XML 91 R51.htm IDEA: XBRL DOCUMENT v3.20.2
Regulatory Matters (Regulatory Matters Narrative - Duke Energy Florida) (Details) - Duke Energy Florida
$ in Millions
Jul. 01, 2020
USD ($)
plant
MW
Jun. 30, 2020
USD ($)
May 19, 2020
USD ($)
Apr. 02, 2020
USD ($)
Dec. 31, 2019
USD ($)
Dec. 19, 2019
USD ($)
Nov. 22, 2019
USD ($)
Apr. 30, 2019
USD ($)
FPSC                
Public Utilities, General Disclosures [Line Items]                
Accelerated fuel cost refund       $ 78        
Hurricane Michael storm damage                
Public Utilities, General Disclosures [Line Items]                
Estimated storm costs - capital and operation maintenance   $ 163     $ 204      
Hurricane Michael storm damage | FPSC                
Public Utilities, General Disclosures [Line Items]                
Estimated storm costs - capital and operation maintenance               $ 223
Amount of recovery costs sought     $ 188       $ 191  
Requested supplemental true-up     $ 3          
Hurricane Dorian storm damage                
Public Utilities, General Disclosures [Line Items]                
Estimated storm costs - capital and operation maintenance   $ 95     $ 167      
Hurricane Dorian storm damage | FPSC                
Public Utilities, General Disclosures [Line Items]                
Estimated storm costs - capital and operation maintenance           $ 169    
Subsequent event | FPSC                
Public Utilities, General Disclosures [Line Items]                
Number of solar plants | plant 10              
Generation capacity (MW) | MW 750              
Subsequent event | Solar Project                
Public Utilities, General Disclosures [Line Items]                
Estimated cost of facilities $ 1,000              
Estimated cost of facilities period 4 years