XML 64 R16.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies
6 Months Ended
Jun. 30, 2012
Commitments and Contingencies [Abstract]  
Commitments and Contingencies
9.  Commitments and Contingencies

Commitments - NEE and its subsidiaries have made commitments in connection with a portion of their projected capital expenditures.  Capital expenditures at FPL include, among other things, the cost for construction or acquisition of additional facilities and equipment to meet customer demand, as well as capital improvements to and maintenance of existing facilities and the procurement of nuclear fuel.  At NEER, capital expenditures include, among other things, the cost, including capitalized interest, for construction of wind and solar projects and the procurement of nuclear fuel.  Capital expenditures for Corporate and Other primarily include the cost for construction of a transmission line and other associated facilities by Lone Star Transmission, LLC (Lone Star), a rate-regulated transmission service provider in Texas, and the cost to meet customer-specific requirements and maintain the fiber-optic network for the fiber-optic telecommunications business (FPL FiberNet).

At June 30, 2012, estimated planned capital expenditures for the remainder of 2012 through 2016 were as follows:

 
2012
 
2013
 
2014
 
2015
 
2016
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
970

 
$
815

 
$
695

 
$
300

 
$
160

 
$
2,940

Existing
285

 
645

 
660

 
560

 
435

 
2,585

Transmission and distribution
420

 
690

 
690

 
660

 
705

 
3,165

Nuclear fuel
85

 
125

 
205

 
250

 
250

 
915

General and other
120

 
190

 
120

 
80

 
90

 
600

Total
$
1,880

 
$
2,465

 
$
2,370

 
$
1,850

 
$
1,640

 
$
10,205

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(d)
$
1,350

 
$
125

 
$
20

 
$
10

 
$
5

 
$
1,510

Solar(e)
700

 
760

 
185

 
10

 

 
1,655

Nuclear(f)
185

 
275

 
260

 
265

 
285

 
1,270

Other(g)
135

 
160

 
90

 
100

 
95

 
580

Total
$
2,370

 
$
1,320

 
$
555

 
$
385

 
$
385

 
$
5,015

Corporate and Other(h)
$
295

 
$
85

 
$
85

 
$
75

 
$
75

 
$
615

————————————
(a)
Includes allowance for funds used during construction (AFUDC) of approximately $42 million, $84 million, $59 million, $58 million and $28 million in 2012 to 2016, respectively.
(b)
Includes land, generating structures, transmission interconnection and integration and licensing.
(c)
Consists of projects that have received FPSC approval.  Includes pre-construction costs and carrying charges (equal to a pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $52 million and $41 million in 2012 and 2013, respectively.  Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.  
(d)
Consists of capital expenditures for planned new wind projects and related transmission totaling approximately 1,300 mw, including approximately 150 mw in Canada, that have received applicable internal approvals.  Excludes new Canadian wind projects requiring internal approvals with generation totaling approximately 470 mw in 2014 and 2015, with an estimated cost of approximately $1.3 billion to $1.5 billion.
(e)
Consists of capital expenditures for planned new solar projects and related transmission totaling 625 mw that have received applicable internal approvals, including equity contributions associated with a 50% equity method investment in a 550 mw solar project.  Excludes solar projects requiring internal approvals with generation totaling 270 mw with an estimated cost of approximately $600 million to $800 million.
(f)
Includes nuclear fuel.
(g)
Consists of capital expenditures that have received applicable internal approvals.  In addition, NEER plans to add natural gas infrastructure projects at a total cost of approximately $600 million in 2013 through 2016.
(h)
Consists of capital expenditures that have received applicable internal approvals and includes AFUDC of approximately $30 million and $14 million in 2012 and 2013, respectively.

These estimates are subject to continuing review and adjustment and actual capital expenditures may vary significantly from these estimates.

