Commitments and Contingent Liabilities 
Guarantees 
Indemnifications
In connection with acquisitions and divestitures, the company has indemnified respective parties against certain liabilities that may arise in connection with these transactions and business activities prior to the completion of the transaction. The term of these indemnifications, which typically pertain to environmental, tax and product liabilities, is generally indefinite. In addition, the company indemnifies its duly elected or appointed directors and officers to the fullest extent permitted by Delaware law, against liabilities incurred as a result of their activities for the company, such as adverse judgments relating to litigation matters. If the indemnified party were to incur a liability or have a liability increase as a result of a successful claim, pursuant to the terms of the indemnification, the company would be required to reimburse the indemnified party. The maximum amount of potential future payments is generally unlimited. The carrying amounts recorded for all indemnifications was $31 as of March 31, 2013 and December 31, 2012.

Obligations for Equity Affiliates & Others 
The company has directly guaranteed various debt obligations under agreements with third parties related to equity affiliates, customers and suppliers. At March 31, 2013 and December 31, 2012, the company had directly guaranteed $533 and $535, respectively, of such obligations. These amounts represent the maximum potential amount of future (undiscounted) payments that the company could be required to make under the guarantees. The company would be required to perform on these guarantees in the event of default by the guaranteed party.

The company assesses the payment/performance risk by assigning default rates based on the duration of the guarantees. These default rates are assigned based on the external credit rating of the counterparty or through internal credit analysis and historical default history for counterparties that do not have published credit ratings. For counterparties without an external rating or available credit history, a cumulative average default rate is used.

In certain cases, the company has recourse to assets held as collateral, as well as personal guarantees from customers and suppliers. Assuming liquidation, these assets are estimated to cover approximately 51 percent of the $350 of guaranteed obligations of customers and suppliers. Set forth below are the company's guaranteed obligations at March 31, 2013:
 
Short-Term
Long-Term
Total
Obligations for customers and suppliers1:
 

 

 

Bank borrowings (terms up to 5 years)
$
265

$
84

$
349

Leases on equipment and facilities (terms up to 4 years)


$
1

1

Obligations for equity affiliates2:
 

 

 

Bank borrowings (terms up to 2 years)
182

1

183

Total
$
447

$
86

$
533

 
1 
Existing guarantees for customers and suppliers arose as part of contractual agreements. As of March 31, 2013, approximately $13 of these guarantees relate to customers of the Performance Coatings business, which was sold in February 2013. See Note 2 for additional information.
2   
Existing guarantees for equity affiliates arose for liquidity needs in normal operations.

Imprelis® 
The company has received claims and been served with multiple lawsuits alleging that the use of Imprelis® herbicide caused damage to certain trees. The lawsuits seeking class action status have been consolidated in multidistrict litigation in federal court in Philadelphia, Pennsylvania.

In February 2013, the court granted preliminary approval of a class action settlement. The settlement incorporates the company's existing claims process and provides certain additional relief. The proposed settlement class includes affected property owners and lawn care companies who do not "opt out" of the settlement. DuPont may cancel the agreement if the number of “opt-outs” is unsatisfactory to DuPont. As part of the settlement, DuPont will pay about $7 in plaintiffs' attorney fees and expenses. In addition, DuPont is providing a warranty against new damage, if any, caused by the use of Imprelis® on class members' properties through May 2015. The settlement notification process began on March 25, 2013.   The notice period is scheduled to end on June 28, 2013 which will also be the last day to “opt out” of the settlement or file a new claim. The court has scheduled the final approval hearing on September 27, 2013. In addition, about 95 individual actions on behalf of approximately 195 plaintiffs have been filed in state court in various jurisdictions. DuPont has removed most of these cases to federal court in Philadelphia, Pennsylvania. Once removed to federal court, the individual actions are stayed through September 2013.
In August 2011, the company suspended sales of Imprelis® and in September 2011 began a process to fairly resolve claims associated with the use of Imprelis®. The company believes that the number of unasserted claims is limited due to the fact that sales were suspended in August 2011 and the product was last applied during the 2011 spring application season.

The company has established review processes to verify and evaluate damage claims. There are several variables that impact the evaluation process including the number of trees on a property, the species of tree with reported damage, the height of the tree, the extent of damage and the possibility for trees to naturally recover over time. Upon receiving claims, DuPont verifies their accuracy and validity which often requires physical review of the property.

