XML 23 R46.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies, Planned Capital Expenditures (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended
Jun. 30, 2012
MW
FPL [Member]
 
Planned Capital Expenditures [Line Items]  
2012 $ 1,880
2013 2,465
2014 2,370
2015 1,850
2016 1,640
Total 10,205
FPL [Member] | New Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 970 [1],[2],[3]
2013 815 [1],[2],[3]
2014 695 [1],[2],[3]
2015 300 [1],[2],[3]
2016 160 [1],[2],[3]
Total 2,940 [1],[2],[3]
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2012 52
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2013 41
FPL [Member] | Existing Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 285 [1]
2013 645 [1]
2014 660 [1]
2015 560 [1]
2016 435 [1]
Total 2,585 [1]
FPL [Member] | Transmission And Distribution Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 420
2013 690
2014 690
2015 660
2016 705
Total 3,165
FPL [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 85
2013 125
2014 205
2015 250
2016 250
Total 915
FPL [Member] | General And Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 120
2013 190
2014 120
2015 80
2016 90
Total 600
FPL [Member] | Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - 2012 42
Allowance for funds used during construction (AFUDC) - 2013 84
Allowance for funds used during construction (AFUDC) - 2014 59
Allowance for funds used during construction (AFUDC) - 2015 58
Allowance for funds used during construction (AFUDC) - 2016 28
NextEra Energy Resources [Member]
 
Planned Capital Expenditures [Line Items]  
2012 2,370
2013 1,320
2014 555
2015 385
2016 385
Total 5,015
NextEra Energy Resources [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 185 [4]
2013 275 [4]
2014 260 [4]
2015 265 [4]
2016 285 [4]
Total 1,270 [4]
NextEra Energy Resources [Member] | Wind Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 1,350 [5]
2013 125 [5]
2014 20 [5]
2015 10 [5]
2016 5 [5]
Total 1,510 [5]
Planned New Wind Generation To Be Added over 5 Years 1,300
Planned New Canadian Wind With Internal Approvals 150
Planned New Canadian Wind Generation Requiring Internal Approvals MW 470
Expected Cost of New Wind Projects Requiring Internal Approvals - Low End of Range 1,300
Expected Costs of New Wind Projects Requiring Internal Approvals - High End of Range 1,500
NextEra Energy Resources [Member] | Solar Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 700 [6]
2013 760 [6]
2014 185 [6]
2015 10 [6]
2016 0 [6]
Total 1,655 [6]
Planned new solar generation over 5 year period (in megawatts) 625
Planned New Solar Capacity of Equity Method Investment 550
Planned new solar capacity of projects requiring internal approvals 270
Expected cost of new solar projects requiring internal approals - Low End of Range 600
Expected Costs of New Solar Projects Requiring Internal Approval - High End of Range 800
NextEra Energy Resources [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Planned gas infrastructure costs over 4 year period 600
NextEra Energy Resources [Member] | Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 135 [7]
2013 160 [7]
2014 90 [7]
2015 100 [7]
2016 95 [7]
Total 580 [7]
Corporate and Other [Member]
 
Planned Capital Expenditures [Line Items]  
2012 295 [8]
2013 85 [8]
2014 85 [8]
2015 75 [8]
2016 75 [8]
Total 615 [8]
Allowance for funds used during construction (AFUDC) - 2012 30
Allowance for funds used during construction (AFUDC) - 2013 $ 14
[1] Includes allowance for funds used during construction (AFUDC) of approximately $42 million, $84 million, $59 million, $58 million and $28 million in 2012 to 2016, respectively.
[2] Includes land, generating structures, transmission interconnection and integration and licensing.
[3] Consists of projects that have received FPSC approval. Includes pre-construction costs and carrying charges (equal to a pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $52 million and $41 million in 2012 and 2013, respectively. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.
[4] Includes nuclear fuel.
[5] Consists of capital expenditures for planned new wind projects and related transmission totaling approximately 1,300 mw, including approximately 150 mw in Canada, that have received applicable internal approvals. Excludes new Canadian wind projects requiring internal approvals with generation totaling approximately 470 mw in 2014 and 2015, with an estimated cost of approximately $1.3 billion
[6] Consists of capital expenditures for planned new solar projects and related transmission totaling 625 mw that have received applicable internal approvals, including equity contributions associated with a 50% equity method investment in a 550 mw solar project. Excludes solar projects requiring internal approvals with generation totaling 270 mw with an estimated cost of approximately $600 million
[7] Consists of capital expenditures that have received applicable internal approvals. In addition, NEER plans to add natural gas infrastructure projects at a total cost of approximately $600 million in 2013 through 2016.
[8] Consists of capital expenditures that have received applicable internal approvals and includes AFUDC of approximately $30 million and $14 million in 2012 and 2013, respectively.