Gas
site
Jun. 30, 2012
Gas
Jun. 30, 2012
Permits
Electric
Y
Jun. 30, 2012
Compliance Plan
Electric
Jun. 30, 2012
SO2 Emissions
Electric
T
Jun. 30, 2012
Clean Air Interstate Rule
Electric
allowancePerTon
MW
state
Jun. 30, 2012
NAAQS
Electric
ppb
Y
Jan. 06, 2010
NAAQS
Electric
Minimum
ppb
Jan. 06, 2010
NAAQS
Electric
Maximum
ppb
Jun. 30, 2012
Power Plant Mercury And Air Toxics Rule
Electric
phase
Jun. 30, 2012
Power Plant Mercury And Air Toxics Rule
Electric
Minimum
Jun. 30, 2012
Power Plant Mercury And Air Toxics Rule
Electric
Maximum
Jun. 30, 2012
Surface Impoundments
Electric
option
Jun. 30, 2012
Surface Impoundments
Iatan
Electric
Jun. 30, 2012
Surface Impoundments
Plum point
Electric
Jun. 30, 2012
Green House Gases
poundperMWh
Y
Jun. 30, 2012
Green House Gases
Minimum
Sep. 22, 2009
Green House Gases
Electric
T
Nov. 30, 2010
Renewable Energy
Electric
Jun. 30, 2012
Renewable Energy
Electric
mWh
certificate
Nov. 04, 2008
Renewable Energy
Electric
customer
Mar. 31, 2011
National Emission Standards for Hazardous Air Pollutants
Electric
Y
Environmental Laws And Regulations                                            
Number of years site operating permits are valid     5                                      
Expected cost of adding Carbon injection system                     $ 112 $ 130                    
Period for compliance (in years)                                           4
Amount of SO2 emission permitted under each SO2 allowance per affected unit (in tons)         1                                  
Minimum capacity of power plant called to reduce emission levels of SO2 and NOx (in megawatts)           25                                
Number of states in which fossil-fueled power plants are required to reduce emission levels of SO2 and NOx as per CAIR           28                                
Ratio of S02 allowances that must be utilized           2                                
Percentage of SO2 reduction from 2005 levels by 2014, required by the proposed CATR           73.00%                                
Number of allowances per ton of SO2 emissions           1                                
Percentage of NOx reduction from 2005 levels by 2014, required by the proposed CATR           54.00%                                
Proposed primary standard               60 70                          
Normal reconsideration period for ozone standards (in years)             5                              
2008 standard at which states will continue to identify and designate all non-attainment areas             75                              
Phase-in period for proposed standards (in years)                                           3
Number of phases expected to reduce nationwide mercury emissions                   2                        
Minimum emission threshold of CO2e from power generating and certain other facilities requires to report Greenhouse Gases (in metric tons)                                   25,000        
Limit of CO2 emissions                               1,000            
Minimum threshold percentage of emission for coal-fired power plant                                 50.00%          
Average period required for emission of CO2 (in years)                               30            
Percentage of ownership in a coal ash impoundment at a generating facility                           12.00% 7.52%              
Number of options in the EPA proposal                         2                  
Potential cost for construction of new landfill and conversion of existing ash handling from wet to dry system(s)                         15                  
Minimum percentage of energy purchased through long-term Purchased Power Agreements                                       15.00%    
Amount of renewable energy certificates generated each year                                       900,000    
Represents the megawatt-hour of renewable energy per renewable energy certificate (REC)                                       1    
Minimum percentage of Missouri retail sales required to generate or purchase electricity by 2011                                       2.00% 2.00%  
Minimum percentage of Missouri retail sales required to generate or purchase electricity by 2021                                       15.00% 15.00%  
Number of customers who have challenged exemption from solar requirement                                         2  
Percentage of Missouri retail sales required to generate or purchase solar energy                                       2.00% 2.00%  
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2011                                     10.00%      
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2016                                     15.00%      
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2020                                     20.00%      
Number of former manufactured plant sites with potential future remediation 2                                          
Remediation costs   0.2                                        
Initial construction costs       13.7                                    
Generating facility costs incurred through the period excluding AFUDC       $ 15.0