Regulation Regulation
General
The rates and services of the Company are regulated by incorporated municipalities in Texas, the PUCT, the NMPRC and the FERC. Municipal orders, ordinances and other agreements regarding rates and services adopted by Texas municipalities are subject to review and approval by the PUCT. The FERC has jurisdiction over the Company's wholesale (sales for resale - full requirements customer) transactions, transmission service and compliance with federally-mandated reliability standards. The decisions of the PUCT, the NMPRC and the FERC are subject to judicial review.
On June 1, 2019, the Company entered into the Merger Agreement. Pursuant to the Merger Agreement, on and subject to the terms and conditions set forth therein, Merger Sub will merge with and into the Company, with the Company continuing as the surviving corporation in the Merger and becoming a wholly owned subsidiary of Parent. Parent and Merger Sub are affiliates of the IIF. Among other things, the Company, Parent and Merger Sub are required to obtain certain regulatory approvals of the Merger as discussed further in Part I, Item 1, Financial Statements, Note M of the Notes to Financial Statements.
On August 13, 2019, the Company, Parent and IIF US Holding 2 LP, an affiliate of IIF, as applicable, filed (i) the joint report and application for regulatory approvals with the PUCT requesting approval of the Merger pursuant to the Texas Public Utility Regulatory Act ("PURA"), which was assigned PUCT Docket No. 49849, (ii) the joint application for regulatory approvals with the NMPRC requesting approval of the Merger pursuant to the New Mexico Public Utility Act ("NMPUA") and NMPRC Rule 450, which was assigned NMPRC Case No. 19-00234-UT, (iii) the joint application requesting approval of the Merger with the FERC under Section 203 of the Federal Power Act, which was assigned FERC Docket No. EC19-120-000, and (iv) the joint application for regulatory approval for the indirect transfer of the Company’s Nuclear Regulatory Commission ("NRC") licenses to Parent from the NRC under the Atomic Energy Act of 1954, which was assigned Docket ID NRC-2019-0214. In addition, on August 13, 2019, the Company and Parent sought the authorization of the Federal Communications Commission ("FCC") to assign or transfer control of the Company’s FCC licenses under FCC File No. 008737430. On December 4, 2019, the Company and Parent received consent from the FCC to transfer the Company's FCC licenses.
On August 16, 2019, the Company and Parent filed the notification and report form with the Antitrust Division of the U.S. Department of Justice and the Federal Trade Commission ("FTC") under the Hart-Scott-Rodino Antitrust Improvements Act of 1976 (the "HSR Act"), as amended, and the rules and regulations promulgated thereunder, which was assigned Transaction Identification No. 2019 1858. On September 3, 2019, the Company and Parent received notice from the FTC granting early termination of the waiting period under the HSR Act.
On November 21, 2019, the Company and IIF reached an agreement in principle with the PUCT staff and most intervenors regarding the Merger. The PUCT issued an order delaying the hearing on the merits in order to assist in reaching a unanimous settlement. The parties continued discussions and provided an update on the status of settlement at the PUCT meeting on December 13, 2019. A non-unanimous settlement was filed with the PUCT on December 18, 2019, resolving substantially all issues in the application. The hearing at the PUCT on the non-unanimous issues was held on January 7, 2020, at the conclusion of which the PUCT requested the Company and IIF attend the PUCT's January 16, 2020 open meeting to answer any follow-up questions. On January 16, 2020, the PUCT approved the Merger and issued its final order on January 28, 2020.
On January 3, 2020, the Company and IIF filed an unopposed stipulation with the NMPRC regarding the Merger. A hearing at the NMPRC for the unopposed stipulation was held on January 16, 2020. On January 16, 2020, the Hearing Examiner of the NMPRC (the "Hearing Examiner") agreed with the consent of parties to waive briefing. On February 12, 2020, the Hearing Examiner issued an Amended Certification of the Stipulation in which it is recommended that the NMPRC approve the unopposed stipulation subject to the parties agreeing to the Hearing Examiner's modifications. A final order adopting the Certification of the Stipulation and approving the Merger was issued by the NMPRC on March 11, 2020.
