New Facility (Notes)
3 Months Ended
Sep. 30, 2016
Leases [Abstract]  
New Facility
New Facility
Lease Agreement and Purchase Option Exercise
On June 15, 2016, the Company exercised the purchase option to purchase the land and the partially constructed New Facility located thereon pursuant to the terms of the lease agreement dated as of July 17, 2015, as amended (the "Lease Agreement"). On September 15, 2016 ("Purchase Option Closing Date"), the Company closed the purchase option and acquired the land and the partially constructed New Facility located thereon for an aggregate purchase price of $42.5 million (the “Purchase Price”), consisting of the purchase option price of $42.0 million based on actual construction costs incurred as of the Purchase Option Closing Date plus the option exercise fee, plus amounts paid in respect of real estate commissions, title insurance, and recording fees. Upon closing of the purchase option, the Company recorded the aggregate purchase price of the New Facility in "Property, plant and equipment, net" on its consolidated balance sheet. The asset related to the New Facility lease obligation included in "Property, plant and equipment, net," the offsetting liability for the lease obligation included in "Other long-term liabilities" and the rent expense related to the land were reversed. Concurrent with the purchase option closing, on September 15, 2016, the Company terminated the Lease Agreement. The Company did not pay any early termination penalties in connection with the termination of the Lease Agreement.
Based on the final budget, the Company estimates that the total construction costs including the cost of land for the New Facility will be approximately $55 million to $60 million, of which the Company has spent $42.5 million as of September 30, 2016. Construction of and relocation to the New Facility are expected to be completed in the third quarter of fiscal 2017.
Development Management Agreement
In conjunction with the Lease Agreement, the Company also entered into a Development Management Agreement with an affiliate of Stream Realty Partners (the ‘DMA”) to manage, coordinate, represent, assist and advise the Company on matters from the pre-development through construction of the New Facility. Pursuant to the DMA, the Company will pay the developer a development fee, an oversight fee and development services fee which are included in the construction costs incurred-to-date. An incentive fee, the amount of which will be determined by the developer and the Company, will also be payable if final completion occurs prior to the scheduled completion date.
New Facility Construction Contract
On September 17, 2016, the Company and The Haskell Company (“Builder”) entered into a Change Order, which, among other things, amended the building contract previously entered into between the Company and Builder to provide a guaranteed maximum price and the basis for the price and the scope of Builder’s services in connection with the construction of the New Facility (the "Amended Building Contract").
Pursuant to the Amended Building Contract, Builder will provide pre-construction and construction services, including specialized industrial design and construction work in connection with Builder’s construction of certain production equipment that will be installed in portions of the New Facility (the “Project”). The Company has engaged other designers and builders to provide traditional construction work on the Project site, including for the foundation, building envelope and roof of the New Facility.
Pursuant to the Amended Building Contract, the Company will pay Builder up to $21.4 million for Builder’s services in connection with the Project. This amount is a guaranteed maximum price and is subject to adjustment in accordance with the terms of the Amended Building Contract. The Company has paid $7.0 million towards these services as of September 30, 2016 (see Note 18), The date for substantial completion of Builder’s work on the Project is February 9, 2017, which is also subject to adjustment in accordance with the terms of the Amended Building Contract. The Amended Building Contract includes an “IDB Work Contract Schedule,” which sets forth interim milestones, durations and material dates in relation to the performance and timing of Builder’s work. The Amended Building Contract includes remedies for the Company in the event agreed milestone dates relating to Builder’s services are not met. The Amended Building Contract is subject to customary undertakings, covenants, obligations, rights and conditions.
Machinery and Equipment, Furniture and Fixtures
In addition to the costs to complete the construction of the New Facility, the Company estimates that it will incur $35 million to $39 million for machinery and equipment, furniture and fixtures and related expenditures. As of September 30, 2016 and June 30, 2016, the Company had spent $12.7 million and $5.9 million, respectively, toward the purchase of machinery and equipment, furniture and fixtures and related expenditures for the New Facility. The majority of the capital expenditures associated with machinery and equipment, furniture and fixtures, and related expenditures for the New Facility are expected to be incurred in the first three quarters of fiscal 2017.