XML 64 R14.htm IDEA: XBRL DOCUMENT v2.4.1.9
Commitments, Contingencies And Uncertainties
3 Months Ended
Mar. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
Commitments, Contingencies And Uncertainties
Commitments, Contingencies and Uncertainties
For a full discussion of commitments and contingencies, see Note K of Notes to Financial Statements in the 2014 Annual Report on Form 10-K. In addition, see Notes C and D above and Notes C and E of Notes to Financial Statements in the 2014 Annual Report on Form 10-K regarding matters related to wholesale power sales contracts and transmission contracts subject to regulation and Palo Verde, including decommissioning, spent nuclear fuel and waste disposal, and liability and insurance matters.
Power Purchase and Sale Contracts
To supplement its own generation and operating reserves, and to meet required renewable portfolio standards, the Company engages in firm power purchase arrangements which may vary in duration and amount based on evaluation of the Company’s resource needs, the economics of the transactions, and specific renewable portfolio requirements. For a full discussion of power purchase and sale contracts that the Company has entered into with various counterparties, see Note K of Notes to Financial Statements in the 2014 Form 10-K.
Environmental Matters
General. The Company is subject to extensive laws, regulations and permit requirements with respect to air and greenhouse gas emissions, water discharges, soil and water quality, waste management and disposal, natural resources and other environmental matters by federal, state, regional, tribal and local authorities. Failure to comply with such laws, regulations and requirements can result in actions by authorities or other third parties that might seek to impose on the Company administrative, civil and/or criminal penalties or other sanctions. In addition, releases of pollutants or contaminants into the environment can result in costly cleanup liabilities. These laws, regulations and requirements are subject to change through modification or reinterpretation, or the introduction of new laws and regulations and, as a result, the Company may face additional capital and operating costs to comply. For a full discussion of certain key environmental issues, laws and regulations facing the Company see Note K of Notes to Financial Statements in the 2014 Form 10-K.
Clean Air Interstate Rule/Cross State Air Pollution Rule. The EPA promulgated the Cross-State Air Pollution Rule ("CSAPR") in August 2011, which rule involves requirements to limit emissions of nitrogen oxides ("NOx") and sulfur dioxide ("SO2") from certain of the Company's power plants in Texas and/or purchase allowances representing other parties' emissions reductions. CSAPR was intended to replace the EPA's 2005 Clean Air Interstate Rule ("CAIR"). While the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") vacated CSAPR in August 2012 and allowed CAIR to stand until the EPA issued a proper replacement, on April 29, 2014, the U.S. Supreme Court reversed and upheld CSAPR, remanding certain portions of CSAPR to the D.C. Circuit for further consideration. On June 26, 2014, the EPA filed a motion asking the D.C. Circuit to lift its stay on CSAPR. On October 23, 2014, the D.C Circuit lifted its stay of CSAPR, and while we are unable to determine the full impact of the reinstatement of CSAPR until the D.C. Circuit and the EPA take further action, the Company believes it is currently positioned to comply with CSAPR.
National Ambient Air Quality Standards. Under the CAA, the EPA sets National Ambient Air Quality Standards ("NAAQS") for six criteria pollutants considered harmful to public health and the environment, including PM, NOx, carbon monoxide ("CO"), ozone and SO2. NAAQS must be reviewed by the EPA at five-year intervals. In 2010, the EPA tightened the NAAQS for both NOx and SO2. The EPA is considering a 1-hour secondary NAAQS for NOx and SO2. In January 2013, the EPA tightened the NAAQS for fine PM. On November 26, 2014, the EPA announced a proposal to tighten the 2008 primary and secondary ground-level ozone NAAQS. Ozone is the main component of smog. While not directly emitted into the air, it forms from precursors, including NOx and volatile organic compounds, in combination with sunlight. EPA proposes to tighten the current 8-hour primary (health-based) standard of 75 parts per billion ("ppb") to a level within its preferred range of 65 to 70 ppb, while also taking comment on a potential standard as low as 60 ppb and on retaining the current standard. The EPA is expected to issue a final rule by November 2015 and make attainment/nonattainment designations for any revised standards by November 2017. The Company continues to evaluate what impact these final and proposed NAAQS could have on its operations. If the Company is required to install additional equipment to control emissions at its facilities, the revised NAAQS could have a material impact on its operations and financial results.
Other Laws and Regulations and Risks. The Company has entered into an agreement to sell its interest in Four Corners Generating Station ("Four Corners") to APS at the expiration of the 50-year participation agreement in July 2016. The Company believes that it has better economic and cleaner alternatives for serving the energy needs of its customers than coal-fired generation, which is subject to extensive regulation and litigation. By ceasing its participation in Four Corners, the Company will avoid the significant cost required to install expensive pollution control equipment in order to continue operation of the plant as well as the risks of water availability that might adversely affect the amount of power available, or the price thereof, from Four Corners in the future. The closing of the transaction is subject to the receipt of regulatory approvals.
