Subsequent Event
12 Months Ended
Jun. 30, 2014
Subsequent Events [Abstract]  
Subsequent Event

Note. 18 Subsequent Event

As of June 30, 2014, the Company’s gross profit, reported in the statement of comprehensive income, includes a contract loss in the amount of $3.6 million, resulting from the cancellation of an engineering design contract effective after the balance sheet dated June 30, 2014. The events leading up to the cancellation qualifies the transaction as a Type 1 Subsequent Event. The Company was unsuccessful in delivering all required compliant prototypes required by the design contract by the agreed upon contract dates. Our customer would not allow any more time to complete these units as they were required to close out the prime contract by the U.S. Government.