On December 5, 2019, the FERC requested additional information regarding the parties to the Merger. On January 6, 2020, the Company and IIF filed a joint response to the FERC's inquiry. On January 17, 2020, the Company and IIF filed a second supplement to the application. The FERC established a January 27, 2020 deadline date for comments on the filings. Several motions to intervene were filed, along with a protest of the January 6, 2020 response. On February 6, 2020, the Company and IIF filed a reply to the January 27, 2020 protest. On March 30, 2020, the FERC issued an order authorizing the Merger, subject to the FERC’s approval of mitigation to address certain discrete competitive effects of the Merger that could arise. The FERC concluded that the Merger, as conditioned, satisfies governing federal standards and authorized the Merger as consistent with the public interest. The FERC required that the proposed mitigation be filed within 45 days of the issuance of the FERC Order. On April 15, 2020, the
Company and IIF filed proposed mitigation options with the FERC. The matter is pending final approval from the FERC.
The FERC’s final approval is the last regulatory approval needed to close the Merger. The Company anticipates that the closing of the Merger will occur in the second quarter of 2020, upon the FERC’s approval of the required mitigation and satisfaction or waiver of the other Merger Agreement closing conditions.
Texas Regulatory Matters
2017 Texas Retail Rate Case Filing. On February 13, 2017, the Company filed with the City of El Paso, other municipalities incorporated in the Company's Texas service territory, and the PUCT in Docket No. 46831, a request for an increase in non-fuel base revenues. On December 18, 2017, the PUCT issued a final order in Docket No. 46831 (the "2017 PUCT Final Order").
The 2017 PUCT Final Order required the Company to file a refund tariff if the federal statutory income tax rate, as it relates to the Company, was decreased before the Company files its next general rate case. Following the enactment of the federal legislation commonly referred to as the Tax Cuts and Jobs Act of 2017 (the "TCJA") on December 22, 2017, and in compliance with the 2017 PUCT Final Order, on March 1, 2018, the Company filed with the PUCT and each of its Texas municipalities a proposed refund tariff designed to reduce base charges for Texas customers equivalent to the expected annual decrease of $22.7 million in federal income tax expense resulting from the TCJA changes, and an additional refund of $4.3 million for the amortization of a regulatory liability related to the reduced tax expense for the months of January through March of 2018. This filing was assigned PUCT Docket No. 48124. On March 27, 2018, the PUCT approved the Company's proposed refund tariff on an interim basis, subject to refund or surcharge, for customer billing effective April 1, 2018. Each of the Company's municipalities also implemented the Company's proposed tax credits on an interim basis effective April 1, 2018. The refund is reflected in rates over a period of one year beginning April 1, 2018, and is required to be updated annually until new base rates are implemented pursuant to the Company's next Texas rate case filing. The PUCT issued an order on December 10, 2018, approving the proposed refund tariff. On February 22, 2019, the Company filed with the PUCT and each of its Texas municipalities an application to modify the tax refund tariff to remove the portion of the base rate credit associated with the $4.3 million of regulatory liability amortization, which expired March 31, 2019. The filing was assigned PUCT Docket No. 49251 and approved by final order on June 27, 2019. On February 20, 2020, the Company filed its required annual update of the refund factor with the PUCT and each of its Texas municipalities. In its application, the Company proposed that the existing refund factors remain in effect. The filing is currently pending as PUCT Docket No. 50575.
Texas Energy Efficiency Cost Recovery Factor ("EECRF"). On May 1, 2018, the Company filed its annual application with the PUCT, which was assigned PUCT Docket No. 48332, to establish its EECRF for 2019. In addition to projected energy efficiency costs for 2019 and a reconciliation of collections to actual costs for the prior year, the Company requested approval of a $1.0 million incentive bonus for the 2017 energy efficiency program results in accordance with PUCT rules. Instead of convening a live hearing on the merits of this case, the parties agreed to enter into the record the pre-filed testimony of the parties and certain other exhibits and then file briefs on the contested issues. The Administrative Law Judge ("ALJ") issued a proposal for final decision on November 15, 2018, including the Company's fully requested incentive bonus. On January 17, 2019, the PUCT issued a final order approving a modified bonus amount of $0.9 million.