In 2012, several environmental groups filed a lawsuit in federal district court against the Office of Surface Mining Reclamation and Enforcement (“OSM”) of the U.S. Department of the Interior challenging OSM’s 2012 approval of a permit revision which allowed for the expansion of mining operations into a new area of the mine that serves Four Corners (“Area IV North”). In April 2015, the court issued an order invalidating the permit revision, thereby prohibiting mining in Area IV North until OSM takes action to cure the defect in its permitting process identified by the court. Navajo Transitional Energy Company, the owner of the mine and supplier of coal to Four Corners, has indicated that it does not anticipate any near-term interruption of coal supply to the plant as a result of the suspension of mining in Area IV North. The Company cannot predict the time period that will be required for OSM’s further permitting process to be completed or whether the outcome of the process will be sufficient to allow the permit to be reinstated.
Climate Change. The U.S. federal government has either considered, proposed and/or finalized legislation or regulations limiting GHG emissions, including carbon dioxide. In particular, the U.S. Congress has considered legislation to restrict or regulate GHG emissions. In the past few years, the EPA began using the CAA to regulate carbon dioxide and other GHG emissions, such as the 2009 GHG Reporting Rule and the EPA's sulfur hexafluoride ("SF6") reporting rule, both of which apply to the Company, as well as the EPA's 2010 actions to impose permitting requirements on new and modified sources of GHG emissions. After announcing his plan to address climate change in 2013, the President directed the EPA to issue proposals for GHG rulemaking addressing power plants. In January 2014, the EPA published a proposal to establish new source performance standards limiting carbon dioxide emissions from new electric generating units, and in June 2014, a proposal to create carbon dioxide standards for existing and modified/reconstructed power plants. The Company participated in the associated proposed rulemaking comment periods. On January 7, 2015, EPA announced it plans to issue final rules for new, existing and modified/reconstructed power plants by this summer. Given the very significant remaining uncertainties regarding these EPA rules, the Company believes it is impossible to meaningfully quantify the costs of these potential requirements at present.
Environmental Litigation and Investigations. Since 2009, the EPA and certain environmental organizations have been scrutinizing, and in some cases, have filed lawsuits, relating to certain air emissions and air permitting matters related to Four Corners. In particular, since July 2011, the U.S. Department of Justice (the "DOJ"), on behalf of the EPA, and APS have been engaged in substantive settlement negotiations in an effort to resolve certain of the pending matters. The allegations being addressed through settlement negotiations are that APS failed to obtain the necessary permits and install the controls necessary under the Clean Air Act ("CAA") to reduce SO2, NOx, and particular matter ("PM"), and that defendants failed to obtain an operating permit under Title V of the CAA that reflects applicable requirements imposed by law. In November 2014, the DOJ provided APS with a draft consent decree to settle the EPA matter, which decree contains specific provisions for the reduction and control of NOx, SO2, and PM, as well as provisions for a civil penalty, and expenditures on environmental mitigation projects with an emphasis on projects that address alleged harm to the Navajo Nation. Settlement discussions are on-going and the Company is unable to predict with certainty the final outcome of these settlement negotiations. The Company has accrued a total of $0.6 million as its estimated share of the loss contingency related to this matter.
Earthjustice filed a lawsuit in the United States District Court for New Mexico on October 4, 2011 for alleged violations of the Prevention of Significant Deterioration ("PSD") provisions of the CAA related to Four Corners. On January 6, 2012, Earthjustice filed a First Amended Complaint adding claims for violations of the CAA's New Source Performance Standards ("NSPS") program. Among other things, the plaintiffs seek to have the court enjoin operations at Four Corners until APS applies for and obtains any required PSD permits and complies with the referenced NSPS program. The plaintiffs further request the court to order the payment of civil penalties, including a beneficial mitigation project. On April 2, 2012, APS and the other Four Corners participants filed motions to dismiss with the court. The case is being held in abeyance while the parties seek to negotiate a settlement. On March 30, 2013, upon joint motion of the parties, the court issued an order deeming the motions to dismiss withdrawn without prejudice during pendency of the stay. At such time as the stay is lifted, APS, the Company and the other Four Corners participants may reinstate the motions to dismiss. Settlement discussions are on-going. The Company does not expect the outcome of this matter to have a material impact on its financial position, results of operations or cash flows.
New Mexico Tax Matter Related to Coal Supplied to Four Corners
On May 23, 2013, the New Mexico Taxation and Revenue Department issued a notice of assessment for coal severance surtax, penalty, and interest totaling approximately $30 million related to coal supplied under the coal supply agreement for Four Corners (the "Assessment"). The Company's share of the Assessment is approximately $1.5 million. On behalf of the Four Corners participants, the coal supplier made a partial payment of the Assessment and immediately filed a refund claim with respect to that partial payment in August 2013. The New Mexico Taxation and Revenue Department denied the refund claim. On December 19, 2013, the coal supplier and APS, on its own behalf and as operating agent for Four Corners, filed complaints with the New Mexico District Court contesting both the validity of the Assessment and the refund claim denial. APS believes the Assessment and the refund claim denial are without merit. The Company cannot predict the timing, results, or potential impacts of the outcome of this litigation.