ 765,000,000 $ 115,000,000 [5] $ 455,000,000 [6] $ 130,000,000 [7] $ 65,000,000 [8] $ 25,000,000 [9]  
2014 2,975,000,000 [1] 710,000,000 [2],[3],[4] 760,000,000 [2] 1,205,000,000 140,000,000 160,000,000   1,470,000,000 315,000,000 [5] 660,000,000 [6] 455,000,000 [7] 40,000,000 [8] 75,000,000 [9]  
2015 2,445,000,000 [1] 290,000,000 [2],[3],[4] 730,000,000 [2] 1,105,000,000 210,000,000 110,000,000   1,235,000,000 280,000,000 [5] 115,000,000 [6] 825,000,000 [7] 15,000,000 [8] 70,000,000 [9]  
2016 2,090,000,000 [1] 75,000,000 [2],[3],[4] 600,000,000 [2] 1,070,000,000 220,000,000 125,000,000   920,000,000 305,000,000 [5] 10,000,000 [6] 530,000,000 [7] 75,000,000 [8] 60,000,000 [9]  
2017 1,680,000,000 [1] 0 [2],[3],[4] 540,000,000 [2] 795,000,000 225,000,000 120,000,000   290,000,000 245,000,000 [5] 5,000,000 [6] 0 [7] 40,000,000 [8] 70,000,000 [9]  
Total 10,040,000,000 [1] 1,270,000,000 [2],[3],[4] 2,875,000,000 [2] 4,410,000,000 910,000,000 575,000,000   4,680,000,000 1,260,000,000 [5] 1,245,000,000 [6] 1,940,000,000 [7] 235,000,000 [8] 300,000,000 [9]  
Allowance for funds used during construction (AFUDC) - 2013             19,000,000              
Allowance for funds used during construction (AFUDC) - 2014             48,000,000              
Allowance for funds used during construction (AFUDC) - 2015             57,000,000              
Allowance for funds used during construction (AFUDC) - 2016             26,000,000              
Incremental Capital Expenditures Low Range 1,500,000,000                          
Incremental Capital Expenditures High Range 2,500,000,000                          
Potential Capital Expenditures For Natural Gas Pipeline                         1,600,000,000  
Generation capacity of additional U.S. wind projects receiving approval (in megawatts)                           850
Generation capacity of new Canadian wind projects receiving internal approvals (in megawatts)                           80
Expected cost of new U.S. and Canadian wind projects receiving internal approvals                           1,600,000,000
Expected generation of new solar project under purchase agreement (in megawatts)                     250      
Expected cost of solar project under purchase agreement                     1,100,000,000      
Planned New Wind Generation To Be Added over 5 Years (in megawatts)                   710        
Planned New Canadian Wind With Internal Approvals (in megawatts)                   385        
Planned New Canadian Wind Generation Requiring Internal Approvals (in megawatts)                   80        
Expected Cost of New Wind Projects Requiring Internal Approvals                   200,000,000        
Planned US wind generation to be added in 2013 and 2014 in megawatts - High end of range                   1,500        
Planned cost of US wind generation to be added in 2013 and 2014 - High end of range                   $ 3,000,000,000        
Planned new solar generation over 5 year period (in megawatts)                     1,045      
Planned New Solar Capacity of Equity Method Investment (in megawatts)                     550      
[1] FPL has identified $1.5 billion to $2.5 billion in potential incremental capital expenditures through 2016 in addition to what is included in the table above.
[2] Includes allowance for funds used during construction (AFUDC) of approximately $19 million, $48 million, $57 million and $26 million for the remainder of 2013 through 2016, respectively.
[3] Includes land, generating structures, transmission interconnection and integration and licensing.
[4] Consists of projects that have received FPSC approval. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.
[5] Includes nuclear fuel.
[6] Consists of capital expenditures for new wind projects and related transmission totaling approximately 710 MW, including approximately 385 MW in Canada, that have received applicable internal approvals. Excludes new Canadian wind projects requiring internal approvals with generation totaling approximately 80 MW in 2014, with an estimated remaining cost of approximately $200 million. NEER expects to add up to 1,500 MW of new U.S. wind generation through 2014 at a total cost of up to $3 billion.
[7] Consists of capital expenditures for new solar projects and related transmission totaling 1,045 MW that have received applicable internal approvals, including equity contributions associated with a 50% equity investment in a 550 MW solar project. Includes approximately $1.1 billion of estimated costs associated with the pending acquisition of a 250 MW solar project that is expected to close in early 2014, subject to certain conditions precedent, and complete construction in 2016.
[8] Consists of capital expenditures that have received applicable internal approvals.
[9] Excludes new natural gas pipeline system requiring certain external and internal approvals with an estimated total cost of approximately $1.6 billion. See Part II, Item 5. (c)(i) in the Quarterly Report on Form 10-Q for the quarterly period ended June 30, 2013 for NEE and FPL.