ENSCO INTERNATIONAL INCORPORATED
Contract Status of Offshore Rig Fleet
As of December 15, 2005


Statements contained in this Contract Status of Offshore Rig Fleet report including information regarding the Company's estimated rig availability, contract duration or future day rates, customers or contract status are forward-looking statements. The forward-looking statements are made pursuant to safe harbor provisions of the Private Securities Litigation Reform Act of 1995. Such forward-looking statements include references to estimated rig availability, future day rates, customers, contracts or rig utilization. It is important to note that the Company's actual results could differ materially from those projected in such forward-looking statements. The factors that could cause actual results to differ materially from those in the forward-looking statements include the following: (i) renegotiation or adjustment of day rates (ii) timing of completion of work in progress, (iii) actual duration of wells, (iv) letter of intent or contract cancellations; (v) early contract termination, (vi) actual timing of contract term completion, (vii) finalization, modifications or termination of commitments made verbally or by letters of intent, (viii) new contracts or contract extensions, and (ix) the operational and other risks described from time to time in the Company's SEC filings. Copies of such filings may be obtained at no charge by contacting the Company's Investor Relations Department at 214-397-3045 or the investor relations section of the Company's website at http://www.enscous.com.
 
All information in this rig status release is as of date posted. The Company undertakes no duty to update the contents of this Offshore Rig Fleet Contract Status report or any forward-looking statement contained therein to conform the statement to actual results or to reflect changes in the Company's expectations.

            Est. Avail/  
    Water          Contract  
Rig Name      Design      Depth    Customer/Status Day Rate    Location   Change                Comments                 
                               
North & South
America          

Gulf of Mexico
Jackups
                      
ENSCO 60  Levingston 111-C  300  Taylor Energy  Mid 80's  Gulf of Mexico  Jan. 06    
ENSCO 68  MLT 84-CE  400  ExxonMobil  Mid 90's  Gulf of Mexico  Jan. 06    
ENSCO 69  MLT 84-S  400  Shipyard     Gulf of Mexico  Feb. 06  Next to ConocoPhillips in Venezuela to Jun. 07, low 70's  
ENSCO 74  MLT Super 116-C  400  Dominion  Low 90's  Gulf of Mexico  Apr. 06  Rate increases late Jan. 06 to low 110's 
ENSCO 75  MLT Super 116-C  400  Stone  Mid 90's  Gulf of Mexico  Feb. 06    
ENSCO 81  MLT 116-C  350  Hunt Petroleum  Mid 130's  Gulf of Mexico  Feb. 06  Next to BP, well to well, market rate 
ENSCO 82  MLT 116-C  300  Dominion  Low 120's  Gulf of Mexico  Dec. 05  Next to Pogo to Feb. 06, high 80's, then to Chevron to Aug. 06, low 100's 
ENSCO 83  MLT 82 SD-C  250  Gryphon  Low 90's  Gulf of Mexico  Apr. 06  Next to shipyard for approx. 40 days to Jun. 06 
ENSCO 84  MLT 82 SD-C  250  Apache  Mid 90's  Gulf of Mexico  Apr. 06  Rate increases late Dec. 05 to low 100's 
ENSCO 86  MLT 82 SD-C  250  Shipyard     Gulf of Mexico  Mar. 06    
ENSCO 87  MLT 116-C  350  Shipyard     Gulf of Mexico  Mar. 06  Next to Hunt Petroleum to Sep. 06, market rate 
ENSCO 89  MLT 82 SD-C  250  Unocal  Low 60's  Gulf of Mexico  Apr. 06    
ENSCO 90  MLT 82 SD-C  250  Apache  Mid 90's  Gulf of Mexico  Apr. 06  Rate increases Jan. 06 to low 100's 
ENSCO 93  MLT 82 SD-C  250  Hunt Oil  Mid 70's  Gulf of Mexico  Feb. 06    
ENSCO 98  MLT 82 SD-C  250  Dominion  Low 70's  Gulf of Mexico  Jan. 06  Next to Stone to Jul. 06, mid 70's 
ENSCO 99  MLT 82 SD-C  250  ExxonMobil  Low 80's  Gulf of Mexico  Apr. 06  Well to well, market rate 
ENSCO 105  KFELS MOD V-B  400  Houston Expl.  Mid 130's  Gulf of Mexico  Dec. 05  Next to Dominion to Jan. 06, low 100's, then to Nexen to Jan. 07, low 140's 

Semisubmersible
                      
ENSCO 7500  Dynamically Positioned  8000  Anadarko  Mid 180's  Gulf of Mexico  Dec. 05  Next to shipyard for approx. 30 days until mid Jan. 06, then to Chevron to Jan. 08, mid 180's, plus options 
ENSCO 8500  Dynamically Positioned  8500  Under construction        2Q 08  Contracted to Anadarko, Dominion, Kerr McGee to 2Q12, low 250's plus operating cost escalation & lump sum payment of $20 million, plus options 

Platform Rigs
                      
ENSCO 25  3000 HP API     Chevron  Mid 30's  Gulf of Mexico  Dec. 06  Well to well 
 
          Note:  Highlighted/underlined rig names signify changes in rig status information from the previous month.

