XML 32 R19.htm IDEA: XBRL DOCUMENT v3.23.1
Electric utility segment
3 Months Ended
Mar. 31, 2023
Electric Utility Subsidiary [Abstract]  
Electric utility segment Electric utility segment
Unconsolidated variable interest entities.
Power purchase agreements.  As of March 31, 2023, the Utilities had four power purchase agreements (PPAs) for firm capacity and other PPAs with independent power producers (IPPs) and Schedule Q providers (i.e., customers with cogeneration and/or power production facilities who buy power from or sell power to the Utilities), none of which are currently required to be consolidated as VIEs.
Pursuant to the current accounting standards for VIEs, the Utilities are deemed to have a variable interest in Kalaeloa Partners, L.P. (Kalaeloa) and Hamakua Energy by reason of the provisions of the PPA that the Utilities have with the two IPPs. However, management has concluded that the Utilities are not the primary beneficiary of Kalaeloa and Hamakua Energy because the Utilities do not have the power to direct the activities that most significantly impact the two IPPs’ economic performance nor the obligation to absorb their expected losses, if any, that could potentially be significant to the IPPs. Thus, the Utilities have not consolidated Kalaeloa and Hamakua Energy in its condensed consolidated financial statements. However, Hamakua Energy is an indirect subsidiary of Pacific Current and is consolidated in HEI’s condensed consolidated financial statements.
For the other PPAs with IPPs, the Utilities have concluded that the consolidation of the IPPs was not required because either the Utilities do not have variable interests in the IPPs due to the absence of an obligation in the PPAs for the Utilities to absorb any variability of the IPPs, or the IPP was considered a “governmental organization,” and thus excluded from the scope of accounting standards for VIEs. The consolidation of any significant IPP could have a material effect on the unaudited condensed consolidated financial statements, including the recognition of a significant amount of assets and liabilities and, if such a consolidated IPP were operating at a loss and had insufficient equity, the potential recognition of such losses. If the Utilities determine they are required to consolidate the financial statements of such an IPP and the consolidation has a material effect, the Utilities would retrospectively apply accounting standards for VIEs to the IPP.
Commitments and contingencies.
Contingencies. The Utilities are subject in the normal course of business to legal, regulatory and environmental proceedings. Management does not anticipate that the aggregate ultimate liability arising out of these pending or threatened legal proceedings will be material to its financial position. However, the Utilities cannot rule out the possibility that such outcomes could have a material effect on the results of operations or liquidity for a particular reporting period in the future. The Utilities record loss contingencies when the outcome of such proceedings is probable and when the amount of the loss is reasonably estimable. The Utilities also evaluate, on a continuous basis, whether developments in such proceedings could cause these assessments or estimates to change. Assessment regarding future events is required when evaluating whether a loss is probable or reasonably possible, and as to whether such loss or a range of such loss is estimable. Management is often unable to estimate a reasonably possible loss, or a range of loss, particularly in cases in which: (i) the damages sought are indeterminate or the basis for the damages claimed is not clear; (ii) proceedings are in early stages; (iii) discovery is not complete; (iv) the matters involve novel or unsettled legal theories; (v) significant facts are in dispute; (vi) a large number of parties are represented (including circumstances in which it is uncertain how liability, if any, would be shared among multiple defendants); (vii) a lower court or administrative agency’s decision or ruling has been appealed; and/or (vii) a wide range of potential outcomes exist. In such cases, there may be considerable uncertainty regarding the timing or ultimate resolution, including any possible loss, fine, penalty, or business impact.
Power purchase agreements.  Purchases from all IPPs were as follows:
 Three months ended March 31
(in millions)20232022
Kalaeloa$67 $60 
AES Hawaii 1
— 27 
HPOWER18 19 
Hamakua Energy20 16 
Puna Geothermal Venture10 
Wind IPPs24 18 
Solar IPPs14 13 
Other IPPs 2
Total IPPs$153 $164 
1 The term of the PPA with AES Hawaii expired on September 1, 2022 and the AES Hawaii coal plant ceased operations.
2 Includes hydro power and other PPAs.
Kalaeloa Partners, L.P.  Under a 1988 PPA, as amended, Hawaiian Electric is committed to purchase 208 MW of firm capacity from Kalaeloa. In October 2021, Hawaiian Electric and Kalaeloa signed the Amended and Restated Power Purchase Agreement for Firm Dispatchable Capacity and Energy (Amended and Restated PPA) to extend the PPA for an additional term of 10 years. The Amended and Restated PPA was approved by the PUC on November 23, 2022. The new pricing provisions in the Amended and Restated PPA took effect on January 1, 2023.
Stage 1 Renewable PPAs. In February 2018, the Utilities issued their Stage 1 renewable request for proposals and have procured eight renewable PPAs with a total of 274.5 MW capacity. The total annual payments to be made by the Utilities under the eight renewable PPAs are estimated at $64.5 million. The Utilities have received PUC approvals to recover the total projected annual payments under the eight renewable PPAs through the purchased power adjustment clause (PPAC) to the extent such costs are not included in base rates. As of March 31, 2023, the Utilities have accounted for the battery portion of two PPAs that were placed in service during 2022 and first quarter of 2023 as finance leases and recorded lease liabilities with corresponding right-of-use assets of $88 million. On April 21, 2023, the AES Waikoloa Solar project with a capacity of 30 MW, including 120 MWh of batteries, was placed into commercial operation on Hawaii Island, and the battery portion of the PPA will be recorded as a finance lease during the second quarter of 2023. The timing of the Utilities’ recognition of the expense conforms to ratemaking treatment for the Utilities’ recovery of the cost of electricity and is included in purchased power for the interest and amortization of financing leases related to PPAs. Any material differences between expense recognition and timing of payments is deferred as a regulatory asset or liability in order to match what is being recovered for ratemaking purposes.