At March 31, 2013, DuPont had recorded charges of $785 to resolve these claims, which included charges of $35 recorded during the first quarter 2013. It is reasonably possible that additional charges could result related to this matter. While there is a high degree of uncertainty, total charges could range up to $900. Predicting the impact of Imprelis® on living organisms and how those organisms may react over time are significant factors driving the uncertainty of future charges. Imprelis® was applied throughout the United States and the ability of any particular species of tree to naturally recover over time may be different depending on the property's geography and associated climate. The company has an applicable insurance program with a deductible equal to the first $100 of costs and expenses. The insurance program limits are $725 for costs and expenses in excess of the $100. DuPont has submitted and will continue to submit requests for payment to its insurance carriers for costs associated with this matter. The process of seeking insurance recovery is ongoing and the timing and outcome are uncertain.

Litigation
The company is subject to various legal proceedings arising out of the normal course of its business including product liability, intellectual property, commercial, environmental and antitrust lawsuits. It is not possible to predict the outcome of these various proceedings. Except as otherwise noted, management does not anticipate their resolution will have a materially adverse effect on the company's consolidated financial position or liquidity.  However, the ultimate liabilities could be significant to results of operations in the period recognized.  

PFOA 
DuPont uses PFOA (collectively, perfluorooctanoic acids and its salts, including the ammonium salt), as a processing aid to manufacture some fluoropolymer resins at various sites around the world including its Washington Works plant in West Virginia. At March 31, 2013, DuPont has accruals of $15 related to the PFOA matters discussed below.

The accrual includes charges related to DuPont's obligations under agreements with the U.S. Environmental Protection Agency and voluntary commitments to the New Jersey Department of Environmental Protection.  These obligations include surveying, sampling and testing drinking water in and around certain company sites and offering treatment or an alternative supply of drinking water if tests indicate the presence of PFOA in drinking water at or greater than the national Provisional Health Advisory.

Drinking Water Actions
In August 2001, a class action, captioned Leach v DuPont, was filed in West Virginia state court alleging that residents living near the Washington Works facility had suffered, or may suffer, deleterious health effects from exposure to PFOA in drinking water.

DuPont and attorneys for the class reached a settlement in 2004 that binds about 80,000 residents. In 2005, DuPont paid the plaintiffs’ attorneys’ fees and expenses of $23 and made a payment of $70, which class counsel designated to fund a community health project.  The company funded a series of health studies which were completed in October 2012 by an independent science panel of experts (the “C8 Science Panel”). The studies were conducted in communities exposed to PFOA to evaluate available scientific evidence on whether any probable link exists, as defined in the settlement agreement, between exposure to PFOA and human disease.

The C8 Science Panel found probable links, as defined in the settlement agreement, between exposure to PFOA and pregnancy-induced hypertension, including preeclampsia; kidney cancer; testicular cancer; thyroid disease; ulcerative colitis; and diagnosed high cholesterol.

A panel of three medical experts will determine an appropriate medical monitoring protocol, if any, as a result of these findings. If a medical monitoring protocol for any of these diseases is defined, DuPont is required to fund a medical monitoring program to pay for such medical testing. Plaintiffs may pursue personal injury claims against DuPont only for those human diseases for which the C8 Science Panel determined a probable link exists. In January 2012, the company put $1 in an escrow account as required by the settlement agreement. Under the settlement agreement, the company's total obligation to pay for medical monitoring cannot exceed $235. In addition, the company must continue to provide water treatment designed to reduce the level of PFOA in water to six area water districts, including the Little Hocking Water Association (LHWA), and private well users.

An Ohio action brought by the LHWA is ongoing. In addition to general claims of PFOA contamination of drinking water, the action claims “imminent and substantial endangerment to health and or the environment” under the Resource Conservation and Recovery Act (RCRA). DuPont denies these claims and is defending itself vigorously.

At March 31, 2013, 42 lawsuits alleging personal injury and two lawsuits alleging wrongful death from exposure to PFOA in drinking water are pending in federal court in Ohio and West Virginia. This is an increase in pending cases of 17 and one, respectively, over year-end 2012. These cases have been consolidated for discovery purposes in multi-district litigation in Ohio federal court. DuPont denies the allegations in these lawsuits and is defending itself vigorously.

While DuPont believes that it is reasonably possible that it could incur losses related to PFOA matters in addition to those matters discussed above for which it has established accruals, a range of such losses, if any, cannot be reasonably estimated at this time.

