New Facility
3 Months Ended
Sep. 30, 2017
Leases [Abstract]  
New Facility
New Facility
Lease Agreement and Purchase Option Exercise
On June 15, 2016, the Company exercised the purchase option to purchase the land and the partially constructed New Facility located thereon pursuant to the terms of the lease agreement dated as of July 17, 2015, as amended (the “Lease Agreement”). On September 15, 2016 (“Purchase Option Closing Date”), the Company closed the purchase option and acquired the land and the partially constructed New Facility located thereon for an aggregate purchase price of $42.5 million (the “Purchase Price”), consisting of the purchase option price of $42.0 million based on actual construction costs incurred as of the Purchase Option Closing Date plus the option exercise fee, plus amounts paid in respect of real estate commissions, title insurance, and recording fees. Upon closing of the purchase option, the Company recorded the aggregate purchase price of the New Facility in “Property, plant and equipment, net” on its consolidated balance sheet. The asset related to the New Facility lease obligation included in “Property, plant and equipment, net,” the offsetting liability for the lease obligation included in “Other long-term liabilities” and the rent expense related to the land were reversed. Concurrent with the purchase option closing, on September 15, 2016, the Company terminated the Lease Agreement. The Company did not pay any early termination penalties in connection with the termination of the Lease Agreement.
Development Management Agreement
In conjunction with the Lease Agreement, the Company also entered into a Development Management Agreement with an affiliate of Stream Realty Partners (the “DMA”) to manage, coordinate, represent, assist and advise the Company on matters from the pre-development through construction of the New Facility. Services under the DMA have concluded. The Company incurred $4.0 million under this agreement which amount is included in “Building and Facilities” (see Note 12), of which $0.4 million remains to be paid which is included in accounts payable on the Company's condensed consolidated balance sheet at September 30, 2017.
Amended Building Contract
On September 17, 2016, the Company and The Haskell Company (“Builder”) entered into a Change Order, which, among other things, amended the building contract previously entered into between the Company and Builder to provide a guaranteed maximum price and the basis for the price and the scope of Builder’s services in connection with the construction of the New Facility (the “Amended Building Contract”).
Pursuant to the Amended Building Contract, Builder provided pre-construction and construction services, including specialized industrial design and construction work in connection with Builder’s construction of certain production equipment installed in portions of the New Facility (the “Project”). The Company engaged other designers and builders to provide traditional construction work on the Project site, including for the foundation, building envelope and roof of the New Facility. In April 2017, the Company and Builder entered into a change order to change the scope of work which added $0.6 million to the Amended Building Contract. Builder's work on the Project has been completed. The Company incurred $22.5 million for Builder’s services in connection with the Project which amount is included in “Building and Facilities” (see Note 12), of which $0.5 million remains to be paid which is included in accounts payable on the Company condensed consolidated balance sheet at September 30, 2017.
New Facility Costs
The Company estimated that the total construction costs including the cost of land for the New Facility would be approximately $60 million. As of September 30, 2017, the Company has incurred an aggregate of $60.8 million in construction costs and has outstanding contractual obligations of $0.7 million. In addition to the costs to complete the construction of the New Facility, the Company estimated that it would incur approximately $35 million to $39 million for machinery and equipment, furniture and fixtures and related expenditures of which the Company has incurred an aggregate of $33.2 million as of September 30, 2017, including $22.5 million under the Amended Building Contract, and has outstanding contractual obligations of $0.5 million as of September 30, 2017. The majority of the capital expenditures associated with machinery and equipment, furniture and fixtures, and related expenditures for the New Facility were incurred in the first three quarters of fiscal 2017. The Company commenced distribution activities at the New Facility during the second quarter of fiscal 2017 and initial production activities late in the third quarter of fiscal 2017. The Company began roasting coffee in the New Facility in the fourth quarter of fiscal 2017.