XML 42 R30.htm IDEA: XBRL DOCUMENT v3.20.2
RESTRUCTURING AND ASSET IMPAIRMENTS (Tables)
9 Months Ended
Sep. 30, 2020
Restructuring and Related Activities [Abstract]  
Schedule of Restructuring and Impairment Charges Incurred
Total restructuring and impairment charges incurred for these programs are as follows and are reported in the “Restructuring expenses, net and asset impairments” line item in our Condensed Consolidated Statements of Operations:
Three months ended September 30, 2020
SeveranceContract Termination CostsOther Exit CostsTotal
DynaEnergetics$109 $$16 $133 
NobelClad— — 10 10 
Total$109 $$26 $143 

Three months ended September 30, 2019
SeveranceAsset ImpairmentContract Termination CostsEquipment Moving CostsOther Exit CostsTotal
DynaEnergetics$1,260 $4,620 $— $— $— $5,880 
NobelClad— (4)13 18 
Total$1,262 $4,620 $(4)$$13 $5,898 
Nine months ended September 30, 2020
SeveranceAsset ImpairmentContract Termination CostsEquipment Moving CostsOther Exit CostsTotal
DynaEnergetics$936 $1,181 $19 $126 $660 $2,922 
NobelClad244 — — — 20 264 
Corporate119 — — — — 119 
Total$1,299 $1,181 $19 $126 $680 $3,305 

Nine months ended September 30, 2019
SeveranceAsset Impairment / (Gain on Asset Disposal)Contract Termination CostsEquipment Moving CostsOther Exit CostsTotal
DynaEnergetics$1,260 $4,620 $— $— $— $5,880 
NobelClad714 (636)39 234 69 420 
Total$1,974 $3,984 $39 $234 $69 $6,300 
Schedule of Changes to the Restructuring Liability
During the nine months ended September 30, 2020, the changes to the restructuring liability associated with these programs is summarized below:
December 31, 2019Net expense (1)Payments and Other AdjustmentsCurrency AdjustmentsSeptember 30, 2020
Severance$2,404 $1,299 $(2,393)$(139)$1,171 
Contract termination costs— 19 (11)— 
Equipment moving costs— 126 (126)— — 
Other exit costs271 680 (1,129)178 — 
Total$2,675 $2,124 $(3,659)$39 $1,179 
(1) Excludes asset impairment expenses