Contracts - In addition to the estimated planned capital expenditures included in the table in Commitments above, FPL has commitments under long-term purchased power and fuel contracts.  FPL is obligated under take-or-pay purchased power contracts with JEA and with subsidiaries of The Southern Company (Southern subsidiaries) to pay for approximately 1,330 mw annually through 2015 and 375 mw annually thereafter through 2021.  FPL also has various firm pay-for-performance contracts to purchase approximately 705 mw from certain cogenerators and small power producers (qualifying facilities) with expiration dates ranging from 2024 through 2034.  The purchased power contracts provide for capacity and energy payments.  Energy payments are based on the actual power taken under these contracts.  Capacity payments for the pay-for-performance contracts are subject to the qualifying facilities meeting certain contract conditions.  FPL has contracts with expiration dates through 2036 for the purchase and transportation of natural gas and coal, and storage of natural gas.

NEER has entered into contracts primarily for the purchase of wind turbines and towers, solar reflectors, steam turbine generators and heat collection elements and related construction and development activities, as well as for the supply of uranium, conversion, enrichment and fabrication of nuclear fuel, with expiration dates ranging from August 2012 through 2030, approximately $2.6 billion of which is included in the estimated planned capital expenditures table in Commitments above.  In addition, NEER has contracts primarily for the purchase, transportation and storage of natural gas and firm transmission service with expiration dates ranging from September 2012 through 2033.

The transmission business included in Corporate and Other has entered into contracts primarily for development and construction activities relating to Lone Star's transmission line and other associated facilities, all of which is included in the estimated planned capital expenditures table in Commitments above.

The required capacity and/or minimum payments under the contracts discussed above as of June 30, 2012 were estimated as follows:

 
2012
 
2013
 
2014
 
2015
 
2016
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges:(a)
 
 
 
 
 
 
 
 
 
 
 
Qualifying facilities
$
150

 
$
270

 
$
275

 
$
280

 
$
245

 
$
2,415

JEA and Southern subsidiaries
$
115

 
$
230

 
$
220

 
$
195

 
$
70

 
$
155

Minimum charges, at projected prices:
 

 
 

 
 

 
 

 
 

 
 

Natural gas, including transportation and storage(b)
$
1,000

 
$
1,330

 
$
1,030

 
$
565

 
$
525

 
$
6,925

Coal(b)
$
40

 
$
90

 
$
35

 
$
5

 
$
5

 
$

NEER
$
1,680

 
$
610

 
$
120

 
$
110

 
$
105

 
$
605

Corporate and Other(c)
$
110

 
$
30

 
$
15

 
$
15

 
$
15

 
$

————————————
(a)
Capacity charges under these contracts, substantially all of which are recoverable through the capacity clause, totaled approximately $129 million and $124 million for the three months ended June 30, 2012 and 2011, respectively, and approximately $262 million and $247 million for the six months ended June 30, 2012 and 2011, respectively. Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $82 million and $129 million for the three months ended June 30, 2012 and 2011, respectively, and approximately $121 million and $206 million for the six months ended June 30, 2012 and 2011, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes an approximately $73 million commitment to invest in clean power and technology businesses through 2017.

Insurance - Liability for accidents at nuclear power plants is governed by the Price-Anderson Act, which limits the liability of nuclear reactor owners to the amount of insurance available from both private sources and an industry retrospective payment plan.  In accordance with this Act, NEE maintains $375 million of private liability insurance per site, which is the maximum obtainable, and participates in a secondary financial protection system, which provides up to $12.2 billion of liability insurance coverage per incident at any nuclear reactor in the United States.  Under the secondary financial protection system, NEE is subject to retrospective assessments of up to $940 million ($470 million for FPL), plus any applicable taxes, per incident at any nuclear reactor in the United States, payable at a rate not to exceed $140 million ($70 million for FPL) per incident per year.  NEE and FPL are contractually entitled to recover a proportionate share of such assessments from the owners of minority interests in Seabrook, Duane Arnold Energy Center (Duane Arnold) and St. Lucie Unit No. 2, which approximates $14 million, $35 million and $18 million, plus any applicable taxes, per incident, respectively.