1

ENSCO INTERNATIONAL INCORPORATED
Contract Status of Offshore Rig Fleet
As of December 15, 2005


Statements contained in this Contract Status of Offshore Rig Fleet report including information regarding the Company's estimated rig availability, contract duration or future day rates, customers or contract status are forward-looking statements. The forward-looking statements are made pursuant to safe harbor provisions of the Private Securities Litigation Reform Act of 1995. Such forward-looking statements include references to estimated rig availability, future day rates, customers, contracts or rig utilization. It is important to note that the Company's actual results could differ materially from those projected in such forward-looking statements. The factors that could cause actual results to differ materially from those in the forward-looking statements include the following: (i) renegotiation or adjustment of day rates (ii) timing of completion of work in progress, (iii) actual duration of wells, (iv) letter of intent or contract cancellations; (v) early contract termination, (vi) actual timing of contract term completion, (vii) finalization, modifications or termination of commitments made verbally or by letters of intent, (viii) new contracts or contract extensions, and (ix) the operational and other risks described from time to time in the Company's SEC filings. Copies of such filings may be obtained at no charge by contacting the Company's Investor Relations Department at 214-397-3045 or the investor relations section of the Company's website at http://www.enscous.com.
 
All information in this rig status release is as of date posted. The Company undertakes no duty to update the contents of this Offshore Rig Fleet Contract Status report or any forward-looking statement contained therein to conform the statement to actual results or to reflect changes in the Company's expectations.

            Est. Avail/  
    Water          Contract  
Rig Name      Design      Depth    Customer/Status Day Rate    Location   Change                Comments                 
                               
Europe & Africa

North Sea
                      
ENSCO 70  Hitachi K1032N  250  ATP  Mid 70's  UK  May 06  Plus options 
ENSCO 71  Hitachi K1032N  225  Maersk  High 70's  Denmark  Aug. 06  Possible accommodation mode in late Dec. 05 for 1-2 months, rate TBD, plus options 
ENSCO 72  Hitachi K1025N  225  Total  Low 110's  Netherlands  Dec. 06  Market rate, plus option 
ENSCO 80  MLT 116-CE  225  ConocoPhillips  Mid 110's  UK  May 06  Market rate, plus options 
ENSCO 85  MLT 116-C  225  BHPB  Mid 80's  UK  Dec. 05  Next to Newfield to Feb. 06, mid 80's, then to ExxonMobil to Apr. 06, mid 90's, then to Newfield to Dec. 07, market rate, plus options 
ENSCO 92  MLT 116-C  225  ConocoPhillips  Mid 110's  UK  Mar. 06  Market rate, plus options, expect continuation to Jan. 07, next expect to work to May 08, mid 160's, plus options 
ENSCO 101  KFELS MOD V-A  400  Tullow  Low 100's  UK  Apr. 07  Market rate commencing Jan. 06, plus options  
ENSCO 102  KFELS MOD V-A  400  Enroute     UK  Feb. 06  Next to ConocoPhillips to Mar. 07, low 150's, plus options 

Africa
                      
ENSCO 100  MLT 150-88-C  350  ExxonMobil  Mid 130's  Nigeria  Feb. 07  Plus option 

