XML 46 R23.htm IDEA: XBRL DOCUMENT v3.20.4
Litigation And Other Contingencies
12 Months Ended
Dec. 31, 2020
Loss Contingency [Abstract]  
Litigation And Other Contingencies Litigation and Other Contingencies
Litigation. A variety of claims have been made against ExxonMobil and certain of its consolidated subsidiaries in a number of pending lawsuits. Management has regular litigation reviews, including updates from corporate and outside counsel, to assess the need for accounting recognition or disclosure of these contingencies. The Corporation accrues an undiscounted liability for those contingencies where the incurrence of a loss is probable and the amount can be reasonably estimated. If a range of amounts can be reasonably estimated and no amount within the range is a better estimate than any other amount, then the minimum of the range is accrued. The Corporation does not record liabilities when the likelihood that the liability has been incurred is probable but the amount cannot be reasonably estimated or when the liability is believed to be only reasonably possible or remote. For contingencies where an unfavorable outcome is reasonably possible and which are significant, the Corporation discloses the nature of the contingency and, where feasible, an estimate of the possible loss. For purposes of our contingency disclosures, “significant” includes material matters, as well as other matters, which management believes should be disclosed. ExxonMobil will continue to defend itself vigorously in these matters. Based on a consideration of all relevant facts and circumstances, the Corporation does not believe the ultimate outcome of any currently pending lawsuit against ExxonMobil will have a material adverse effect upon the Corporation’s operations, financial condition, or financial statements taken as a whole.
Other Contingencies. The Corporation and certain of its consolidated subsidiaries were contingently liable at December 31, 2020, for guarantees relating to notes, loans and performance under contracts. Where guarantees for environmental remediation and other similar matters do not include a stated cap, the amounts reflect management’s estimate of the maximum potential exposure.
 December 31, 2020
 
Equity Company Obligations (1)
Other Third-Party ObligationsTotal
 (millions of dollars)
Guarantees   
Debt-related986 124 1,110 
Other745 4,944 5,689 
Total1,731 5,068 6,799 
(1)ExxonMobil share.
 
Additionally, the Corporation and its affiliates have numerous long-term sales and purchase commitments in their various business activities, all of which are expected to be fulfilled with no adverse consequences material to the Corporation’s operations or financial condition.
In accordance with a Venezuelan nationalization decree issued in February 2007, a subsidiary of the Venezuelan National Oil Company (PdVSA) assumed the operatorship of the Cerro Negro Heavy Oil Project. The decree also required conversion of the Cerro Negro Project into a “mixed enterprise” and an increase in PdVSA’s or one of its affiliate’s ownership interest in the Project. ExxonMobil refused to accede to the terms proffered by the government, and on June 27, 2007, the government expropriated ExxonMobil’s 41.67 percent interest in the Cerro Negro Project.
ExxonMobil collected awards of $908 million in an arbitration against PdVSA under the rules of the International Chamber of Commerce in respect of an indemnity related to the Cerro Negro Project and $260 million in an arbitration for compensation due for the La Ceiba Project and for export curtailments at the Cerro Negro Project under rules of International Centre for Settlement of Investment Disputes (ICSID). An ICSID arbitration award relating to the Cerro Negro Project’s expropriation ($1.4 billion) was annulled based on a determination that a prior Tribunal failed to adequately explain why the cap on damages in the indemnity owed by PdVSA did not affect or limit the amount owed for the expropriation of the Cerro Negro Project. ExxonMobil filed a new claim seeking to restore the original award of damages for the Cerro Negro Project with ICSID on September 26, 2018.
The net impact of this matter on the Corporation’s consolidated financial results cannot be reasonably estimated. Regardless, the Corporation does not expect the resolution to have a material effect upon the Corporation’s operations or financial condition.
An affiliate of ExxonMobil is one of the Contractors under a Production Sharing Contract (PSC) with the Nigerian National Petroleum Corporation (NNPC) covering the Erha block located in the offshore waters of Nigeria. ExxonMobil's affiliate is the operator of the block and owns a 56.25 percent interest under the PSC. The Contractors are in dispute with NNPC regarding NNPC's lifting of crude oil in excess of its entitlement under the terms of the PSC. In accordance with the terms of the PSC, the Contractors initiated arbitration in Abuja, Nigeria, under the Nigerian Arbitration and Conciliation Act. On October 24, 2011, a three-member arbitral Tribunal issued an award upholding the Contractors' position in all material respects and awarding damages to the Contractors jointly in an amount of approximately $1.8 billion plus $234 million in accrued interest. The Contractors petitioned a Nigerian federal court for enforcement of the award, and NNPC petitioned the same court to have the award set aside. On May 22, 2012, the court set aside the award. The Contractors appealed that judgment to the Court of Appeal, Abuja Judicial Division. On July 22, 2016, the Court of Appeal upheld the decision of the lower court setting aside the award. On October 21, 2016, the Contractors appealed the decision to the Supreme Court of Nigeria. In June 2013, the Contractors filed a lawsuit against NNPC in the Nigerian federal high court in order to preserve their ability to seek enforcement of the PSC in the courts if necessary. Following dismissal by this court, the Contractors appealed to the Nigerian Court of Appeal in June 2016. In October 2014, the Contractors filed suit in the United States District Court for the Southern District of New York (SDNY) to enforce, if necessary, the arbitration award against NNPC assets residing within that jurisdiction. NNPC moved to dismiss the lawsuit. On September 4, 2019, the SDNY dismissed the Contractors’ petition to recognize and enforce the Erha arbitration award. The Contractors filed a notice of appeal in the Second Circuit on October 2, 2019. At this time, the net impact of this matter on the Corporation's consolidated financial results cannot be reasonably estimated. However, regardless of the outcome of enforcement proceedings, the Corporation does not expect the proceedings to have a material effect upon the Corporation's operations or financial condition.