NEE participates in a nuclear insurance mutual company that provides $2.75 billion of limited insurance coverage per occurrence per site for property damage, decontamination and premature decommissioning risks at its nuclear plants.  The proceeds from such insurance, however, must first be used for reactor stabilization and site decontamination before they can be used for plant repair.  NEE also participates in an insurance program that provides limited coverage for replacement power costs if a nuclear plant is out of service for an extended period of time because of an accident.  In the event of an accident at one of NEE's or another participating insured's nuclear plants, NEE could be assessed up to $178 million ($102 million for FPL), plus any applicable taxes, in retrospective premiums in a policy year.  NEE and FPL are contractually entitled to recover a proportionate share of such assessments from the owners of minority interests in Seabrook, Duane Arnold and St. Lucie Unit No. 2, which approximates $2 million, $4 million and $4 million, plus any applicable taxes, respectively.

Due to the high cost and limited coverage available from third-party insurers, NEE does not have insurance coverage for a substantial portion of its transmission and distribution property and has no insurance coverage for FPL FiberNet's fiber-optic cable.  Should FPL's future storm restoration costs exceed the reserve amount established through the issuance of storm-recovery bonds by a VIE in 2007, FPL may recover storm restoration costs, subject to prudence review by the FPSC, either through surcharges approved by the FPSC or through securitization provisions pursuant to Florida law.

In the event of a loss, the amount of insurance available might not be adequate to cover property damage and other expenses incurred.  Uninsured losses and other expenses, to the extent not recovered from customers in the case of FPL, would be borne by NEE and FPL and could have a material adverse effect on NEE's and FPL's financial condition, results of operations and liquidity.

Legal Proceedings - In November 1999, the Attorney General of the United States, on behalf of the U.S. Environmental Protection Agency (EPA), brought an action in the U.S. District Court for the Northern District of Georgia against Georgia Power Company and other subsidiaries of The Southern Company for certain alleged violations of the Prevention of Significant Deterioration (PSD) provisions and the New Source Performance Standards (NSPS) of the Clean Air Act.  In May 2001, the EPA amended its complaint to allege, among other things, that Georgia Power Company constructed and is continuing to operate Scherer Unit No. 4, in which FPL owns a 76% interest, without obtaining a PSD permit, without complying with NSPS requirements, and without applying best available control technology for nitrogen oxides, sulfur dioxides and particulate matter as required by the Clean Air Act.  It also alleges that unspecified major modifications have been made at Scherer Unit No. 4 that require its compliance with the aforementioned Clean Air Act provisions.  The EPA seeks injunctive relief requiring the installation of best available control technology and civil penalties.  Under the EPA's civil penalty rules, the EPA could assess up to $25,000 per day for each violation from an unspecified date after June 1, 1975 through January 30, 1997, up to $27,500 per day for each violation from January 31, 1997 through March 15, 2004, up to $32,500 per day for each violation from March 16, 2004 through January 12, 2009 and up to $37,500 per day for each violation thereafter.  Georgia Power Company has answered the amended complaint, asserting that it has complied with all requirements of the Clean Air Act, denying the plaintiff's allegations of liability, denying that the plaintiff is entitled to any of the relief that it seeks and raising various other defenses.  In June 2001, a federal district court stayed discovery and administratively closed the case and the EPA has not yet moved to reopen the case.  In April 2007, the U.S. Supreme Court in a separate unrelated case rejected an argument that a "major modification" occurs at a plant only when there is a resulting increase in the hourly rate of air emissions.  Georgia Power Company has made a similar argument in defense of its case, but has other factual and legal defenses that are unaffected by the U.S. Supreme Court's decision.