Hu Honua Bioenergy, LLC (Hu Honua). In May 2012, Hawaii Electric Light signed a PPA, which the PUC approved in December 2013, with Hu Honua for 21.5 MW of renewable, dispatchable firm capacity fueled by locally grown biomass from a facility on the island of Hawaii. Under the terms of the PPA, the Hu Honua plant was scheduled to be in service in 2016. However, Hu Honua encountered construction and litigation delays, which resulted in an amended and restated PPA between Hawaii Electric Light and Hu Honua dated May 9, 2017. On May 23, 2022, the PUC issued a decision and order denying the amended and restated PPA, based on, among other things, findings that: (1) the project will result in significant greenhouse gas (GHG) emissions, (2) Hu Honua’s proposed carbon commitment to sequester more GHG emissions than produced by the project are speculative and unsupported, (3) the amended and restated PPA is likely to result in high costs to customers through its relatively high cost of electricity and through potential displacement of other, lower cost, renewable resources, and (4) based on the foregoing, approving the amended and restated PPA is not prudent or in the public interest. On June 2, 2022, Hawaii Electric Light and Hu Honua filed their separate motions for reconsideration, which were denied by the PUC on June 24, 2022. On June 29, 2022, Hu Honua filed its notice of appeal to the Hawaii Supreme Court of the PUC’s May 23, 2022 decision and order denying the amended and restated PPA, and the PUC’s June 24, 2022 order denying Hawaii Electric Light and Hu Honua’s motions for reconsideration. Opening briefs were filed with the Supreme Court on October 5, 2022. Answering briefs were filed on December 5, 2022, and reply briefs were filed on December 28, 2022. The Supreme Court heard oral arguments on January 31, 2023. On March 13, 2023, the Hawaii Supreme Court affirmed the PUC’s decision denying the amended and restated PPA between Hu Honua and Hawaii Electric Light and entered its judgment on appeal on April 12, 2023.
Molokai New Energy Partners (MNEP). In July 2018, the PUC approved Maui Electric’s PPA with MNEP to purchase solar energy from a photovoltaic (PV) plus battery storage project. The 4.88 MW PV and 3 MW Battery Energy Storage System project was to deliver no more than 2.64 MW at any time to the Molokai system. On March 25, 2020, MNEP filed a complaint in the United Stated District Court for the District of Hawaii against Maui Electric claiming breach of contract. On June 3, 2020, Maui Electric provided a Notice of Default and Termination of the PPA to MNEP terminating the PPA with an effective date of July 10, 2020. Thereafter, MNEP filed an amended complaint to include claims relating to the termination and Hawaiian Electric filed its answer to the amended complaint on September 11, 2020, disputing the facts presented by MNEP and all claims within the original and amended complaint. Currently, the discovery phase is ongoing.
Utility projects.  Many public utility projects require PUC approval and various permits from other governmental agencies. Difficulties in obtaining, or the inability to obtain, the necessary approvals or permits or community support can result in significantly increased project costs or even cancellation of projects. In the event a project does not proceed, or if it becomes probable the PUC will disallow cost recovery for all or part of a project, or if PUC-imposed caps on project costs are expected to be exceeded, project costs may need to be written off in amounts that could result in significant reductions in Hawaiian Electric’s consolidated net income.
Enterprise Resource Planning/Enterprise Asset Management (ERP/EAM) implementation project. The ERP/EAM Implementation Project went live in October 2018. Hawaii Electric Light and Hawaiian Electric began to incorporate their portion of the deferred project costs in rate base and started the amortization over a 12-year period in January 2020 and
November 2020, respectively. The PUC required a minimum of $246 million ERP/EAM project-related benefit to be delivered to customers over the system’s 12-year service life.
In February 2019, the PUC approved a methodology for passing the future cost saving benefits of the new ERP/EAM system to customers developed by the Utilities in collaboration with the Consumer Advocate. The Utilities filed a benefits clarification document on June 10, 2019, reflecting $150 million in future net other operation and maintenance (O&M) expense reductions and cost avoidance, and $96 million in capital cost reductions and tax savings over the 12-year service life. To the extent the reduction in O&M expense relates to amounts reflected in electric rates, the Utilities would reduce future rates for such amounts. In October 2019, the PUC approved the Utilities and the Consumer Advocate’s Stipulated Performance Metrics and Tracking Mechanism. As of March 31, 2023, the Utilities’ regulatory liability was $11.0 million ($3.7 million for Hawaiian Electric, $2.9 million for Hawaii Electric Light and $4.4 million for Maui Electric) for the O&M expense savings that are being amortized or to be included in future rates. As part of the settlement agreement approved in the Hawaiian Electric 2020 test year rate case, the regulatory liability for Hawaiian Electric will be amortized over five years, beginning in November 2020, and the O&M benefits for Hawaiian Electric was considered flowed through to customers.
At the PUC’s direction, the Utilities have been filing Annual Enterprise System Benefits (AESB) report on the achieved benefits savings. The most recent AESB report was filed on February 14, 2023 for the period January 1 through December 31, 2022.
Waena Switchyard/Synchronous Condenser Project. In October 2020, to support efforts to increase renewable energy generation and reduce fossil fuel consumption by deactivating current generating units, Maui Electric filed a PUC application to construct a switchyard, which includes the extension of two 69 kV transmission lines and the relocation of another 69 kV transmission line; and the conversion of two generating units to synchronous condensers at Kahului Power Plant in central Maui. In November 2021, the PUC approved Maui Electric’s request to commit funds estimated at $38.8 million for the project, and to recover capital expenditures for the project under Exceptional Project Recovery Mechanism (EPRM) not to exceed $38.8 million, which shall be further reduced to reflect the total project cost exclusive of overhead costs not directly attributable to the project. The Waena Switchyard project is expected to be placed in service in the third quarter of 2023, while the conversion of the two generating units will be performed after the retirement of Kahului Power Plant Units 3 and 4.
In approving the project, the PUC recognized that the project will facilitate the ability to accommodate increased renewable energy, as contemplated under the EPRM guidelines. As of March 31, 2023, $17.1 million has been incurred for the project.
Environmental regulation.  The Utilities are subject to environmental laws and regulations that regulate the operation of existing facilities, the construction and operation of new facilities and the proper cleanup and disposal of hazardous waste and toxic substances.
Hawaiian Electric, Hawaii Electric Light and Maui Electric, like other utilities, periodically encounter petroleum or other chemical releases associated with current or previous operations. The Utilities report and take action on these releases when and as required by applicable law and regulations. The Utilities believe the costs of responding to such releases identified to date will not have a material effect, individually or in the aggregate, on Hawaiian Electric’s consolidated results of operations, financial condition or liquidity.
Former Molokai Electric Company generation site.  In 1989, Maui Electric acquired Molokai Electric Company. Molokai Electric Company had sold its former generation site (Site) in 1983, but continued to operate at the Site under a lease until 1985 and left the property in 1987. The federal Environmental Protection Agency (EPA) has since identified environmental impacts in the subsurface soil at the Site. In cooperation with the Department of Health of State of Hawaii and EPA, Maui Electric further investigated the Site and the adjacent parcel to determine the extent of impacts of polychlorinated biphenyls (PCBs), residual fuel oils and other subsurface contaminants. Maui Electric has a reserve balance of $2.6 million as of March 31, 2023, representing the probable and reasonably estimable undiscounted cost for remediation of the Site and the adjacent parcel based on presently available information; however, final costs of remediation will depend on the cleanup approach implemented.