On May 1, 2019, the Company filed its annual application with the PUCT, which was assigned PUCT Docket No. 49496, to establish its EECRF for 2020. In addition to projected energy efficiency costs for 2020 and a reconciliation of collections to actual costs for the prior year, the Company requested approval of a $0.8 million incentive bonus for the 2018 energy efficiency program results in accordance with PUCT rules. On July 1, 2019, the Company requested, and received approval for, a suspension of the procedural schedule in order to pursue settlement of the case. On July 12, 2019, the Company informed the ALJ in the case that all parties had agreed in principle on terms for settlement. On August 14, 2019, the Company filed an unopposed settlement agreement and proposed order which resolved all issues in the proceeding, including the requested incentive bonus. The case was remanded on August 16, 2019, to the PUCT for a final order approving the settlement agreement and the Company's EECRF rates. On November 14, 2019, the PUCT issued an order approving the filed settlement.
On May 1, 2020, the Company filed its annual application with the PUCT, which was assigned PUCT Docket No. 50806, to establish its EECRF for 2021. In addition to projected energy efficiency costs of $4.7 million for 2021 and a reconciliation of collections to actual costs for the prior year, the Company requested approval of a $1.2 million incentive bonus for the 2019 energy efficiency program results in accordance with PUCT rules.

Fuel and Purchased Power Costs. The Company's actual fuel costs, including purchased power energy costs, net of the cost of off-system sales and related shared margins, are recovered from customers through a fixed fuel factor. The PUCT has adopted a fuel cost recovery rule ("Texas Fuel Rule") that allows the Company to seek periodic adjustments to its fixed fuel factor. The Company can seek to revise its fixed fuel factor based upon the approved formula at least four months after its last revision except in the month of December. The Texas Fuel Rule requires the Company to request to refund fuel costs in any month when the over-recovery balance exceeds a threshold material amount and it expects fuel costs to continue to be materially over-recovered. The Texas Fuel Rule also permits the Company to seek to surcharge fuel under-recoveries in any month the balance exceeds a threshold material amount and it expects fuel cost recovery to continue to be materially under-recovered. Fuel over- and under-recoveries are considered material when they exceed 4% of the previous twelve months' fuel costs. All such fuel revenue and expense activities are subject to periodic final review by the PUCT in periodic fuel reconciliation proceedings.
On April 29, 2019, the Company filed a petition with the PUCT, which was assigned PUCT Docket No. 49482, requesting authority to implement, beginning on June 1, 2019, a four-month, interim fuel refund of $19.4 million in fuel cost over-recoveries, including interest, for the period from April 2016 through March 2019. On May 30, 2019, the Company's fuel refund credit was approved on an interim basis. The Company implemented the fuel refund in customer bills beginning June 1, 2019. On September 27, 2019, the PUCT issued a final order approving the fuel refund credits. The fuel refund was completed on September 30, 2019, with a total fuel refund of $20.1 million, including interest, returned to Texas customers.
On September 13, 2019, the Company filed a request with the PUCT, which was assigned PUCT Docket No. 49960, to decrease the Texas fixed fuel factor by approximately 12.2% to reflect decreased fuel expenses primarily related to a decrease in the price of natural gas used to generate power. On September 25, 2019, the Company's fixed fuel factor was approved by the PUCT on an interim basis effective for the first billing cycle of the October 2019 billing month. The Texas fixed fuel factor was determined to be final on October 15, 2019, and will continue until changed by the PUCT.
On November 26, 2019, the Company filed a petition with the PUCT, which was assigned PUCT Docket No. 50292, requesting authority to implement, beginning on January 1, 2020, a three-month, interim fuel refund of $15.0 million in fuel cost over-recoveries for the period from April 2019 through October 2019, including interest for the period from April 2019 through March 2020. On December 12, 2019, the Company’s fuel refund credit was approved on an interim basis. The Company implemented the fuel refund in customer bills beginning January 1, 2020, and completed the refund period on March 31, 2020, during which $14.0 million was refunded. On March 26, 2020, the PUCT issued a final order approving the fuel refund credits. As of March 31, 2020, the Company had a net fuel over-recovery balance of approximately $8.8 million in Texas.
Fuel Reconciliation Proceeding. On September 27, 2019, the Company filed an application with the PUCT, which was assigned PUCT Docket No. 50058, to reconcile $363.0 million of Texas fuel and purchased power expenses incurred during the period of April 1, 2016, through March 31, 2019. The Company cannot predict the outcome of this filing at this time. The April 1, 2019, through March 31, 2020, Texas jurisdictional fuel and purchased power costs subject to a future prudence review total approximately $61.7 million.