Asia & Pacific Rim

Middle East/ India
                      
ENSCO 50  F&G 780 Mod II  300  British Gas  Low 70's  India  Dec. 06  Rate increases late Dec. 05 to mid 70's, then increases Jun. 06 to high 90's, plus option 
ENSCO 53  F&G 780 Mod II  300  British Gas  Mid 60's  India  Dec. 06  Rate increases Mar. 06 to high 90's, plus option 
ENSCO 54  F&G 780 Mod II  300  Ras Gas  Mid 50's  Qatar  Aug. 07  Plus options 
ENSCO 76  MLT Super 116-C  350  Saudi Aramco  Low 100's  Saudi Arabia  Sep. 08  Plus options 
ENSCO 88  MLT 82 SD-C  250  Ras Gas  Low 60's  Qatar  May 08  Plus options 
ENSCO 94  Hitachi 250-C  250  Ras Gas  Mid 50's  Qatar  Jan. 08  Plus options 
ENSCO 95  Hitachi 250-C  250  Saudi Aramco  Mid 70's  Saudi Arabia  Nov. 08  Plus options 
ENSCO 96  Hitachi 250-C  250  Saudi Aramco  Low 80's  Saudi Arabia  Dec. 08  Plus option 
ENSCO 97  MLT 82 SD-C  250  Saudi Aramco  Low 80's  Saudi Arabia  Oct. 07  Plus options 
 
          Note:  Highlighted/underlined rig names signify changes in rig status information from the previous month.

2

ENSCO INTERNATIONAL INCORPORATED
Contract Status of Offshore Rig Fleet
As of December 15, 2005


Statements contained in this Contract Status of Offshore Rig Fleet report including information regarding the Company's estimated rig availability, contract duration or future day rates, customers or contract status are forward-looking statements. The forward-looking statements are made pursuant to safe harbor provisions of the Private Securities Litigation Reform Act of 1995. Such forward-looking statements include references to estimated rig availability, future day rates, customers, contracts or rig utilization. It is important to note that the Company's actual results could differ materially from those projected in such forward-looking statements. The factors that could cause actual results to differ materially from those in the forward-looking statements include the following: (i) renegotiation or adjustment of day rates (ii) timing of completion of work in progress, (iii) actual duration of wells, (iv) letter of intent or contract cancellations; (v) early contract termination, (vi) actual timing of contract term completion, (vii) finalization, modifications or termination of commitments made verbally or by letters of intent, (viii) new contracts or contract extensions, and (ix) the operational and other risks described from time to time in the Company's SEC filings. Copies of such filings may be obtained at no charge by contacting the Company's Investor Relations Department at 214-397-3045 or the investor relations section of the Company's website at http://www.enscous.com.
 
All information in this rig status release is as of date posted. The Company undertakes no duty to update the contents of this Offshore Rig Fleet Contract Status report or any forward-looking statement contained therein to conform the statement to actual results or to reflect changes in the Company's expectations.

            Est. Avail/  
    Water          Contract  
Rig Name      Design      Depth    Customer/Status Day Rate    Location   Change                Comments                 
                               

Southeast Asia/
                      
Australia                      
ENSCO 51  F&G 780 Mod II  300  Shell  Low 60's  Brunei  Jan. 08  Rate increases Jan. 06 to mid 60's and adjusts every six months thereafter  
ENSCO 52  F&G 780 Mod II  300  Petronas Carigali  Mid 50's  Malaysia  Nov. 06  Next expect to work to Nov. 07, mid 90's, plus options 
ENSCO 56  F&G 780 Mod II  300  Shipyard     Singapore  Jan. 06  Next to Shell Todd in New Zealand to Feb. 07, low 80's, plus options, then expect to work to Mar. 07, mid 140's, plus options 
ENSCO 57  F&G 780 Mod II  300  Murphy  Low 90's  Malaysia  Dec. 06  Rate increases Aug. 06 to low 100's, plus options 
ENSCO 67  MLT 84-CE  400  ROC Oil  High 90's  Australia  Feb. 06  Plus options, then to Apache to Dec. 06, mid 90's, then expect to work to Jul. 07, mid 140's 
ENSCO 104  KFELS MOD V-B  400  ConocoPhillips  Mid 80's  Indonesia  Dec. 05  Next to Premier to Feb. 06, mid 80's, then to CTOC to Jul. 06, mid 90's, plus options 
ENSCO 106  KFELS MOD V-B  400  Apache  Low 100's  Australia  Feb. 07  Rate increases Feb. 06, mid 180's, plus options 
ENSCO 107  KFELS MOD V-B  400  Under construction     Singapore  Feb. 06  Next expect to work in Malaysia to Mar. 06, low 100's, then to Pearl in Thailand to May 06, low 100's, then to KNOC in Vietnam to Sep. 06, low 100's, plus options, then expect to work in New Zealand to Aug. 07, mid 180's, plus options 
ENSCO 108  KFELS MOD V-B  400  Under construction     Singapore  1Q 07    
 
ENSCO I  Barge Rig     Total  Low 50's  Indonesia  Apr. 07    
 
 
          Note:  Highlighted/underlined rig names signify changes in rig status information from the previous month.


3