Additionally, on November 24, 2021, the current landowners of the Site, Misaki’s, Inc., filed a lawsuit against Hawaiian Electric (as alleged successor in interest to Molokai Electric, the prior owner of the Site) in the Circuit Court of the Second Circuit of the State of Hawaii (removed to the U.S. District Court for the District of Hawaii). The complaint, which was subsequently amended to include Maui Electric, alleges that Hawaiian Electric is responsible for remediation of the Site based on the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), and the Hawaii Environmental Response Law under Hawaii Revised Statutes Chapter 128D, as well as being liable on contractual claims related to a short leaseback period during the transition of ownership from Molokai Electric. The amended complaint was dismissed and a new complaint may be filed subject to the parties attempt to enter into settlement negotiations, but the Utilities
intend to vigorously defend the action if necessary. At this time, the Utilities are unable to determine the ultimate outcome of the lawsuit or the amount of any possible loss. As of March 31, 2023, the reserve balance recorded by the Utilities to address the lawsuit was not material.
Pearl Harbor sediment study. In July 2014, the U.S. Navy notified Hawaiian Electric of the Navy’s determination that Hawaiian Electric is a Potentially Responsible Party under CERCLA responsible for the costs of investigation and cleanup of PCB contamination in sediment in the area offshore of the Waiau Power Plant as part of the Pearl Harbor Superfund Site. Hawaiian Electric was also required by the EPA to assess potential sources and extent of PCB contamination onshore at Waiau Power Plant.
As of March 31, 2023, the reserve account balance recorded by Hawaiian Electric to address the PCB contamination was $9.9 million. The reserve balance represents the probable and reasonably estimable undiscounted cost for the onshore and offshore investigation and remediation. The final remediation costs will depend on the actual onshore and offshore cleanup costs.
Regulatory proceedings
Decoupling. Decoupling is a regulatory model that is intended to provide the Utilities with financial stability and facilitate meeting the State of Hawaii’s goals to transition to a clean energy economy and achieve an aggressive renewable portfolio standard. Decoupling delinks the utility’s revenues from the utility’s sales, removing the disincentive to promote energy efficiency and accept more renewable energy. Decoupling continues under the PBR Framework.
Performance-based regulation framework. On December 23, 2020, the PUC issued a decision and order (PBR D&O) establishing the PBR Framework to govern the Utilities. The PBR Framework incorporates an annual revenue adjustment (ARA) and a suite of new regulatory mechanisms in addition to previously established regulatory mechanisms. Under the PBR Framework, the decoupling mechanism (i.e., the Revenue Balancing Account (RBA)) established by the previous regulatory framework will continue. The existing cost recovery mechanisms will continue as currently implemented (e.g., the Energy Cost Recovery Clause, PPAC, Demand Side Management surcharge, Renewable Energy Infrastructure Program, Demand Response Adjustment Clause, Pension and Other Post-Employment Benefits (OPEB) tracking mechanisms). In addition to annual revenues provided by the ARA, the Utilities may seek relief for extraordinary projects or programs through the Exceptional Project Recovery Mechanism (EPRM) (formerly known as the Major Project Interim Recovery adjustment mechanism) and earn financial rewards for exemplary performance as provided through a portfolio of Performance Incentive Mechanisms (PIMs) and Shared Savings Mechanisms (SSMs). The PBR Framework incorporates a variety of additional performance mechanisms, including Scorecards, Reported Metrics, and an expedited Pilot Process. The PBR Framework also contains a number of safeguards, including a symmetric Earnings Sharing Mechanism (ESM) which protects the Utilities and customers from excessive earnings or losses, as measured by the Utilities’ achieved rate-making ROACE and a Re-Opener mechanism, under which the PUC will open an examination, at its discretion, to determine if adjustments or modifications to specific PBR mechanisms are appropriate. The PBR Framework became fully effective on June 1, 2021.
On June 17, 2022, the PUC issued a decision and order (June 2022 D&O) establishing additional PIMs under the PBR Framework for the Utilities. The June 2022 D&O approved two new PIMs, a new SSM, and extended the timeframe for an existing PIM. Of the new PIMs, only one is penalty-only. Specifically, the PUC approved (1) a new (penalty-only) generation-caused interruption reliability PIM, (2) a new (penalty/reward) interconnection requirements study (IRS) PIM, (3) a new (reward-only) Collective Shared Savings Mechanism (CSSM), and (4) a modification and extension of the existing interim (reward-only) Grid Services PIM. On November 23, 2022, the PUC approved the Utilities’ proposed tariffs to implement the aforementioned PIMs with an effective date of January 1, 2023.
In addition, the June 2022 D&O instructed the Utilities to prepare and submit: a detailed fossil fuel retirement report (FF Retirement Report) outlining necessary steps to safely and reliably retire certain existing fossil fuel power plants during the first multi-year rate period (MRP); and a functional integration plan (FIP) for distributed energy resources (DER) to increase transparency into the Utilities’ plans and progress for utilizing cost-effective grid services from DERs and ensure that the necessary functionalities and requisite technologies are in place to do so. The PUC also instructed the PBR Working Group to continue its ongoing collaborative efforts to consider other potential new incentive mechanisms and to address other issues raised during the proceeding. On March 30, 2023, the PUC held a PBR Working Group coordination meeting to initiate subgroups on the priority topics of a long-term DER Grid Services PIM, modification to/evaluation of existing PIMs, and a comprehensive PBR Framework review to be addressed in the near term.
In accordance with the June 2022 D&O, the Utilities filed their FIP and FF Retirement Report with the PUC on September 30, 2022 and April 17, 2023, respectively.
Revenue adjustment mechanism. Prior to the implementation of the PBR Framework, the revenue adjustment mechanism (RAM) was a major component of the previously established regulatory framework. The RAM was based on the lesser of: a) an inflationary adjustment for certain O&M expenses and return on investment for certain rate base changes, or b) cumulative annual compounded increase in Gross Domestic Product Price Index applied to annualized target revenues (the RAM Cap). Under the PBR Framework, the ARA mechanism replaced the RAM, and became effective on June 1, 2021. RAM revenue adjustments approved by the PUC in 2020 will continue to be included in the RBA provision’s target revenue and RBA rate adjustment unless modified with PUC approval.
Annual revenue adjustment mechanism. The PBR Framework established a five-year MRP during which there will be no general rate cases. Target revenues will be adjusted according to an index-driven ARA based on (i) an inflation factor, (ii) a predetermined X-factor to encompass productivity, which is set at zero, (iii) a Z-factor to account for exceptional circumstances not in the Utilities’ control and (iv) a customer dividend consisting of a negative adjustment of 0.22% of adjusted revenue requirements compounded annually and a flow through of the “pre-PBR” savings commitment from the management audit recommendations developed in a prior docket at a rate of $6.6 million per year from 2021 to 2025. The implementation of the ARA occurred on June 1, 2021.