Community Solar. On March 20, 2018, the Company filed a petition with the PUCT and each of its Texas municipalities to expand its community solar program in Texas to include two-megawatts ("MW") of solar powered generation from the ten-MW solar photovoltaic facility located at Newman Power Station ("Newman") and to reduce rates under the community solar tariff. The case before the PUCT was assigned PUCT Docket No. 48181 and a hearing was held on December 4, 2018. The ALJ issued a proposal for decision on March 19, 2019, that approved the project as proposed by the Company. On May 9, 2019, the PUCT approved the Company's request to expand the program utilizing the two-MW of solar powered generation available from Newman. New subscriptions for the expanded program were accepted beginning in June 2019, and new rates for all existing and new customers were implemented in customer bills beginning July 1, 2019. As of June 30, 2019, the expanded program was fully subscribed.
Transmission Cost Recovery Factor ("TCRF"). On January 25, 2019, the Company filed an application with the PUCT to establish its TCRF, which was assigned PUCT Docket No. 49148 (the "2019 TCRF rate filing"). The 2019 TCRF rate filing was designed to recover a requested $8.2 million of Texas jurisdictional transmission revenue requirement that was not being recovered in the Company's Texas base rates for transmission-related investments placed in service from October 1, 2016, through September 30, 2018, net of retirements. On September 12, 2019, the Company filed an unopposed settlement agreement and proposed order for a TCRF revenue requirement of $7.5 million with a provision for recovery of revenue relating to the period from July 30, 2019 to December 31, 2019. Such revenue through December 31, 2019, approximated $3.0 million. On December 16, 2019, the PUCT issued a final order approving the settlement agreement, and the Company's TCRF rates became effective in customer bills beginning January 1, 2020. On January 14, 2020, the Company filed with the PUCT a proposed surcharge in
compliance with the final order issued in PUCT Docket No. 49148 for recovery of the $3.0 million related to 2019, over a period of 12 months beginning on April 1, 2020. The filing was assigned PUCT Docket No. 50256, and on February 7, 2020, the surcharge was approved through delegated authority by a Commission ALJ.
Distribution Cost Recovery Factor ("DCRF"). On March 28, 2019, the Company filed an application with the PUCT and each of its Texas municipalities to establish its DCRF, which was assigned PUCT Docket No. 49395 (the “2019 DCRF rate filing”). The 2019 DCRF rate filing was designed to recover a requested $7.9 million of Texas jurisdictional distribution revenue requirement that was not being recovered in the Company’s Texas base rates for distribution-related investments placed in service from October 1, 2016, through December 31, 2018, net of retirements. On August 13, 2019, the Company filed an unopposed settlement agreement and proposed order which resolved all issues in the proceeding and approved a DCRF revenue requirement of $7.8 million. On September 27, 2019, the PUCT issued a final order approving the settlement agreement, and the Company's DCRF rates became effective in customer bills beginning October 1, 2019.
Newman Unit 6 Certificate of Convenience and Necessity ("CCN"). On November 22, 2019, the Company filed an application with the PUCT for a CCN to own and operate a new, approximately 228 MW, natural gas-fired unit to be constructed at Newman. The case was assigned PUCT Docket No. 50277. The proposed unit is called Newman Unit 6. An air permit application for Newman Unit 6 was concurrently submitted to the Texas Commission on Environmental Quality. The new unit was selected through a competitive bidding process and is needed to serve growth in customer demand, to replace older and less efficient generators that the Company plans to retire in the next several years, and to help the Company meet its planning reserve margin. The Company cannot predict the outcome of these filings at this time.
Merger Rate Credit. On March 13, 2020, the Company filed an application with the PUCT and each of its Texas municipalities to implement a Merger rate credit of $21.0 million over 36 months, which was assigned PUCT Docket No. 50477. The final order that approved the Merger in Docket No. 49849 required the Company to file for approval of the Merger rate credit within 45 days after the issuance of that final order. The Company cannot predict the outcome of this filing at this time.
