Regulatory Matters 
Regulatory Matters

Note 3— Regulatory Matters

 

Construction Accounting. The Missouri Public Service Commission (MPSC) approved a regulatory plan in 2005, allowing construction accounting. Construction accounting, for the purposes of this regulatory plan, was specific to Iatan 1 and Iatan 2 and allowed us to defer certain charges as regulatory assets. These deferred charges included depreciation, operations and maintenance and carrying costs related to operation of the facilities until the facilities were ultimately included in our rates. The regulatory plan also required us to continue to defer the fuel and purchased power expense impacts of Iatan 2, which were approximately $8.3 million as of September 30, 2011 and are recorded in Non-Current Regulatory Liabilities. Construction accounting began for Iatan 2 in August 2010 when it met its in-service criteria on August 26, 2010. In addition, in our 2009 Missouri rate case, construction accounting was approved for Plum Point, which met its in-service criteria on August 13, 2010. Construction accounting for Plum Point applied only to construction costs incurred subsequent to February 28, 2010. All of these deferrals began at the in-service dates and are to be amortized at the weighted average of the current depreciation rates for these plants once they were included in our rates, which for Iatan 2 and Plum Point was on June 15, 2011, the effective date of rates for our recently completed Missouri rate case. The amortization of the deferred Iatan 1 costs began in September 2010.

 

As part of a stipulated agreement in our 2009 Kansas rate case, approved by the KCC on June 25, 2010, we also defer depreciation and operating and maintenance expense on both Plum Point and Iatan 2 from their respective in-service dates until the effective date for rates from the next Kansas case, which was filed on June 17, 2011 as an abbreviated case. These deferrals will be recovered over a 3-5 year period as determined in the next case. (See Note 7 for additional details).

 

Rate base inclusion or amortizable lives for some of our regulatory assets and liabilities have been modified since December 31, 2010. As a result of our recently completed Missouri rate case, a tracking mechanism has been created to track the 2010 Southwest Power Administration (SWPA) payment and associated taxes (see Note 12). The Missouri jurisdictional portion of the payment will be amortized over ten years and reflected as a reduction to fuel expense. The Arkansas jurisdictional portion of the 2010 SWPA payment will be amortized on a straight-line basis over a 50 year period and reflected in the fuel adjustment clause. A tracking mechanism was also created related to the Plum Point, Iatan 2 and Iatan common plant operating expenses. The tracker is to exclude consumables and SO2 allowances which are recovered through the fuel adjustment clause. A regulatory asset or liability will be recorded for the difference between the Missouri jurisdictional portion of actual expenses and the annual recovery allowance with a corresponding charge or credit to regulated operating expense.

 

The following table sets forth the components of our regulatory assets and liabilities on our consolidated balance sheet (in thousands).

 

Regulatory Assets and Liabilities

 

 

 

September 30, 2011

 

December 31, 2010

 

Regulatory Assets:

 

 

 

 

 

Under recovered electric fuel and purchased power costs — current

 

$

8,770

 

$

4,974

 

Regulatory assets, current(1)

 

8,770

 

4,974

 

Pension and other postretirement benefits(2)

 

85,700

 

92,192

 

Income taxes

 

49,707

 

50,188

 

Unamortized loss on reacquired debt

 

11,982

 

13,099

 

Deferred operating and maintenance expenses

 

442

 

 

Unamortized loss on interest rate derivative

 

1,541

 

1,776

 

Asbury five-year maintenance

 

606

 

948

 

Storm costs(3)

 

5,440

 

7,733

 

Deferred construction accounting costs(4)

 

17,012

 

10,521

 

Asset retirement obligation

 

3,532

 

3,412

 

Under recovered electric fuel and purchased gas costs

 

1,069

 

 

Under recovered purchased gas costs — gas segment

 

1,159

 

439

 

Unsettled derivative losses — electric segment

 

4,505

 

3,166

 

Customer programs

 

3,205

 

2,119

 

System reliability — vegetation management

 

4,871

 

3,338

 

Other

 

713

 

473

 

Regulatory assets, long-term

 

191,484

 

189,404

 

Total

 

$

200,254

 

$

194,378

 

 

 

 

September 30, 2011

 

December 31, 2010

 

Regulatory Liabilities:

 

 

 

 

 

Over recovered purchased gas costs — gas segment - current

 

$

120

 

$

1,243

 

Regulatory liabilities, current(1)

 

120

 

1,243

 

Cost of removal

 

70,932

 

62,756

 

SWPA payment for Ozark Beach lost generation

 

25,689

 

 

Income taxes

 

12,344

 

12,715

 

Unamortized gain on interest rate derivative

 

3,754

 

3,881

 

Pension and other postretirement benefits(5)

 

3,210

 

4,604

 

Deferred construction accounting costs — fuel

 

8,340

 

3,126

 

Over recovered electric fuel and purchased power costs

 

175

 

155

 

Other

 

 

342

 

Regulatory liabilities, long-term

 

124,444

 

87,579

 

Total

 

$

124,564

 

$

88,822

 

 

 

(1)  Reflects under or over recovered costs expected to be recovered within the next 12 months in Missouri rates.

(2)  Primarily reflects regulatory assets resulting from the unfunded portion of our pension and OPEB liabilities and regulatory accounting for EDG acquisition costs. Approximately $0.4 million in pension and other postretirement benefit costs have been recognized since January 1, 2011 to reflect the amortization of the regulatory assets that were recorded at the time of the EDG acquisition of the Aquila, Inc. gas properties.

(3)  Primarily reflects ice storm costs incurred in 2007.

 

(4)

Balances as of September 30, 2011

 

Deferred Carrying Charges

 

Deferred O&M

 

Depreciation

 

Total

 

 

Iatan 1

 

$

2,738

 

1,368

 

1,657

 

$

5,763

 

 

Iatan 2

 

$

3,908

 

4,244

 

2,689

 

$

10,841

 

 

Plum Point

 

$

65

 

207

 

136

 

$

408

 

 

Total

 

 

 

 

 

 

 

$

17,012

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Balances as of December 31, 2010

 

Deferred Carrying Charges

 

Deferred O&M

 

Depreciation

 

Total

 

 

Iatan 1

 

$

2,779

 

1,388

 

1,682

 

$

5,849

 

 

Iatan 2

 

$

1,770

 

1,643

 

1,111

 

$

4,524

 

 

Plum Point

 

$

33

 

70

 

45

 

$

148

 

 

Total

 

 

 

 

 

 

 

$

10,521

 

 

(5) Includes the effect of costs incurred that are more or less than those allowed in rates for the Missouri (EDE and EDG) and Kansas (EDE) portion of pension and other postretirement benefit costs. Since January 1, 2011, regulatory liabilities and corresponding expenses have been reduced by approximately $0.5 million as a result of ratemaking treatment.