XML 29 R21.htm IDEA: XBRL DOCUMENT v3.23.1
Subsequent Events
3 Months Ended
Apr. 01, 2023
Subsequent Events  
Subsequent Events

Note O – Subsequent Events

 

On April 25, 2023, the Board of Directors of The Eastern Company (the “Company”) approved a plan to close the Company’s Associated Tool Makers Ltd. facility located in Farndon, United Kingdom, which specializes in the design and manufacture of molds for the plastic injection molding industry. The plan is intended to address long-standing profitability issues at the Farndon facility. The plan would include approximately 10 job reductions at the Farndon facility.

 

The Company expects to substantially complete this plan by the end of the third quarter of 2023 and estimates total pre-tax charges associated with this action to be between $3.5 million and $4.5 million, of which $0.4 million to $0.8 million is expected to be cash charges primarily for associate-related and other exit costs, with the remainder representing non-cash charges primarily for accelerated depreciation and other asset-related charges. The Company expects to record the majority of these pre-tax charges and cash outflows in the second quarter of 2023.