COVID-19 Orders. On March 13, 2020, in response to the growing threat of COVID-19, Governor Greg Abbott issued a Declaration of State of Disaster for all counties in Texas. On March 16, 2020, the PUCT opened Docket No. 50664 for Issues Related to the State of Disaster for the Coronavirus Disease 2019. That same day, the PUCT issued an order suspending certain of its rules related to filings and procedural requirements.
On March 26, 2020, the PUCT issued an order finding that the public emergency and imperative public necessity constitute good cause to grant exemptions to its rules related to utility authorization to disconnect service for nonpayment and the assessment of late fees for delinquent bills. On the same day, the PUCT issued a second order to provide regulated utility companies regulatory certainty by authorizing the use of an accounting mechanism and a subsequent process through which regulated utility companies may seek future recovery of expenses resulting from the effects of COVID-19. The PUCT order authorized electric, water, and sewer utilities to record as regulatory assets expenses resulting from the effects of COVID-19, including but not limited to non-payment of qualified customer bills as specified by the prior order. In future proceedings, the PUCT indicated it would consider whether each utility's request for recovery of these regulatory assets is reasonable and necessary.
On April 12, 2020, Governor Abbott renewed the disaster declaration proclamation for all counties in Texas. Finding that good cause continues to exist, the PUCT on April 17, 2020, extended its order finding exceptions to its rules until May 15, 2020, for residential customers.
Other Required Approvals. The Company has obtained other required approvals for tariffs and other approvals required by the PURA and the PUCT.
New Mexico Regulatory Matters
Future New Mexico Rate Case Filing. The Company was required to file its next New Mexico base rate case no later than July 31, 2019. On July 10, 2019, the NMPRC issued an order approving a joint request by the Company, NMPRC staff, and the New Mexico Attorney General to delay filing of the Company's next base rate case until after the conclusion of a proceeding addressing the Merger. The NMPRC order requires the Company to file its next rate case application within three months of the final disposition of the proceeding addressing the Merger in New Mexico. A final order approving the Merger was issued by the NMPRC on March 11, 2020.
New Mexico Order Commencing Review of the Effects of the TCJA on Regulated New Mexico Utilities. On January 24, 2018, the NMPRC initiated a proceeding in Case No. 18-00016-UT on the impact of the TCJA on New Mexico regulated utilities. On
April 4, 2018, the NMPRC issued an order requiring the Company to file a proposed interim rate rider to adjust the Company's New Mexico base revenues in amounts equivalent to the Company's reduced income tax expense for New Mexico customers resulting from the TCJA, to be implemented on or before May 1, 2018. The NMPRC order further requires that the Company record and track a regulatory liability for the excess accumulated deferred income taxes ("ADIT") created by the change in the federal corporate income tax rate, consistent with the effective date of the TCJA, and subject to amortization determined by the NMPRC in the Company's next general rate case. The Company recorded such a regulatory liability in 2017. On April 16, 2018, after consultation with the New Mexico Attorney General pursuant to the NMPRC order, the Company filed an interim rate rider with the NMPRC with a proposed effective date of May 1, 2018. The annualized credits expected to be refunded to New Mexico customers approximate $4.9 million. The Company implemented the interim rate rider in customer bills beginning May 1, 2018 pursuant to the NMPRC order.
On September 5, 2018, the NMPRC issued an order in Case No. 17-00255-UT involving the request of Southwestern Public Service Company ("SPS") to change rates in which the NMPRC directed SPS to refund the difference in corporate tax rate from January 1, 2018, through the effective date of new rates. SPS appealed the NMPRC order to the New Mexico Supreme Court in Southwestern Public Service Co. v. NMPRC, No. S-1-SC-37248 ("SPS Appeal No. 1"), challenging the refund as prohibited retroactive ratemaking among other reasons. The New Mexico Supreme Court issued a partial and interim stay of the rates on September 26, 2018. On September 12, 2018, the NMPRC in Case No. 18-00016-UT issued an Order Regarding the Disposition of Tax Savings Under the Federal Tax Cuts and Jobs Act of 2017, which put public utilities on notice that all revenue collected through general rates for the purpose of payment of federal income taxes is and will continue to be subject to possible refund upon a subsequent determination to be made in the appropriate pending or future NMPRC adjudicatory hearing. On October 11, 2018, SPS filed a Notice of Appeal of that NMPRC order to the New Mexico Supreme Court in Southwestern Public Service Co. v. NMPRC, No. S-1-SC-37308 ("SPS Appeal No. 2"). On February 15, 2019, the NMPRC and SPS filed a joint motion for remand and stipulated dismissal of SPS appeals of NMPRC orders with the New Mexico Supreme Court, which among other things, reflected agreements between the NMPRC and SPS, which in part provide that the NMPRC will replace the order in Case No. 17-00255-UT with a new order that eliminates the retroactive TCJA refund and that SPS will request dismissal of SPS Appeal No. 1 and SPS Appeal No. 2. On February 28, 2019, the New Mexico Supreme Court remanded SPS Appeal No. 1 back to the NMPRC and dismissed the appeal. On March 6, 2019, the NMPRC issued a revised final order on remand in Case No. 17-00255-UT that, in part, eliminated the retroactive TCJA refund.