Earnings sharing mechanism. The PBR Framework established a symmetrical ESM for achieved rate-making ROACE outside of a 300 basis points dead band above or below the current authorized ROACE of 9.5% for each of the Utilities. There is a 50/50 sharing between customers and Utilities for the achieved rate-making ROACE falling within 150 basis points outside of the dead band in either direction, and a 90/10 sharing for any further difference. A reopening or review of the PBR terms will be triggered if the Utilities credit rating outlook indicates a potential credit downgrade below investment grade status, or if its achieved rate-making ROACE enters the outer most tier of the ESM.
Exceptional project recovery mechanism. Prior to the implementation of the PBR Framework, the PUC established the Major Project Interim Recovery (MPIR) adjustment mechanism and MPIR Guidelines. The MPIR mechanism provides the opportunity to recover revenues for net costs of approved eligible projects placed in service between general rate cases. In establishing the PBR Framework, the MPIR Guidelines were terminated and replaced with the EPRM Guidelines. Although the MPIR Guidelines were terminated and replaced by the EPRM Guidelines, the MPIR mechanism will continue within the PBR Framework to provide recovery of project costs previously approved for recovery under the MPIR. The established EPRM Guidelines permit the Utilities to include the full amount of approved costs in the EPRM for recovery in the first year the project goes into service, pro-rated for the portion of the year the project is in service. Deferred and O&M expense projects are also eligible for EPRM recovery under the EPRM Guidelines. EPRM recoverable costs will be limited to the lesser of actual incurred project costs or PUC‑approved amounts, net of savings.
As of March 31, 2023, the Utilities annualized MPIR and EPRM revenue amounts totaled $26.2 million, including revenue taxes, for the Schofield Generating Station ($16.5 million), West Loch PV project ($3.5 million), Grid Modernization Strategy (GMS) Phase 1 project ($6.1 million for all three utilities) and Waiawa UFLS project ($0.1 million) that included the 2022 return on project amount (based on approved amounts) in rate base, depreciation and incremental O&M expenses. The PUC approved the Utilities’ recovery of the annualized 2022 MPIR amounts for the Schofield Generating Station, West Loch PV, and GMS Phase 1 projects effective June 1, 2022 through the RBA rate adjustment. Recovery of the incremental change to the West Loch PV project and Waiawa UFLS project were approved on December 7, 2022 and December 5, 2022, respectively.
As of March 31, 2023, the PUC approved two EPRM applications for projects totaling $41 million to the extent that the project costs are not included in rates. Currently, the Utilities are seeking EPRM recovery for six projects with total project costs up to $480 million, subject to PUC approval.
Pilot process. As part of the PBR Framework, the PUC approved a Pilot Process to foster innovation by establishing an expedited implementation process for pilots that tests new technologies, programs, business models, and other arrangements. Under the Pilot Process, the Utilities submit specific pilot proposals (Pilot Notices) that are within the scope of the approved Workplan to the PUC for their expedited review. The PUC will strive to issue an order addressing a proposed pilot within 45 days of the filing date of a Pilot Notice. If the PUC does not take affirmative action on a Pilot Notice by the end of the 45-day period, the Pilot Notice shall be considered approved as submitted. The PUC may modify the pilot as originally proposed, and the Utilities shall have 15 days to notify the PUC whether the Utilities accept the modification, propose further modification, or withdraw the Pilot Notice. The PUC may also, where necessary, suspend the Pilot Notice for further investigation.
The approved Pilot Process includes a cost recovery process that generally allows the Utilities to defer and recover total annual expenditures of approved pilot projects net of revenues, subject to an annual cap of $10 million, over 12 months beginning June 1 of the year following pilot implementation through the RBA rate adjustment, although the PUC may determine on a case-by-case basis that a particular project’s deferred costs should be amortized over a period greater than 12 months.
On February 28, 2023, the Utilities filed their annual Pilot Update report covering pilot projects that were active during 2022, including reporting on pilot projects that were initiated prior to the commencement of the Pilot Process. The Pilot Update reported on approximately $0.4 million of 2022 recorded pilot project costs including revenue taxes for the Utilities. The 2022 recorded pilot project costs were included in the Utilities’ proposed adjustments to target revenue in the 2023 spring revenue report filed on March 28, 2023.
On February 2, 2023, the Utilities filed a Pilot Notice to commence an EV Telematics Pilot project in April 2023. On March 22, 2023, the PUC issued an order approving the Utilities’ EV Telematics Pilot project. The order also temporarily suspends the filing of Pilot Notices, pending a stakeholder meeting to be held in the second quarter of 2023, to discuss the Pilot Process and potential improvements.
Performance incentive mechanisms. The PUC has established the following PIMs and SSMs: (1) Service Quality performance incentives, (2) Phase 1 Request for proposal (RFP) PIM for procurement of low-cost renewable energy, (3) Phase 2 RFP PIMs for generation and generation plus storage project, and Grid Services and standalone storage, (4) new PIMs established in the PBR D&O and (5) new PIMs and a SSM established in the June 2022 D&O.
Service Quality performance incentives (ongoing). Service Quality performance incentives are measured on a calendar-year basis. The PIM tariff requires the performance targets, deadbands and the amount of maximum financial incentives used to determine the PIM financial incentive levels for each of the PIMs to remain constant in interim periods, unless otherwise amended by order of the PUC.
Service Reliability Performance measured by Transmission and Distribution-caused System Average Interruption Duration and Frequency Indexes (penalties only). Target performance is based on each utility’s historical 10-year average performance with a deadband of one standard deviation. The maximum penalty for each performance index is 20 basis points applied to the common equity share of each respective utility’s approved rate base (or maximum penalties of approximately $6.8 million - for both indices in total for the three utilities). For the 2022 evaluation period, the Utilities incurred $(0.1) million in penalties.
Call Center Performance measured by the percentage of calls answered within 30 seconds. Target performance is based on the annual average performance for each utility for the most recent eight quarters with a deadband of 3% above and below the target. The maximum penalty or reward is 8 basis points applied to the common equity share of each respective utility’s approved rate base (or maximum penalties or rewards of approximately $1.4 million - in total for the three utilities).
Phase 1 RFP PIM. Procurement of low-cost variable renewable resources through the RFP process in 2018 is measured by comparison of the procurement price to target prices. The first portion of the incentive was earned upon PUC approval of the PPAs. Based on the seven PPAs approved in 2019, the Utilities recognized $1.7 million in 2019 with the remaining award to be recognized in the year following the in-service date of the projects, which is estimated to occur from 2023 to 2025.
