In October of 2011, the Company was named a defendant in a personal injury suit (Paul Gendrolis and Katherine Gendrolis v. Saxon Fleet Sales, Kolstad Company, and Supreme Industries, Inc.) which was filed in the United States District Court, District of Massachusetts.  The complaint seeks $10 million in damages based on allegations that a truck body manufactured by the Company contained an improperly installed plate or lip, which caused Paul Gendrolis to trip and become injured.  Claims alleged against the Company include negligence, breach of warranty, breach of consumer protection laws, and loss of consortium.  Due to the inherent risk of litigation, the outcome of this case is uncertain and unpredictable.  The Company is vigorously defending this matter.  The Company has insurance coverage for personal injury claims with the Company’s self-insurance deductible being $250,000.

 

In February of 2012, the Company was named a defendant in a claim that a fleet of buses manufactured by the Company was defective (King County v. Supreme Corporation) which was filed in Superior Court in King County, Washington.  King County sought to revoke its acceptance of a fleet of thirty-five buses which had been manufactured by the Company and sold to King County, and alleged breach of contract and breach of implied warranties.  As of February 28, 2013, King County claimed its damages were $10.6 million and subsequently moved to add a consumer protection act claim which would have permitted an award of attorney’s fees, if successful.

 

On June 14, 2013, the Company and King County entered into a Settlement and Release Agreement under the terms of which the lawsuit would be dismissed and mutual releases granted in exchange for payment of the sum of $4.7 million to King County within ninety days of the date of the agreement and the return of thirty-five buses to the Company.  Through separate agreements, the Company settled third-party claims against certain third-party subcontractors who have contributed to the Company $520,000 of the settlement funds, with the Company responsible for the balance which is intended to be paid by utilization of the Company’s Credit Agreement.  The legal settlement liability is included in other accrued liabilities at June 29, 2013.  The Company assigned an estimated $1.1 million to the returned product. Including the legal settlement and related costs, the Company recorded a pre-tax charge of $3.4 million in the quarter and $3.6 million for the first six months.