Fuel and Purchased Power Costs. Pursuant to NMPRC Rule 550, fuel and purchased power costs, net of the cost of off-system sales and related shared margins, are reconciled to actual costs on a monthly basis and recovered or refunded to customers the second succeeding month through the New Mexico Fuel and Purchased Power Cost Adjustment Clause ("FPPCAC"). The Company must file an application for continued use of its FPPCAC no more than four years from the date its last FPPCAC was continued. As required, the Company filed a request to continue use of its FPPCAC with the NMPRC on January 5, 2018, which was assigned Case No. 18-00006-UT. The NMPRC issued a final order in the case on February 13, 2019, which authorized the Company to continue use of its FPPCAC without change and approved the Company's reconciliation of its fuel and purchased power costs for the period January 1, 2015, through December 31, 2016. New Mexico jurisdictional fuel and purchased power costs subject to a future prudence review are fuel and purchased power costs from January 1, 2017, through March 31, 2020 that total approximately $116.6 million. At March 31, 2020, the Company had a net fuel over-recovery balance of approximately $0.8 million related to the FPPCAC in New Mexico.
Amendments to the New Mexico Renewable Energy Act (the "REA"). The REA requires electric utilities to meet a Renewable Portfolio Standard ("RPS") of twenty percent of its total retail sales to New Mexico customers by 2020. Effective June 14, 2019, the New Mexico Energy Transition Act amended the REA (the "Amended REA") to, among other things: (i) increase the RPS to forty percent by 2025, fifty percent by 2030, and eighty percent by 2040; (ii) impose a zero-carbon standard by 2045; (iii) eliminate the reduction to the RPS requirement for sales to qualifying large non-governmental customers whose costs are capped under the REA; (iv) set a statutory reasonable cost threshold; and (v) provide cost recovery for certain undepreciated investments and decommissioning costs, such as coal-fired generation, associated with generation required by the NMPRC to be discontinued and replaced with lower or zero-carbon generation. In administering the eighty percent RPS and zero-carbon standards, the Amended REA requires the NMPRC to consider certain factors, including safety, reliability and rate impact to customers. On October 10, 2019, the NMPRC initiated a rulemaking proceeding to implement the Amended REA in Case No. 19-00296-UT. The Company is currently evaluating the impact that the Amended REA may have on its operations. Further, the Company has not determined the costs associated with complying with the Amended REA including potential fines that could be associated with non-compliance.
New Mexico RPS. Effective January 1, 2018, pursuant to the final order in NMPRC Case No. 17-00090-UT, the RPS costs for New Mexico are recovered through a separate RPS Cost Rider and not through the FPPCAC. At March 31, 2020, the Company had a net fuel over-recovery balance related to the RPS Cost Rider of approximately $2.5 million. The RPS Cost Rider is updated
in an annual NMPRC filing, including a reconciliation of the prior year’s RPS costs and RPS Cost Rider revenue. On October 1, 2019, in Case No. 19-00099-UT, the Company filed its required application with the NMPRC for approval of its 2019 Annual Renewable Plan and for adjustment of its RPS Cost Rider for reconciliation of 2018 costs and revenues and to recover RPS costs for 2020. On November 18, 2019, following a second prehearing conference, the Hearing Examiner issued an order suspending the procedural schedule in order to allow the Company to amend its filed plan after the completion of an ongoing Request for Proposals to solicit possible new resources, by no later than March 31, 2020. The order suspending the procedural schedule also required the Company to file a revised RPS Cost Rider to reconcile the net fuel over-recovery balance as of December 31, 2018, which the Company filed on December 2, 2019 and which became effective on January 1, 2020. On March 31, 2020, the Company filed an application for approval of its amended 2019 Annual Renewable Plan and 2020 Annual Renewable Plan and for adjustment of its RPS Cost Rider for reconciliation of 2019 costs and revenue and to recover RPS costs for 2021. The Company cannot predict the outcome of this filing at this time.