Phase 2 RFP PIMs. The PUC order issued on October 9, 2019 establishes pricing thresholds, timelines to complete contracting, and other performance criteria for the performance incentive eligibility. The PIMs provide incentives only without penalties. On July 9, 2020, the Utilities filed two Grid Services Purchase Agreements (GSPA) for the Grid Service RFP that potentially qualify for a demand response PIM; however, details of the incentive metrics will be determined by the PUC. On September 15, 2020, the Utilities filed one PPA that qualified for a PIM incentive and on February 16, 2021, the Utilities filed one additional PPA that qualified for a declining PIM incentive. The PUC approved two PPAs in September 2021 and November 2021 and two GSPAs on December 31, 2020. Based on the two approved PPAs, the Utilities recognized $0.1 million in rewards in 2021. In December 2022 and March 2023, these two PPAs were terminated or declared null and void.
The PUC previously established the following two PIMs in its PBR D&O, which were approved in an order issued on March 23, 2021 and became effective on June 1, 2021. In its June 2022 D&O, the PUC modified and extended the Grid Services PIM.
Renewable portfolio standard (RPS) - A PIM that provides a financial reward for accelerating the achievement of RPS goals. The Utilities may earn a reward for the amount of system generation above the interpolated statutory RPS goal at $20/MWh in 2021 and 2022, $15/MWh in 2023, and $10/MWh for the remainder of the MRP. Penalties are already prescribed in the RPS as $20/MWh for failing to meet RPS targets in 2030, 2040 and 2045. The evaluation period commenced on January 1, 2021.
Grid Services PIM that provides financial rewards on a $/kW basis for the acquisition of eligible grid services. The eligibility period for this PIM initially commenced on January 1, 2021 and was scheduled to end on
December 31, 2022. However, the June 2022 D&O extended the eligibility period for this PIM through December 31, 2023. The June 2022 D&O also increased the incentive rate for the acquisition of load reduction grid services. During the PIM performance period, newly acquired committed capacity in the Oahu Scheduled Dispatch Program (SDP), the Oahu Fast DR program (up to the 7 MW cap), and the Maui SDP program shall qualify for the incentive. The Utilities can earn a maximum reward of $1.5 million from 2021 through 2023. In 2022, the Utilities earned $0.04 million in rewards.
The PUC also previously established the following three PIMs in its PBR D&O, which were approved by the PUC on May 17, 2021 and became effective on June 1, 2021.
Interconnection Approval PIM that provides financial rewards and penalties for interconnection times for DER systems <100 kW in size. The Utilities can earn a total annual maximum reward of $3.0 million or a total annual maximum penalty of $0.9 million. In 2022, the Utilities earned $3.0 million in rewards.
Low-to-Moderate Income (LMI) Energy Efficiency PIM that provides financial rewards for collaboration between the Utilities and the third-party Public Benefits Fee Administrator to deliver energy savings for low- and moderate-income customers. The Utilities can earn a total annual maximum reward of $2.0 million. The PIM will initially have a duration of three years and be subject to an annual review. The evaluation period is based on Hawaii Energy’s program year with the initial evaluation year being the period of July 1, 2021 through June 30, 2022. The Utilities earned $0.5 million in rewards for the program period ending June 30, 2022.
Advanced Metering Infrastructure Utilization PIM that provides financial rewards for leveraging grid modernization investments and engaging customers beyond what is already planned in the Phase 1 Grid Modernization program. The Utilities can earn a total annual maximum reward of $2.0 million. The PIM will initially have a duration of three years after which it will be re-evaluated. The evaluation period commenced on January 1, 2021.
The PUC established the following new PIMs and SSM in its June 2022 D&O, which became effective on January 1, 2023.
Generation-caused System Average Interruption Duration and Frequency Indexes PIMs to incentivize achievement of generation-based reliability targets, measured by Generation System Average Interruption Duration and Frequency Indexes (penalties only). Target performance is based on each utility’s historical 10-year average performance with a deadband of one standard deviation. The maximum penalty for each performance index is 3 basis points applied to the common equity share of each respective utility’s approved rate base (or maximum penalties of approximately $1 million - for both indices in total for the three utilities).
An IRS PIM to incentivize the timely completion of the IRS process for large-scale renewable energy projects (rewards and penalties) measured by the number of months between final model checkout and delivery of IRS results to the developer. Target performance is ten months with an asymmetrical deadband of two-months for penalties and no deadband for rewards. The maximum penalty and reward will depend on the specifics of the upcoming procurement.
A CSSM to incentivize cost control over the Utilities’ fuel, purchased power, and EPRM/MPIR costs (collectively, non-ARA costs). This is a reward only incentive where the Utilities retain 20% share of savings when non-ARA costs in a performance year are lower than target year non-ARA costs, which are adjusted for changes in fuel prices, inflation, and system generation from a base year (calendar year 2021). The CSSM does not have a potential penalty and does not have a cap for maximum reward.
For the 2022 evaluation period, the Utilities earned $3.4 million ($2.5 million for Hawaiian Electric, $0.4 million for Hawaii Electric Light and $0.5 million for Maui Electric) in rewards net of penalties. The net rewards related to 2022 were reflected in the 2023 PIMs annual report and 2023 spring revenue report filings.
Annual review cycle. PBR D&O established an annual review cycle for revenue adjustments under the PBR Framework, including the biannual submission of the revenue reports. The Utilities filed the spring revenue report on March 28, 2023, which is subject to PUC approval.
The net incremental amounts between the 2022 fall and 2023 spring revenue reports are shown in the following table. The amounts are to be collected (refunded) from June, 1, 2023 through May 31, 2024 under the RBA rate tariffs, which were included in the 2023 spring revenue report filing.
(in millions)Hawaiian ElectricHawaii Electric LightMaui ElectricTotal
Incremental Performance Incentive Mechanisms (net)
(0.4)0.1 0.1 (0.2)
Incremental EPRM/MPIR Revenue Adjustment2.5 1.4 1.0 4.9
Other0.4 0.1 — $0.5 
Net incremental amount to be collected under the RBA rate tariffs$2.5 $1.5 $1.1 $5.1 
Note: Columns may not foot due to rounding.
