Facility Lease Obligation
6 Months Ended
Dec. 31, 2015
Leases [Abstract]  
Facility Lease Obligation
Facility Lease Obligation
On July 17, 2015, the Company entered into the Lease Agreement pursuant to which the Company will lease a 538,000 square foot facility to be constructed on 28.2 acres of land located in Northlake, Texas, which will include corporate offices, areas dedicated to manufacturing and distribution, as well as a lab. Principal design work for the facility is expected to be finalized by the end of February 2016. The construction of the new facility is estimated to be completed by the end of the second quarter of fiscal 2017.
The new facility will be constructed by Lessor, at its expense, in accordance with agreed upon specifications and plans determined as set forth in the Lease Agreement. Due to the Company's involvement in the construction of the facility, as the deemed general contractor, pursuant to ASC 840, the Company is required to capitalize during the construction period the cash and non-cash assets, with the exception of the land which is not capitalized, contributed by Lessor for the construction as property, plant and equipment on the Company’s consolidated balance sheets, with an offsetting liability for the same amount payable to Lessor.
The Company recorded an asset related to the facility lease obligation included in property, plant and equipment of $8.1 million as of December 31, 2015. The facility lease obligation included in "Other long-term liabilities" on the Company’s consolidated balance sheet was $8.1 million as of December 31, 2015 (see Note 12). There were no such amounts recorded at June 30, 2015. As of December 31, 2015 and June 30, 2015, respectively, the Company had recorded $0 and $0.3 million in “Other receivables” representing costs incurred by the Company associated with the new facility (see Note 8).
A portion of the lease arrangement is allocated to land for which the Company will record rent expense during the construction period. The expense associated with the land is determined using the fair value of the leased land at construction commencement and the Company’s incremental borrowing rate, and is recognized on a straight-line basis. Once rent payments commence under the Lease Agreement, all amounts in excess of land rent expense will be recorded as a debt-service payment and recognized as interest expense and a reduction of the financing obligation. Rent expense for the facility lease obligation included in the Company’s consolidated statements of operations in the three and six months ended December 31, 2015 was $74,000 and $0.1 million, respectively. There was no comparable rent expense in the three and six months ended December 31, 2014.
The Lease Agreement contains a purchase option exercisable at any time by the Company on or before ninety days prior to the scheduled completion date with an option purchase price equal to 103% of the total project cost as of the date of the option closing if the option closing occurs on or before July 17, 2016. The option purchase price will increase by 0.35% per month thereafter up to and including the date which is the earlier of (A) ninety days after the scheduled completion date and (B) December 31, 2016. Based upon the preliminary budget delivered at the time the Lease Agreement was executed, the Company had estimated that if it were to exercise the purchase option under the Lease Agreement on or before July 17, 2016, the estimated option purchase price in lieu of the lease payments would be $51.1 million payable in the year ending June 30, 2017. This estimate was based upon the preliminary budget and included amounts in respect of construction costs, acquisition of the land upon which the Northlake, Texas facility will be constructed, Lessor and Company fees and expenses (such as legal fees), and preliminary contingency amounts of approximately $5.1 million, in the aggregate. The actual option purchase price would be based upon the amounts set forth in the final budget. The Company is currently evaluating the optimal size, capacity, utilization, automation and build-out of the Texas facility, among other things, and expects to deliver the final budget to Lessor by the end of February 2016, which may exceed the estimated preliminary budget and result in an increase in the rent payments or the option exercise price under the Lease Agreement. The obligation to pay rent will commence on December 31, 2016, if the option remains unexercised. The decision of whether to exercise the option or not will depend upon, among other things, whether the Company can sell the Torrance facility at an acceptable price.
The initial term of the lease is for 15 years from the rent commencement date with six options to renew, each with a renewal term of 5 years. The annual base rent under the Lease Agreement will be an amount equal to:
the product of 7.50% and (a) the total estimated budget for the project, or (b) all construction costs outlined in the final budget on or prior to the scheduled completion date; or
the product of 7.50% and the total project costs, to the extent that all components of the document delivery and completion requirement are fully satisfied on or prior to the scheduled completion date.
Based on the preliminary budget, the Company had estimated that the annual base rent would be approximately $3.7 million which amount may be higher when the final budget is determined. The annual base rent will increase by 2% during each year of the lease term.
On July 17, 2015, the Company also entered into a Development Management Agreement (“DMA”) with Stream Realty Partners-DFW, L.P., a Texas limited partnership (“Developer”).
Pursuant to the DMA, the Company retained the services of Developer to manage, coordinate, represent, assist and advise the Company on matters concerning the pre-development, development, design, entitlement, infrastructure, site preparation and construction of the facility. The term of the DMA is from July 17, 2015 until final completion of the project. Pursuant to the DMA, the Company will pay Developer:
a development fee of 3.25% of all development costs;
an oversight fee of 2% of any amounts paid to the Company-contracted parties for any oversight by Developer of Company-contracted work;
an incentive fee, the amount of which will be determined by the parties, if final completion occurs prior to the scheduled completion date; and
an amount equal to $2.6 million as additional fee in respect of development services.