New Facility
9 Months Ended
Mar. 31, 2018
Leases [Abstract]  
New Facility
Lease Agreement and Purchase Option Exercise
On June 15, 2016, the Company exercised the purchase option to purchase the land and the partially constructed New Facility located thereon pursuant to the terms of the lease agreement dated as of July 17, 2015, as amended (the “Lease Agreement”). On September 15, 2016 (“Purchase Option Closing Date”), the Company closed the purchase option and acquired the land and the partially constructed New Facility located thereon for an aggregate purchase price of $42.5 million (the “Purchase Price”), consisting of the purchase option price of $42.0 million based on actual construction costs incurred as of the Purchase Option Closing Date plus the option exercise fee, plus amounts paid in respect of real estate commissions, title insurance, and recording fees. Upon closing of the purchase option, the Company recorded the aggregate purchase price of the New Facility in “Property, plant and equipment, net” on its consolidated balance sheet. The asset related to the New Facility lease obligation included in “Property, plant and equipment, net,” the offsetting liability for the lease obligation included in “Other long-term liabilities” and the rent expense related to the land were reversed. Concurrent with the purchase option closing, on September 15, 2016, the Company terminated the Lease Agreement. The Company did not pay any early termination penalties in connection with the termination of the Lease Agreement.
Development Management Agreement
In conjunction with the Lease Agreement, the Company also entered into a Development Management Agreement with an affiliate of Stream Realty Partners (the “DMA”) to manage, coordinate, represent, assist and advise the Company on matters from the pre-development through construction of the New Facility. Services under the DMA have concluded. The Company incurred and paid $4.0 million under this agreement which is included in “Buildings and Facilities” (see Note 12).
Amended Building Contract
On September 17, 2016, the Company and The Haskell Company (“Builder”) entered into a Change Order, which, among other things, amended the building contract previously entered into between the Company and Builder to provide a guaranteed maximum price and the basis for the price and the scope of Builder’s services in connection with the construction of the New Facility (the “Amended Building Contract”).
Pursuant to the Amended Building Contract, Builder provided pre-construction and construction services, including specialized industrial design and construction work in connection with Builder’s construction of certain production equipment installed in portions of the New Facility (the “Project”). In April 2017, the Company and Builder entered into a change order to change the scope of work which added $0.6 million to the Amended Building Contract. Builder's work on the Project has been completed. The Company incurred and paid $22.5 million for Builder’s services in connection with the Project which amount is included in “Machinery and equipment” (see Note 12).
New Facility Costs
The Company estimated that the total construction costs including the cost of land for the New Facility would be approximately $60 million. As of March 31, 2018, the Company has incurred an aggregate of $60.8 million in construction costs. In addition to the costs to complete the construction of the New Facility, the Company estimated that it would incur approximately $35 million to $39 million for machinery and equipment, furniture and fixtures and related expenditures in connection with construction of the New Facility of which the Company has incurred an aggregate of $33.2 million as of March 31, 2018, including $22.5 million under the Amended Building Contract. The majority of the capital expenditures associated with machinery and equipment, furniture and fixtures, and related expenditures in connection with the initial construction of the New Facility were incurred in the first three quarters of fiscal 2017. The Company commenced distribution activities at the New Facility during the second quarter of fiscal 2017 and initial production activities late in the third quarter of fiscal 2017. The Company began roasting coffee in the New Facility in the fourth quarter of fiscal 2017.
New Facility Expansion
On February 9, 2018, the Company and Haskell entered into Task Order No. 6 pursuant to the Standard Form of Agreement between Owner and Design-Builder (AIA Document A141-2014 Edition) dated October 23, 2017. The Standard Form of Agreement serves as a master service agreement (“MSA”) between the Company and Haskell and does not contain any actual work scope or compensation amounts, but instead contemplates a number of project specific task orders (the “Task Orders”) to be executed between the parties, which will define the scope and price for particular projects to be performed under the pre-negotiated terms and conditions contained in the MSA.  The MSA expires on December 31, 2021 (provided that any Task Order that is not finally complete at such time will remain in effect until completion).
Task Order 6 covers the expansion of the Company’s production lines (the “Expansion Project”) in the New Facility including expanding capacity to support the transition of Boyd Business volumes to the New Facility. Task Order 6 includes (i) pre-construction services to define the Company’s criteria for the industrial capacity Expansion Project, (ii) specialized industrial design services for the Expansion Project, (iii) specialty industrial equipment procurement and installation, and (iv) all construction services necessary to complete any modifications to the New Facility in order to accommodate the production line expansion, and to provide power to that expanded production capability. While the Company and Haskell have previously executed Task Orders 1-5, Task Order 6 includes the work and services to be performed under Task Orders 1-5 and, accordingly, Task Orders 1-5 have been superseded and voided by Task Order 6.
Task Order 6 is a guaranteed maximum price contract. Specifically, the maximum price payable by the Company to Haskell under Task Order 6 for all of Haskell’s services, equipment procurement and installation, and construction work in connection with the Expansion Project is $19.3 million. In fiscal 2018, the Company anticipates paying between $9 million to $14 million in capital expenditures associated with the Expansion Project, of which $2.9 million and $5.6 million has been paid in the three and nine months ended March 31, 2018, respectively, with the balance of up to the guaranteed maximum price of $19.3 million expected to be paid in fiscal 2019.