Monsanto Patent Dispute
On August 1, 2012, a St. Louis, Missouri jury awarded $1,000 in damages to Monsanto on its claims that the company willfully infringed Monsanto's RE 39,247 patent directed to Roundup® Ready® 1 glyphosate herbicide tolerance soybean seed technology.

Monsanto alleged that by combining Pioneer's Optimum® GAT® trait with Monsanto's patented Roundup® Ready® trait, Pioneer violated its 2002 Amended and Restated Roundup® Ready® Soybean License Agreement and, in doing so, infringed Monsanto's RE 39,247 patent. The company has never sold soybeans containing a combination of the Optimum® GAT® and Roundup® Ready® traits and discontinued in 2011 its commercialization efforts for such soybeans.

In March 2013, Pioneer and Monsanto entered into technology license agreements. As part of those agreements, the company received, among other things, a non-exclusive royalty bearing license in the United States and Canada for Monsanto's Genuity® Roundup Ready 2 Yield® glyphosate tolerance trait and its dicamba tolerance trait for soybeans, post-patent regulatory access and maintenance support for Roundup Ready® 1 glyphosate tolerance trait for soybeans, Genuity® Roundup Ready 2 glyphosate tolerance trait for corn and YieldGard® corn borer insect resistance trait. The agreements require the company to make a series of up-front and variable payments subject to Monsanto delivering enabling soybean genetic material. Total annual fixed royalty payments of $802 contemplated under the arrangement for trait technology, associated data and soybean lines to support commercial introduction are expected to come due in years 2014 - 2017. Additionally, beginning in 2018, DuPont will pay royalties on a per unit basis related to the Genuity® Roundup Ready 2 Yield® and dicamba tolerance traits for the life of the license, subject to annual minimum payments through 2023 totaling $950.

In a separate agreement, the company agreed to dismiss with prejudice its antitrust claims against Monsanto in exchange for a dismissal with prejudice of Monsanto's patent infringement claims and the related damages verdict. Accordingly, as of March 31, 2013 this matter has been resolved, but for the court-ordered sanctions against the company for “fraud against the court.” The court unsealed the order in November 2012. The parties have agreed to present the sanctions and related rulings for immediate appeal.

Titanium Dioxide Antitrust Litigation
In February 2010, two suits were filed in Maryland federal district court alleging conspiracy to fix prices of titanium dioxide sold in the U.S. between March 2002 and the present. The cases were subsequently consolidated and are pending against DuPont, Huntsman International LLC, Kronos Worldwide Inc. and Millenium Inorganics Chemicals Inc. In August 2012, the court certified a class consisting of U.S. customers that have directly purchased titanium dioxide since February 1, 2003. The class seeks injunctive relief and to recover alleged overcharges and treble damages plus attorneys' fees and costs. Jury trial is scheduled to begin September 9, 2013.

The company believes this case is without merit and expects to prevail. Given the inherent uncertainties in litigation, it is reasonably possible that the company could incur losses related to this matter. A range of loss, if any, cannot be reasonably estimated at this time.
Environmental 
The company is also subject to contingencies pursuant to environmental laws and regulations that in the future may require the company to take further action to correct the effects on the environment of prior disposal practices or releases of chemical or petroleum substances by the company or other parties. The company accrues for environmental remediation activities consistent with the policy as described in the company's 2012 Annual Report in Note 1, “Summary of Significant Accounting Policies.” Much of this liability results from the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA, often referred to as Superfund), RCRA and similar state and global laws. These laws require the company to undertake certain investigative, remediation and restoration activities at sites where the company conducts or once conducted operations or at sites where company-generated waste was disposed. The accrual also includes estimated costs related to a number of sites identified by the company for which it is probable that environmental remediation will be required, but which are not currently the subject of enforcement activities.

Remediation activities vary substantially in duration and cost from site to site. These activities, and their associated costs, depend on the mix of unique site characteristics, evolving remediation technologies, diverse regulatory agencies and enforcement policies, as well as the presence or absence of potentially responsible parties. At March 31, 2013, the Condensed Consolidated Balance Sheet included a liability of $443, relating to these matters and, in management's opinion, is appropriate based on existing facts and circumstances. The average time frame, over which the accrued or presently unrecognized amounts may be paid, based on past history, is estimated to be 15-20 years. Considerable uncertainty exists with respect to these costs and, under adverse changes in circumstances, potential liability may range up to three times the amount accrued as of March 31, 2013.