Regulatory assets for COVID-19 related costs. On May 4, 2020, the PUC issued an order, authorizing all utilities, including the Utilities, to establish regulatory assets to record costs resulting from the suspension of disconnections of service during the pendency of the Governor’s Emergency Proclamation and until otherwise ordered by the PUC. In future proceedings, the PUC will consider the reasonableness of the costs, the appropriate period of recovery, any amount of carrying costs thereon, and any savings directly attributable to suspension of disconnects, and other related matters. As part of the order, the PUC prohibits the Utilities from charging late payment fees on past due payments. As the moratorium on customer disconnections ended on May 31, 2021, the Utilities have resumed charging late payment fees in July 2021. Pursuant to PUC orders, the deferral of COVID-19 related costs by the Utilities ended on December 31, 2020. On October 1, 2021, the PUC approved the Utilities’ request to extend the deferral period to December 31, 2021. In December 2021, to keep customers connected and provide some relief to customers experiencing financial difficulty during the pandemic, the Utilities committed to issuing $2 million in bill credits to qualified customers. The Utilities will not seek recovery for the issued bill credits, resulting in a reduction to the cumulative deferred costs. On June 9, 2022, the Utilities filed an application with the PUC, requesting recovery of a portion of the COVID-19 related deferral costs, net of cost savings realized, not to exceed the amount of $27.8 million over three years, from June 2023 through May 2026. Annual requests will be limited to actual costs incurred. On January 25, 2023, the PUC issued an order to modify the procedural schedule to allow more time for more discovery and consideration of the application. As of March 31, 2023, the Utilities have recorded $9.6 million in regulatory assets for deferral of COVID-19 related costs. The updated amounts have been reflected in the Utilities’ First Supplemental Report to the PUC filed on April 28, 2023.
Army privatization. On October 30, 2020, the PUC approved Hawaiian Electric’s 50-year contract with the U.S. Army to own, operate and maintain the electric distribution system serving the U.S. Army’s 12 installations on Oahu, including Schofield Barracks, Wheeler Army Airfield, Tripler Army Medical Center, Fort Shafter, and Army housing areas. On March 1, 2022, Hawaiian Electric acquired the Army’s existing distribution system for a purchase price of $14.5 million, and will pay the Army in the form of a monthly credit against the monthly utility services charge over the 50-year term of the contract. The acquisition of additional assets contemplated in the contract, with an estimated value of $4 million, is planned for 2024.
Hawaiian Electric took ownership and all responsibilities for operation and maintenance of the system on March 1, 2022 for a 50-year term after a one-year transition period. Under the contract, Hawaiian Electric will make initial capital upgrades over the first six years of the contract and replace aging infrastructure over the 50-year term. In addition to its regular monthly electricity bill, the Army will pay Hawaiian Electric a monthly utility services charge to cover operations and maintenance expenses and provide recovery for capital upgrades, capital replacements, and the existing distribution system based on a rate of return determined by the PUC for regulated utility investments, as well as depreciation expense. The PUC requires Hawaiian Electric to file regular periodic reports on the activities and investments in fulfillment of the contract and will review the major projects planned on behalf of the Army. The annual impact on Hawaiian Electric’s earnings is not expected to be material and will depend on a number of factors, including the amount and timing of capital upgrades and capital replacement.
Condensed consolidating financial information. Condensed consolidating financial information for Hawaiian Electric and its subsidiaries are presented for the three month periods ended March 31, 2023 and 2022, and as of March 31, 2023 and December 31, 2022.
Hawaiian Electric unconditionally guarantees Hawaii Electric Light’s and Maui Electric’s obligations (a) to the State of Hawaii for the repayment of principal and interest on Special Purpose Revenue Bonds issued for the benefit of Hawaii Electric Light and Maui Electric, and (b) under their respective private placement note agreements and the Hawaii Electric Light notes and Maui Electric notes issued thereunder. Hawaiian Electric is also obligated, after the satisfaction of its obligations on its own preferred stock, to make dividend, redemption and liquidation payments on Hawaii Electric Light’s and Maui Electric’s preferred stock if the respective subsidiary is unable to make such payments.
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Income
Three months ended March 31, 2023
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther subsidiariesConsolidating adjustmentsHawaiian Electric
Consolidated
Revenues$601,530 115,288 113,673 — (130)$830,361 
Expenses
Fuel oil253,827 27,760 52,510 — — 334,097 
Purchased power110,279 34,086 8,396 — — 152,761 
Other operation and maintenance83,233 21,350 23,733 — — 128,316 
Depreciation41,038 10,635 9,254 — — 60,927 
Taxes, other than income taxes56,953 10,737 10,695 — — 78,385 
   Total expenses545,330 104,568 104,588 — — 754,486 
Operating income56,200 10,720 9,085 — (130)75,875 
Allowance for equity funds used during construction2,640 284 377 — — 3,301 
Equity in earnings of subsidiaries11,541 — — — (11,541)— 
Retirement defined benefits credit (expense)—other than service costs904 169 (26)— — 1,047 
Interest expense and other charges, net(14,557)(2,831)(2,988)— 130 (20,246)
Allowance for borrowed funds used during construction918 91 122 — — 1,131 
Income before income taxes57,646 8,433 6,570 — (11,541)61,108 
Income taxes10,367 1,909 1,324 — — 13,600 
Net income47,279 6,524 5,246 — (11,541)47,508 
Preferred stock dividends of subsidiaries— 134 95 — — 229 
Net income attributable to Hawaiian Electric47,279 6,390 5,151 — (11,541)47,279 
Preferred stock dividends of Hawaiian Electric270 — — — — 270 
Net income for common stock$47,009 6,390 5,151 — (11,541)$47,009 


Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Comprehensive Income
Three months ended March 31, 2023
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther subsidiariesConsolidating adjustmentsHawaiian Electric Consolidated
Net income for common stock$47,009 6,390 5,151 — (11,541)$47,009 
Other comprehensive loss, net of taxes:
Retirement benefit plans:
Adjustment for amortization of prior service credit and net gains recognized during the period in net periodic benefit cost, net of taxes(470)(56)(63)— 119 (470)
Reclassification adjustment for impact of D&Os of the PUC included in regulatory assets, net of taxes425 50 57 — (107)425 
Other comprehensive loss, net of taxes(45)(6)(6)— 12 (45)
Comprehensive income attributable to common shareholder$46,964 6,384 5,145 — (11,529)$46,964 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Income
Three months ended March 31, 2022

(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther subsidiariesConsolidating adjustmentsHawaiian Electric
Consolidated
Revenues$500,242 108,528 100,028 — (6)$708,792 
Expenses
Fuel oil154,425 25,251 41,610 — — 221,286 
Purchased power124,183 30,712 8,638 — — 163,533 
Other operation and maintenance83,656 20,214 21,387 — — 125,257 
Depreciation39,484 10,351 8,636 — — 58,471 
Taxes, other than income taxes47,274 10,032 9,344 — — 66,650 
   Total expenses449,022 96,560 89,615 — — 635,197 
Operating income51,220 11,968 10,413 — (6)73,595 
Allowance for equity funds used during construction1,990 193 226 — — 2,409 
Equity in earnings of subsidiaries13,661 — — — (13,661)— 
Retirement defined benefits credit (expense)—other than service costs855 167 (32)— — 990 
Interest expense and other charges, net(13,093)(2,609)(2,630)— (18,326)
Allowance for borrowed funds used during construction651 60 67 — — 778 
Income before income taxes55,284 9,779 8,044 — (13,661)59,446 
Income taxes8,605 2,268 1,665 — — 12,538 
Net income46,679 7,511 6,379 — (13,661)46,908 
Preferred stock dividends of subsidiaries— 134 95 — — 229 
Net income attributable to Hawaiian Electric46,679 7,377 6,284 — (13,661)46,679 
Preferred stock dividends of Hawaiian Electric270 — — — — 270 
Net income for common stock$46,409 7,377 6,284 — (13,661)$46,409 


Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Comprehensive Income
Three months ended March 31, 2022
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther subsidiariesConsolidating adjustmentsHawaiian Electric Consolidated
Net income for common stock$46,409 7,377 6,284 — (13,661)$46,409 
Other comprehensive income, net of taxes:
Retirement benefit plans:
Adjustment for amortization of prior service credit and net losses recognized during the period in net periodic benefit cost, net of taxes4,376 670 603 — (1,273)4,376 
Reclassification adjustment for impact of D&Os of the PUC included in regulatory assets, net of taxes(4,325)(670)(603)— 1,273 (4,325)
Other comprehensive income, net of taxes51 — — — — 51 
Comprehensive income attributable to common shareholder$46,460 7,377 6,284 — (13,661)$46,460 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Balance Sheet
March 31, 2023
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsi-
diaries
Consoli-
dating
adjustments
Hawaiian Electric
Consolidated
Assets      
Property, plant and equipment
Utility property, plant and equipment      
Land$42,860 5,606 3,594 — — $52,060 
Plant and equipment5,302,293 1,431,852 1,308,747 — — 8,042,892 
Right-of-use assets - finance lease88,297 — — — — 88,297 
Less accumulated depreciation(1,889,007)(651,463)(593,341)— — (3,133,811)
Construction in progress248,788 28,136 38,938 — — 315,862 
Utility property, plant and equipment, net3,793,231 814,131 757,938 — — 5,365,300 
Nonutility property, plant and equipment, less accumulated depreciation
5,298 115 1,532 — — 6,945 
Total property, plant and equipment, net3,798,529 814,246 759,470 — — 5,372,245 
Investment in wholly owned subsidiaries, at equity705,212 — — — (705,212)— 
Current assets      
Cash and cash equivalents49,393 28,006 38,546 77 — 116,022 
Customer accounts receivable, net172,426 34,224 28,655 — — 235,305 
Accrued unbilled revenues, net118,035 21,831 20,666 — — 160,532 
Other accounts receivable, net22,376 3,883 4,677 — (19,509)11,427 
Fuel oil stock, at average cost116,295 16,678 24,610 — — 157,583 
Materials and supplies, at average cost50,744 10,578 22,771 — — 84,093 
Prepayments and other33,369 5,025 5,515 — — 43,909 
Regulatory assets58,943 2,575 3,455 — — 64,973 
Total current assets621,581 122,800 148,895 77 (19,509)873,844 
Other long-term assets      
Operating lease right-of-use assets40,724 32,599 11,607 — — 84,930 
Regulatory assets151,684 19,041 12,204 — — 182,929 
Other113,888 32,786 30,402 — (16,561)160,515 
Total other long-term assets306,296 84,426 54,213 — (16,561)428,374 
Total assets$5,431,618 1,021,472 962,578 77 (741,282)$6,674,463 
Capitalization and liabilities      
Capitalization      
Common stock equity$2,358,884 346,629 358,506 77 (705,212)$2,358,884 
Cumulative preferred stock—not subject to mandatory redemption
22,293 7,000 5,000 — — 34,293 
Long-term debt, net1,226,587 249,346 258,414 — — 1,734,347 
Total capitalization3,607,764 602,975 621,920 77 (705,212)4,127,524 
Current liabilities      
Current portion of operating lease liabilities8,955 6,780 2,679 — — 18,414 
Current portion of long-term debt49,987 19,994 29,992 — — 99,973 
Accounts payable146,125 20,957 24,687 — — 191,769 
Interest and preferred dividends payable20,788 3,839 4,740 — — 29,367 
Taxes accrued, including revenue taxes178,418 34,570 33,926 — — 246,914 
Regulatory liabilities9,505 7,918 7,811 — — 25,234 
Other61,360 21,072 23,657 — (19,509)86,580 
Total current liabilities475,138 115,130 127,492 — (19,509)698,251 
Deferred credits and other liabilities      
Operating lease liabilities39,387 26,087 9,159 — — 74,633 
Finance lease liabilities84,341 — — — — 84,341 
Deferred income taxes271,588 50,657 62,708 — — 384,953 
Regulatory liabilities745,894 195,238 103,185 — — 1,044,317 
Unamortized tax credits68,123 12,903 12,419 — — 93,445 
Defined benefit pension and other postretirement benefit plans liability
65,917 — — — (16,529)49,388 
Other73,466 18,482 25,695 — (32)117,611 
Total deferred credits and other liabilities1,348,716 303,367 213,166 — (16,561)1,848,688 
Total capitalization and liabilities$5,431,618 1,021,472 962,578 77 (741,282)$6,674,463 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Balance Sheet
December 31, 2022
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsi-diaries
Consoli-
dating
adjustments
Hawaiian Electric
Consolidated
Assets      
Property, plant and equipment
Utility property, plant and equipment      
Land$42,860 5,606 3,594 — — $52,060 
Plant and equipment5,260,685 1,425,442 1,293,383 — — 7,979,510 
Finance lease right-of-use assets48,371 — — — — 48,371 
Less accumulated depreciation(1,855,150)(644,457)(586,892)— — (3,086,499)
Construction in progress215,560 23,989 35,804 — — 275,353 
Utility property, plant and equipment, net3,712,326 810,580 745,889 — — 5,268,795 