Expedited Approval for CCN (Solar/Storage Project at New Mexico State University ("NMSU")). On November 20, 2019, the Company filed an application with the NMPRC requesting a certificate of public convenience and necessity to construct, own and operate a three-MW solar powered generation facility coupled with a one-MW battery storage system to be located on NMSU property in Arrowhead Park in the Company's service territory in New Mexico. The Company's application also seeks approval of a special retail rate contract between the Company and NMSU to recover the costs of the new facility and its operations from NMSU. The new facility will be a dedicated Company-owned resource serving NMSU. The Company has requested approval such that the project can begin construction in 2020 to maximize potential tax benefits. This case was assigned NMPRC Case No. 19-00350-UT. Hearings in this case currently are scheduled to begin June 4, 2020. The Company cannot predict the outcome of this filing at this time.
New Mexico Efficient Use of Energy Recovery Factor ("EUERF"). On July 2, 2018, the Company filed its required application with the NMPRC for approval of its 2019-2021 Energy Efficiency and Load Management Plan and EUERF. The application was assigned Case No. 18-00116-UT. On March 6, 2019, the NMPRC issued a final order approving: (i) the Company's 2019-2021 Energy Efficiency and Load Management Plan, with minor program modifications; (ii) the base incentive of 7.1% of program expenditures, or approximately $0.4 million annually for 2019-2021; and (iii) the continuation of the Company's EUERF. During 2019, the Company recorded incentives in operating revenues of $0.4 million related to its 2019 Energy Efficiency and Load Management Plan.
Newman Unit 6 CCN. On November 18, 2019, the Company filed an application with the NMPRC for a CCN to own and operate a new, approximately 228 MW, natural gas-fired unit to be constructed at Newman. The case was assigned NMPRC Case No. 19-00349-UT. The proposed unit is called Newman Unit 6. The new unit was selected through a competitive bidding process and is needed to serve growth in customer demand, to replace older and less efficient generators that the Company plans to retire in the next several years, and to help the Company meet its planning reserve margin. In light of the current COVID-19 pandemic conditions, on April 8, 2020, the Hearing Examiner issued an order holding the procedural order in abeyance to reset procedural dates, including the public hearing. The Hearing Examiner subsequently issued a procedural order on April 15, 2020, to reset the schedule and establish a new hearing date for July 20-24, 2020. The Company cannot predict the outcome of this case at this time.
Long-Term Purchased Power Agreement ("LTPPA") Approval. On November 18, 2019, the Company filed an application with the NMPRC to request prior approval for three LTPPAs pursuant to NMPRC Rule 17.9.551 of the New Mexico Administrative Code ("Rule 551"). The case was assigned NMPRC Case No. 19-00348-UT. The three LTPPAs provide for the purchase of energy and capacity from: (i) a 100 MW solar plant to be constructed in Santa Teresa, New Mexico; (ii) a 100 MW solar plant combined with a 50 MW of battery energy storage to be constructed in Otero County, New Mexico; and (iii) a 50 MW battery energy storage facility to be constructed in Canutillo, Texas. Rule 551 requires that no utility become irrevocably obligated under a LTPPA without first obtaining the NMPRC’s written approval of the agreement. On April 22, 2020, the Hearing Examiner issued a Recommended Decision in NMPRC Case No. 19-00348-UT recommending NMPRC approval of the solar plant and the combined solar plant and battery energy storage LTPPAs and disapproval of the battery energy storage LTPPA. The Company filed exceptions to the Recommended Decision on April 29, 2020. The Recommended Decision is pending NMPRC final order. The Company cannot predict the outcome of this case at this time.
