XML 28 R9.htm IDEA: XBRL DOCUMENT v2.4.0.6
REGULATION
6 Months Ended
Mar. 31, 2013
Regulated Operations [Abstract]  
REGULATION
REGULATION

NJNG is subject to cost-based regulation, therefore, it is permitted to recover authorized operating expenses and earn a reasonable return on its utility investment based on the BPU's approval, in accordance with accounting guidance applicable to regulated operations. Accordingly, NJNG capitalizes or defers certain costs that are expected to be recovered from its customers as regulatory assets and recognizes certain obligations representing amounts that are probable future expenditures as regulatory liabilities.

Regulatory assets and liabilities included on the Unaudited Condensed Consolidated Balance Sheets are comprised of the following:
(Thousands)
March 31,
2013
September 30,
2012
Regulatory assets-current
 
 
Conservation Incentive Program
$
18,383

$
25,681

Underrecovered gas costs
7,595

7,053

Total current
$
25,978

$
32,734

Regulatory assets-noncurrent
 
 
Environmental remediation costs
 
 
Expended, net of recoveries
$
48,830

$
59,745

Liability for future expenditures
182,000

182,000

Deferred income taxes
11,405

11,405

Energy Efficiency Program
31,712

26,025

New Jersey Clean Energy Program (NJCEP)
7,464

5,619

Postemployment and other benefit costs
137,700

142,495

Deferred Superstorm Sandy costs
14,666


Other
8,431

13,974

Total noncurrent
$
442,208

$
441,263

Regulatory liability-current
 
 
Derivatives, net
$

$
1,169

Total current
$

$
1,169

Regulatory liabilities-noncurrent
 
 
Cost of removal obligation
$
64,346

$
65,994

Derivatives, net
13,189

1,000

Other
1,490

83

Total noncurrent
$
79,025

$
67,077



NJNG's recovery of costs is facilitated through its base tariff rates, Basic Gas Supply Service (BGSS) and other regulatory riders. As recovery of regulatory assets is subject to BPU approval, if there are any changes in regulatory positions that indicate recovery is not probable, the related cost would be charged to income in the period of such determination.

Recent regulatory filings and/or actions include the following:

In November 2012, the BPU approved the utilities' funding obligations for NJCEP for the period from January 1, 2013 to June 30, 2013. Those programs will now be on a July 1 through June 30 fiscal year basis. NJNG's share of the total funding requirement will be approximately $9.8 million. Accordingly, NJNG recorded the obligation and a corresponding regulatory asset on the Unaudited Condensed Consolidated Balance Sheets.

On October 23, 2012, the BPU approved the Safety Acceleration and Facility Enhancement (SAFE) program, allowing a four-year incremental capital investment program of $130 million, exclusive of allowance for funds used during construction (AFUDC) accruals. The approval includes an agreement that these infrastructure costs will be subject to review in NJNG's next base rate case to be filed no later than November 2015, the deferral of depreciation expense on SAFE investments and an overall rate of return on infrastructure investments of 6.9 percent. The deferred cost recovery will include accruals for both debt and equity components of AFUDC while construction is in progress. When construction is completed and plant is placed in service, NJNG will accrue an AFUDC rate at 6.9 percent per year until such time that NJNG receives approval for recovery of all costs through base rates.
On November 19, 2012, NJNG filed a petition with the BPU requesting deferral accounting for uninsured incremental operating and maintenance costs associated with Superstorm Sandy. In addition, NJNG requested the review of and the appropriate recovery period for such deferred expenses be addressed in the Company's next base rate case. As of March 31, 2013, NJNG has recorded a regulatory asset in the amount of $14.7 million related to these costs.

In addition, on March 20, 2013, the BPU issued an order establishing a generic proceeding to review the prudency of costs incurred by New Jersey utility companies in response to major storm events in 2011 and 2012. The BPU order requires NJNG to file a detailed report by July 1, 2013, including unreimbursed, uninsured incremental storm restoration costs.

On November 20, 2012, NJNG submitted a filing requesting a base rate increase of $6.9 million for Accelerated Infrastructure Programs (AIP), related to the initial phase of AIP projects (AIP I) and the second phase of AIP projects (AIP II) infrastructure investments installed in NJNG's distribution and transmission systems through October 31, 2012. The existing weighted average cost of capital remained the same for both AIP I and AIP II investments.

On January 23, 2013, the BPU approved a stipulation to extend NJNG's current SAVEGREEN Project® (SAVEGREEN) through June 30, 2013. NJNG's July 9, 2012 petition, for an extension and expansion of the SAVEGREEN programs over a four-year period, remains open.

On March 1, 2013, NJNG and South Jersey Gas Company (SJG) filed a joint petition with the BPU requesting the continuation of the Conservation Incentive Program (CIP) with certain modifications.

On March 20, 2013, the BPU approved a February 2012 filing that requested approval of NJNG's manufactured gas plant (MGP) expenditures incurred through June 30, 2011, maintaining the existing overall social benefit clause (SBC) rate and recovery.