Nonutility property, plant and equipment, less accumulated depreciation
5,298 115 1,532 — — 6,945 
Total property, plant and equipment, net3,717,624 810,695 747,421 — — 5,275,740 
Investment in wholly owned subsidiaries, at equity
701,833 — — — (701,833)— 
Current assets      
Cash and cash equivalents27,579 5,092 6,494 77 — 39,242 
Advances to affiliates— 4,500 21,700 — (26,200)— 
Customer accounts receivable, net216,802 39,339 32,197 — — 288,338 
Accrued unbilled revenues, net136,508 23,839 22,933 — — 183,280 
Other accounts receivable, net23,746 5,519 6,686 — (22,384)13,567 
Fuel oil stock, at average cost153,342 16,964 21,224 — — 191,530 
Materials and supplies, at average cost48,130 9,783 21,655 — — 79,568 
Prepayments and other24,040 6,346 4,137 — (1,041)33,482 
Regulatory assets46,504 2,435 3,334 — — 52,273 
Total current assets676,651 113,817 140,360 77 (49,625)881,280 
Other long-term assets      
Operating lease right-of-use assets42,752 34,283 12,283 — — 89,318 
Regulatory assets154,040 21,816 14,384 — — 190,240 
Other115,028 32,654 29,495 — (16,288)160,889 
Total other long-term assets311,820 88,753 56,162 — (16,288)440,447 
Total assets$5,407,928 1,013,265 943,943 77 (767,746)$6,597,467 
Capitalization and liabilities      
Capitalization
Common stock equity$2,344,170 344,720 357,036 77 (701,833)$2,344,170 
Cumulative preferred stock—not subject to mandatory redemption
22,293 7,000 5,000 — — 34,293 
Long-term debt, net1,126,915 224,439 233,500 — — 1,584,854 
Total capitalization3,493,378 576,159 595,536 77 (701,833)3,963,317 
Current liabilities     
Current portion of operating lease liabilities9,775 6,690 2,630 — — 19,095 
Current portion of long-term debt49,981 19,992 29,989 — — 99,962 
Short-term borrowings-affiliate26,200 — — — (26,200)— 
Accounts payable143,253 32,113 27,126 — — 202,492 
Interest and preferred dividends payable12,398 2,576 2,282 — (80)17,176 
Taxes accrued, including revenue taxes207,798 42,436 40,709 — (1,041)289,902 
Regulatory liabilities13,145 8,553 9,777 — — 31,475 
Other64,659 20,856 22,385 — (22,304)85,596 
Total current liabilities615,176 133,216 134,898 — (49,625)833,665 
Deferred credits and other liabilities     
Operating lease liabilities41,049 27,817 9,849 — — 78,715 
Finance lease liabilities46,048 — — — — 46,048 
Deferred income taxes271,234 50,615 62,581 — — 384,430 
Regulatory liabilities729,683 194,222 100,270 — — 1,024,175 
Unamortized tax credits69,614 13,150 12,536 — — 95,300 
Defined benefit pension and other postretirement benefit plans liability
65,907 129 — — (16,288)49,748 
Other75,839 17,957 28,273 — 122,069 
Total deferred credits and other liabilities1,299,374 303,890 213,509 — (16,288)1,800,485 
Total capitalization and liabilities$5,407,928 1,013,265 943,943 77 (767,746)$6,597,467 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Changes in Common Stock Equity
Three months ended March 31, 2023
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsidiaries
Consolidating
adjustments
Hawaiian Electric
Consolidated
Balance, December 31, 2022$2,344,170 344,720 357,036 77 (701,833)$2,344,170 
Net income for common stock47,009 6,390 5,151 — (11,541)47,009 
Other comprehensive loss, net of taxes(45)(6)(6)— 12 (45)
Common stock dividends(32,250)(4,475)(3,675)— 8,150 (32,250)
Balance, March 31, 2023$2,358,884 346,629 358,506 77 (705,212)$2,358,884 
 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Changes in Common Stock Equity
Three months ended March 31, 2022
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsidiaries
Consolidating
adjustments
Hawaiian Electric
Consolidated
Balance, December 31, 2021$2,261,899 332,900 343,260 77 (676,237)$2,261,899 
Net income for common stock46,409 7,377 6,284 — (13,661)46,409 
Other comprehensive income, net of taxes51 — — — — 51 
Common stock dividends(31,475)(4,100)(3,800)— 7,900 (31,475)
Balance, March 31, 2022$2,276,884 336,177 345,744 77 (681,998)$2,276,884 
Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Cash Flows
Three months ended March 31, 2023
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsidiaries
Consolidating
adjustments
Hawaiian Electric
Consolidated
Net cash provided by operating activities$143,356 18,733 15,416 — (8,150)$169,355 
Cash flows from investing activities      
Capital expenditures(74,916)(20,747)(26,476)— — (122,139)
Advances to affiliates— 4,500 21,700 — (26,200)— 
Other1,094 153 298 — — 1,545 
Net cash used in investing activities(73,822)(16,094)(4,478)— (26,200)(120,594)
Cash flows from financing activities      
Common stock dividends(32,250)(4,475)(3,675)— 8,150 (32,250)
Preferred stock dividends of Hawaiian Electric and subsidiaries(270)(134)(95)— — (499)
Proceeds from issuance of long-term debt100,000 25,000 25,000 — — 150,000 
Net decrease in short-term borrowings from non-affiliates and affiliate with original maturities of three months or less(114,167)— — — 26,200 (87,967)
Payments of obligations under finance leases(575)— — — — (575)
Other(458)(116)(116)— — (690)
Net cash provided by (used in) financing activities(47,720)20,275 21,114 — 34,350 28,019 
Net increase in cash and cash equivalents21,814 22,914 32,052 — — 76,780 
Cash and cash equivalents, beginning of period27,579 5,092 6,494 77 — 39,242 
Cash and cash equivalents, end of period$49,393 28,006 38,546 77 — $116,022 


Hawaiian Electric Company, Inc. and Subsidiaries
Condensed Consolidating Statement of Cash Flows
Three months ended March 31, 2022
(in thousands)Hawaiian ElectricHawaii Electric LightMaui ElectricOther
subsidiaries
Consolidating
adjustments
Hawaiian Electric
Consolidated
Net cash provided by operating activities$55,669 15,778 13,228 — (7,900)$76,775 
Cash flows from investing activities     
Capital expenditures (44,084)(15,133)(17,141)— — (76,358)
Advances to affiliates(4,000)— (12,800)— 16,800 — 
Other961 280 253 — — 1,494 
Net cash used in investing activities(47,123)(14,853)(29,688)— 16,800 (74,864)
Cash flows from financing activities     
Common stock dividends(31,475)(4,100)(3,800)— 7,900 (31,475)
Preferred stock dividends of Hawaiian Electric and subsidiaries(270)(134)(95)— — (499)
Net increase in short-term borrowings from non-affiliates and affiliate with original maturities of three months or less18,800 4,000 — — (16,800)6,000 
Net cash used in financing activities(12,945)(234)(3,895)— (8,900)(25,974)
Net increase (decrease) in cash and cash equivalents(4,399)691 (20,355)— — (24,063)
Cash, cash equivalents and restricted cash, beginning of period26,433 5,326 23,422 77 — 55,258 
Cash, cash equivalents and restricted cash, end of period22,034 6,017 3,067 77 — 31,195 
Less: Restricted cash(2,140)— — — — (2,140)
Cash and cash equivalents, end of period$19,894 6,017 3,067 77 — $29,055