COVID-19 Order. On March 19, 2020, the NMPRC issued an “Order Finding the Need for the Adoption and Issuance of an Immediate Temporary Emergency Rule Prohibiting the Discontinuation of Residential Customers Utility Service” in NMPRC Case No. 20-00069-UT, adopting a temporary emergency rule prohibiting public utilities from discontinuing residential customer utility service during the period of the New Mexico Governor Lujan Grisham’s Emergency Executive Orders related to the COVID-19. Based on those orders, the NMPRC found that a Public Health Emergency is in effect based on findings of an imminent peril to the public health, safety or welfare and the necessity for the preservation of the public, health, safety or general welfare.
The NMPRC order does not prohibit disconnection of a residential customer’s service during the time period during which the Emergency Executive Orders are in effect for emergency or safety reasons or upon customer request.
On April 27, 2020, the Company, New Mexico Gas Company, Public Service Company of New Mexico, and Southwestern Public Service Company filed a Joint Motion for Authorization for an Accounting Order to Allow Creation of a Regulatory Asset to Track Costs of Emergency Conditions. The joint motion seeks authority to create regulatory assets for uncollectible payment arrearages and incremental expenses incurred March 11, 2020 through December 31, 2020. On May 6, 2020, the NMPRC ordered that additional information is necessary before a final order can be issued on the joint motion. As such, utilities and interested parties are requested to address the additional issues noted in its order, as well as any additional issues they may identify, in the response to the joint motion.
Other Required Approvals. The Company has obtained other required approvals for tariffs and other approvals as required by the NMPUA and the NMPRC.
Federal Regulatory Matters
Inquiry Regarding the Effect of the TCJA on Commission-Jurisdictional Rates and Order to Show Cause. On March 15, 2018, the FERC issued two show cause orders under Section 206 of the Federal Power Act and Rule 209(a) of the FERC’s Rules of Practice and Procedure, directing 48 individual public utilities with stated transmission rates or transmission formula rates with a fixed line item of 35% for the federal income tax component to, within 60 days of the date of the orders, either (i) propose revisions to their transmission rates under their open access transmission tariffs or transmission owner tariffs on file with the FERC, or (ii) show cause why they should not be required to do so ("Show Cause Proceeding"). The Company was included in the list of public utilities impacted by the FERC orders. On May 14, 2018, the Company submitted its response, as required by the FERC order, which demonstrated that the reduced annual income tax does not cause the Company's total transmission revenues to become excessive and therefore no rate reduction was justified. Instead, the Company stated in its response that it will prepare for a future filing in which it will seek approval for revised Open Access Transmission Tariff ("OATT") rates that would include the recovery of an increased total transmission revenue requirement from OATT customers based on current circumstances and appropriate forward-looking adjustments. On November 15, 2018, the FERC issued an order finding that the Company had demonstrated that no rate reduction was justified and terminating the Show Cause Proceeding. The Company expects to file its request for approval to revise OATT rates in 2020.

Notice of Proposed Rulemaking ("NOPR")on Public Utility Transmission Changes to Address ADIT. On November 15, 2018, the FERC issued a NOPR that proposes to direct public utilities with transmission OATT rates, a transmission owner tariff or a rate schedule to determine the amount of excess or deficient ADIT caused by the TCJA’s reduction to the federal corporate income tax rate and return or recover this amount to or from customers. The NOPR has been assigned FERC Docket No. RM19-5-000. On November 21, 2019, the FERC issued a final rule, Order No. 864, which declined to adopt the proposals to require public utilities such as the Company with transmission stated rates to determine the amount of excess or deficient ADIT caused by the TCJA's reduction to the federal corporate income tax and return or recover this amount to or from customers. Instead, the FERC determined that companies with transmission stated rates should address any excess or deficient ADIT caused by the TCJA in their next rate case. On April 16, 2020, the FERC issued an order on rehearing, Order No. 864-A, affirming this decision.
FERC Audit. On February 6, 2019, the FERC notified the Company that it is commencing an audit that is intended to evaluate the Company’s compliance with: (i) the approved terms, conditions, and rates of its OATT; (ii) the accounting requirements of the Uniform System of Accounts; (iii) the reporting requirements of the FERC Form No. 1 Annual Report and Supplemental Form 3-Q Quarterly Financial Reports; and (iv) the regulations regarding Open Access Same-time Information Systems. The audit covers the period January 1, 2016 to the present and was assigned FERC Docket No. PA19-3-000. The Company cannot predict the outcome or findings, if any, of the FERC audit at this time.