XML 31 R40.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies (Details 2) (USD $)
In Millions, unless otherwise specified
1 Months Ended 3 Months Ended 3 Months Ended 1 Months Ended 3 Months Ended 1 Months Ended
Jun. 30, 2006
Gas
site
Mar. 31, 2012
Gas
Mar. 31, 2012
Permits
Electric
Y
Mar. 31, 2012
SO2 Emissions
Electric
T
Mar. 31, 2012
Clean Air Interstate Rule
Electric
state
allowancePerTon
MW
Mar. 31, 2012
NAAQS
Electric
ppb
Y
Jan. 06, 2010
NAAQS
Electric
Minimum
ppb
Jan. 06, 2010
NAAQS
Electric
Maximum
ppb
Mar. 31, 2012
Power Plant Mercury And Air Toxics Rule
Electric
phase
Mar. 31, 2012
Power Plant Mercury And Air Toxics Rule
Electric
Minimum
Mar. 31, 2012
Power Plant Mercury And Air Toxics Rule
Electric
Maximum
Mar. 31, 2012
Surface Impoundments
Electric
option
Mar. 31, 2012
Surface Impoundments
Iatan
Electric
Mar. 31, 2012
Surface Impoundments
Plum point
Electric
Mar. 31, 2012
Green House Gases
poundperMWh
Y
Mar. 31, 2012
Green House Gases
Minimum
Sep. 22, 2009
Green House Gases
Electric
T
Nov. 30, 2010
Renewable Energy
Electric
Mar. 31, 2012
Renewable Energy
Electric
mWh
certificate
Nov. 04, 2008
Renewable Energy
Electric
customer
Mar. 31, 2011
National Emission Standards for Hazardous Air Pollutants
Electric
Y
Environmental Laws And Regulations                                          
Number of years site operating permits are valid     5                                    
Expected cost of adding Carbon injection system                   $ 112 $ 130                    
Period for compliance (in years)                                         4
Amount of SO2 emission permitted under each SO2 allowance per affected unit (in tons)       1                                  
Minimum capacity of power plant called to reduce emission levels of SO2 and NOx (in megawatts)         25                                
Number of states in which fossil-fueled power plants are required to reduce emission levels of SO2 and NOx as per CAIR         28                                
Ratio of S02 allowances that must be utilized numerator         2                                
Ratio of S02 allowances that must be utilized denominator         1                                
Percentage of SO2 reduction from 2005 levels by 2014, required by the proposed CATR         73.00%                                
Number of allowances per ton of SO2 emissions         1                                
Percentage of NOx reduction from 2005 levels by 2014, required by the proposed CATR         54.00%                                
Proposed primary standard             60 70                          
Normal reconsideration period for ozone standards (in years)           5                              
2008 standard at which states will continue to identify and designate all non-attainment areas           75                              
Phase-in period for proposed standards (in years)                                         3
Number of phases expected to reduce nationwide mercury emissions                 2                        
Minimum emission threshold of CO2e from power generating and certain other facilities requires to report Greenhouse Gases (in metric tons)                                 25,000        
Limit of CO2 emissions                             1,000            
Minimum threshold percentage of emission for coal-fired power plant                               50.00%          
Average period reqiure for emission of CO2 (in years)                             30            
Percentage of ownership in a coal ash impoundment at a generating facility                         12.00% 7.52%              
Number of options in the EPA proposal                       2                  
Potential cost for construction of new landfill and conversion of existing ash handling from wet to dry system(s)                       15                  
Minimum percentage of energy purchased through long-term Purchased Power Agreements                                     15.00%    
Amount of renewable energy certificates generated each year                                     900,000    
Represents the megawatt-hour of renewable energy per renewable energy certificate (REC)                                     1    
Minimum percentage of Missouri retail sales required to generate or purchase electricity by 2011                                     2.00% 2.00%  
Minimum percentage of Missouri retail sales required to generate or purchase electricity by 2021                                     15.00% 15.00%  
Number of customers who have challenged exemption from solar requirement                                       2  
Percentage of Missouri retail sales required to generate or purchase solar energy                                     2.00% 2.00%  
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2011                                   10.00%      
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2016                                   15.00%      
Percentage of Kansas retail customer peak capacity required to be sourced from renewable energy by 2020                                   20.00%      
Number of former manufactured plant sites with potential future remediation 2                                        
Remediation costs   $ 0.2