In 1995 and 1996, NEE, through an indirect subsidiary, purchased from Adelphia Communications Corporation (Adelphia) 1,091,524 shares of Adelphia common stock and 20,000 shares of Adelphia preferred stock (convertible into 2,358,490 shares of Adelphia common stock) for an aggregate price of approximately $35,900,000.  On January 29, 1999, Adelphia repurchased all of these shares for $149,213,130 in cash.  In June 2004, Adelphia, Adelphia Cablevision, L.L.C. and the Official Committee of Unsecured Creditors of Adelphia filed a complaint against NEE and its indirect subsidiary in the U.S. Bankruptcy Court, Southern District of New York.  The complaint alleges that the repurchase of these shares by Adelphia was a fraudulent transfer, in that at the time of the transaction Adelphia (i) was insolvent or was rendered insolvent, (ii) did not receive reasonably equivalent value in exchange for the cash it paid, and (iii) was engaged or about to engage in a business or transaction for which any property remaining with Adelphia had unreasonably small capital.  The complaint seeks the recovery for the benefit of Adelphia's bankruptcy estate of the cash paid for the repurchased shares, plus interest from January 29, 1999.  NEE has filed an answer to the complaint.  NEE believes that the complaint is without merit because, among other reasons, Adelphia will be unable to demonstrate that (i) Adelphia's repurchase of shares from NEE, which repurchase was at the market value for those shares, was not for reasonably equivalent value, (ii) Adelphia was insolvent at the time of the repurchase, or (iii) the repurchase left Adelphia with unreasonably small capital.  The trial was completed in May 2012 and closing arguments were heard in July 2012.

In October 2004, TXU Portfolio Management Company (TXU) served FPL Energy Pecos Wind I, LP, FPL Energy Pecos Wind I GP, LLC, FPL Energy Pecos Wind II, LP, FPL Energy Pecos Wind II GP, LLC and Indian Mesa Wind Farm, LP (NEER Affiliates) as defendants in a civil action filed in the District Court in Dallas County, Texas.  FPL Energy, LLC, now known as NextEra Energy Resources, LLC, was added as a defendant in 2005.  The petition alleged that the NEER Affiliates had contractual obligations to produce and sell to TXU a minimum quantity of energy and renewable energy credits each year during the period from 2002 through 2005 and that the NEER Affiliates failed to meet this obligation.  The plaintiff asserted claims for breach of contract and declaratory judgment and sought damages of approximately $34 million plus attorneys' fees, costs and interest.  Following a jury trial in 2007, among other findings, both TXU and the NEER Affiliates were found to have breached the contracts.  In August 2008, the trial court issued a final judgment holding that the contracts were not terminated and neither party was entitled to recover any damages.  In November 2008, TXU appealed the final judgment to the Fifth District Court of Appeals in Dallas, Texas.  In an opinion issued in July 2010, the appellate court reversed portions of the trial court's judgment, ruling that the contracts' liquidated damage provision is an enforceable liquidated damage clause.  The appellate court ordered that the case be remanded back to the trial court for further proceedings to determine the amount of damages payable by the NEER Affiliates.  The NEER Affiliates filed a motion for rehearing of the appellate court’s decision, which motion was denied, and in April 2011 filed a petition for review of the appellate court decision with the Texas Supreme Court. In February 2012, the Texas Supreme Court granted the petition for review and the case has been scheduled for oral argument in September 2012.

NEE and FPL are vigorously defending, and believe that they or their affiliates have meritorious defenses to, the lawsuits described above.  In addition to the legal proceedings discussed above, NEE and its subsidiaries, including FPL, are involved in other legal and regulatory proceedings, actions and claims in the ordinary course of their businesses.  Generating plants in which NEE or FPL has an ownership interest are also involved in legal and regulatory proceedings, actions and claims, the liabilities from which, if any, would be shared by NEE or FPL.  In the event that NEE and FPL, or their affiliates, do not prevail in the lawsuits described above or these other legal and regulatory proceedings, actions and claims, there may be a material adverse effect on their financial statements.  While management is unable to predict with certainty the outcome of the lawsuits described above or these other legal and regulatory proceedings, actions and claims, based on current knowledge it is not expected that their ultimate resolution, individually or collectively, will have a material adverse effect on the financial statements of NEE or FPL.